- Oracle (ORCL) shares fell 5.4% in premarket trading after the company reportedly sent a force majeure notice to the developer of its New Mexico AI data-center project.
- The notice is seen as a risk-management move amid mounting permitting, power-supply, financing, and legal obstacles that threaten the project's timeline and cost.
- Investors are concerned that the project, known as Project Jupiter, could become more expensive, delayed, or scaled back, pressuring Oracle's capital efficiency as it ramps up AI infrastructure spending.
Oracle Corp. shares dropped 5.4% in premarket trading on Tuesday after Bloomberg reported that the company has issued a force majeure notice to the developer of its massive New Mexico AI data-center project, a move that underscores the growing challenges facing the $165 billion campus.
The notice, which typically invokes extraordinary circumstances outside a party’s control to excuse or defer contractual obligations, is seen as an effort to limit Oracle’s exposure to costs associated with the controversial project. According to people familiar with the matter, the company is reassessing its commitments as permitting, power-supply, and legal hurdles mount.
Project Jupiter, located in Doña Ana County near Santa Teresa, has been billed as a cornerstone of Oracle’s AI infrastructure buildout. But the project has been plagued by delays and opposition. A roughly 18-mile natural gas pipeline, known as the Green Chile pipeline, which would supply up to 400 million cubic feet per day, was pushed back from August 2026 to February 2027 after state land-access setbacks and additional environmental review requirements.
The project’s power strategy has also come under fire. New Mexico’s land commissioner twice rejected a key state-trust-land crossing for the pipeline, citing emissions and water-supply concerns. Separately, the New Mexico Supreme Court paused emergency groundwater-well drilling and air-permit proceedings for parts of the project. These setbacks have raised doubts about whether the campus can secure the necessary power to operate on schedule.
Financing conditions are showing signs of strain. Recent reports indicated that approximately $18 billion in loans tied to an Oracle-leased New Mexico data-center development were being quoted at 89–91 cents on the dollar, suggesting lenders are demanding a discount for perceived project and credit risk.
“Force majeure is a standard contractual mechanism, but in this context it signals that Oracle is trying to protect itself from a project that is becoming increasingly unpredictable,” said a person familiar with the negotiations, who asked not to be identified. “It doesn’t mean the project is dead, but it certainly raises the stakes.”
Oracle has been investing heavily in AI infrastructure to meet soaring demand. In fiscal 2026, the company reported record revenue of $67.4 billion, up 17% year over year, with cloud revenue reaching $34 billion, up 39%. Its cloud infrastructure segment grew 93% in the fourth quarter alone. Remaining performance obligations stood at $638 billion at the end of the fiscal year, a sign of strong contracted demand.
But the capital intensity of that buildout is weighing on the balance sheet. Oracle spent $55.7 billion on capital expenditures in fiscal 2026, above its prior guidance of $50 billion, and has signaled even higher spending in fiscal 2027. Operating cash flow was about $32 billion, creating a significant funding gap that makes the company reliant on external financing and partner contributions.
The project’s troubles echo broader challenges across the AI infrastructure landscape, where hyperscale data centers are competing for scarce power and water resources. Utilities and pipeline developers are facing similar permitting and litigation risks, and the outcome of Project Jupiter could have implications for other large-scale AI campuses.
A spokesperson for Oracle declined to comment on the force majeure notice. The developer of the project could not be immediately reached for comment.
Analysts said the premarket selloff reflects concerns that Oracle’s AI ambitions may be harder to execute than anticipated. “The market is pricing in the risk that Project Jupiter becomes a drag on returns rather than a growth engine,” said an analyst at a major investment bank, who was not authorized to speak publicly. “Oracle needs to demonstrate that it can navigate these obstacles without derailing its broader AI strategy.”
It remains unclear whether construction at the site will continue. Oracle has previously maintained that Project Jupiter was on schedule despite the pipeline delay. The force majeure notice may be a negotiating tactic to reallocate risk with its partners, but it could also presage a more significant retrenchment.
In the short term, investors will be watching for the developer’s response, any revised completion milestones, and Oracle’s next public comments on the project. The outcome will be closely watched as a bellwether for the AI infrastructure buildout, which is increasingly colliding with the slow, complex realities of energy and land-use permitting.
Correction: An earlier version of this article misstated the date of the pipeline delay. It was delayed from August 15, 2026, to February 1, 2027, not from August 2025.