Operator
Ladies and gentlemen, good day and welcome to the Adani Enterprises Q2 FY27 earnings conference call. As a reminder, all participant lines will be in the listen-only mode, and there will be an opportunity for you to ask questions after the presentation concludes.
Should you need assistance during the conference call, please signal an operator by pressing "*" then "0" on your touch-tone phone. I now hand the conference over to Mr.
Alok Deora. Thank you, and over to you.
Alok Deora
Thank you. Good evening, everyone.
On behalf of Motilal Oswal, I welcome you all to the 2Q FY27 earnings call of Adani Enterprises. We have with us the senior management from the company led by Mr.
Arun Bansal, Chief Executive Officer, Adani Airport Holdings; Mr. Muralee Krishnan, Chief Executive Officer, Adani New Industries, Solar Manufacturing; Mr.
Rajesh Poddar, CFO, Adani Airport Holdings; Mr. Manan Vakharia, Head of Finance, Adani Enterprises; and Mr.
Jitendra Kalia, Investor Relations, Adani Enterprises. I would now hand over the call to Mr.
Arun Bansal to provide opening remarks, and then we can take up the Q&A. Thank you, and over to you, sir.
Arun Bansal
Thanks, Alok. Good evening, everyone.
Thank you for joining us today for Adani Enterprise earnings call for the quarter and half year ended September 30th, 2026. AEL's portfolio comprises primarily of infrastructure focused businesses, which spans across energy and utilities, transport and logistics, and primary industry.
It is my pleasure to inform you that AEL achieved credit rating upgrade to [AAA?] , AA Stable by CARE during the first week of October 2026, its highest ever long-term rating in its credit history.
This upgrade serves as an independent validation of AEL's disciplined capital management and tight fiscal prudence. As we informed in our earlier discussions, AEL's current fiscal results will reflect value unlock from investments made over the last few years and moving progressively from build-out phase to value realization phase.
AEL has reported its highest ever half yearly EBITDA of ₹11,958 crore. The strong EBITDA delivered is testimony of incubation business model and strength of our diversified business platform, backed by strong operating fundamentals, increasing asset maturity, and the ramp-up of newly commissioned Adani New Industries module line capabilities.
AEL is now well-positioned to sustain this growth trajectory going forward. Moving to our half yearly financial performance, on consolidated basis, total income increased to ₹71,569 crore, an increase of 62% year-over-year.
EBITDA increased to ₹11,958 crore, an increase of 56% year-over-year. Continuing profit before tax increased to ₹3,297 crore, an increase of 45% year-over-year.
Adani Airport Holding Limited EBITDA reported growth of 52% year-over-year to ₹3,275 crore. KCL copper EBITDA reported EBITDA of ₹2,033 crore.
Now let me move to business-wise update. Our data center business: AdaniConnex has signed up a new hyperscale contract of 240 MW capacity, taking cumulative contracted capacity to 1.2+ GW.
During the quarter, we handed over additional 29.2 MW data center to customers, taking operational capacity to 94.6 MW. Moving to airport business: Adani Airport is one of India's largest private airport platforms, operating a portfolio of eight airports, including the greenfield Navi Mumbai International Airport, and contributing approximately 23% of India's passenger traffic and 29% of country's air cargo volume, underscoring our scale and strategic importance in India's aviation ecosystem.
Adani Airports delivered a resilient performance during first half of this fiscal and achieved highest ever half yearly EBITDA of ₹3,275 crore, which is close to full year EBITDA of financial year '25. This growth is achieved despite industry headwinds like elevated fuel prices and airspace disturbances, which have weighed negatively on passenger traffic.
The effort put in over the last few years in developing non-aero strategy and ecosystem have provided resilience in this atmosphere. Our greenfield development of Navi Mumbai International Airport commenced its international operations effective 15th July '26.
Indian domestic airlines IndiGo, Air India, and Akasa have recently announced their operational plans to commence international operations and progressively expand from Navi Mumbai Airport. Moving on to financial and operational bank performance during Q2, financial year '27: We handled passenger traffic of 21.3 million passengers, total income of ₹3,786 crore, up by 20% year-over-year, EBITDA of ₹1,641 crore, up by 55% year-over-year, and aero and non-aero revenue delivered year-over-year growth of 9% and 57% respectively.
During the quarter, we added eight new routes and four new airlines. If I move to mining services portfolio: During the quarter, we dispatched volume up stood at 10.7 million metric ton, while revenue stand at ₹998 crore and EBITDA of ₹407 crore.
In integrated resource management business portfolio: During the quarter, trading volume stood at 7.4 million metric ton, and revenue stood at ₹7,169 crore, and EBITDA of ₹654 crore. In copper business, we are now seeing capacity ramp-up.
During the quarter, copper sales volume of 80.6 kt with capacity utilization increased to 64%. Revenue increased to ₹14,843 crore, and EBITDA increased to ₹1,283 crore.
With this, now I handover the call to my colleague Muralee Krishnan, CEO of Adani Solar. Over to you, Muralee.
Muralee Krishnan
Thank you, Arun. Good evening, ladies and gentlemen.
Adani New Energy ecosystem is developing an end-to-end integrated ecosystem for manufacturing solar modules and wind equipments. As all of Adani Solar has featured in the elite list of top 10 global solar module manufacturing, and Adani Wind became the only Indian company in top 15 global wind turbine manufacturers.
I'm happy to inform you that we have commissioned the remaining module line capacity of 4.3 GW on 31st of August 2026, completing our expansion to 10 GW module line capacity. We are on schedule to commission the solar cell line of 6 GW by end of this financial year.
During the quarter, domestic module sales have increased to 1,478 MW, up by 35% year-on-year basis. This demonstrates strong demand of Adani solar modules in domestic market, which has fully absorbed the export intake.
Now moving into the financials and operational performance of Q2 FY27: The module sales was 1,478 MW, up by 35% year-on-year. Wind turbine sales was to 35 sets, up by 25% year-on-year.
Total income stood at ₹3,669 crore, with an EBITDA at ₹1,094 crore. Now the session is open for question and answer.
Operator
Thank you. We will now begin the question and answer session.
Anyone who wishes to ask a question may press "*" and "1" on your touch-tone telephone. If you wish to remove yourself from the question queue, you may press "*" and "2".
Participants are requested to use handsets while asking a question. Ladies and gentlemen, we'll wait for a moment while the question queue assembles.
We have the first question from the line of Manish A. Somaiya from Cantor.
Please go ahead.
Manish Somaiya
Good evening. Can you hear me?
Operator
Yes, we can hear you, Manish.
Manish Somaiya
Wonderful. I wanted to ask my first question on the airport business, specifically on Navi Mumbai.
Perhaps if Arun can talk about the key traffic, yield, and cost milestones over the next 12-15 months that we should be thinking about as that airport ramps up. What are sort of some of the meaningful contributions to profitability and cash flow that we should think about?
Arun Bansal
Now, thanks for your question. NMIAL, as I said in my commentary, we started the commercial international operations from 26th of July.
As you might have seen recently, together with Indian carriers IndiGo, Akasa, and Air India, we have announced the new international routes. Actually, IndiGo has announced 12 new routes from Navi Mumbai starting from December until up to April, summer schedule '27.
Air India Group has announced seven international routes from Navi Mumbai, and Akasa has announced one additional. That makes 19 international routes.
One is existing from Navi Mumbai. Domestic also we see a proportionate growth.
Our guidance is that we will exit next financial year with full capacity at Navi Mumbai. Navi Mumbai, as the capacity we can handle is max 20 million, which is 5 million international and 15 domestic.
We will exit next financial year, i.e., Q1 2028, running with a run rate of 5 million per quarter.
Manish Somaiya
That's helpful. Then on data centers, it's obviously great to see the tie-up with a new hyperscaler.
The capacity is now 1.2 GW+. If you guys can help us understand how we should think about the commissioning schedule and what level of equity and CapEx we should be kind of baking in as we think about that?
Manan Vakharia
Hi Manish.
Arun Bansal
Manan, over to you.
Manan Vakharia
Yeah. In terms of data center, we will stick to what we discussed in terms of our earning call discussion during Q1, where we are expecting in the range of 120 to 150 MW of operational capacity as a capacity of when we exit FY27, the current fiscal.
Over next 12 to 18 months, we will significantly ramp up all the remaining projects, and we should be expecting close to 500 MW of operational capacity, which we will start billing to the customers. In terms of the CapEx and equity requirement is something where we expect this project to be funded approximately 20-80 to 30-70 kind of scenario.
We'll have the same CapEx numbers as generally are there for any other players, because we are primarily in the core and shell, MEP, and all the structure and not a cool play where we install our servers also because that is in the scope of customers.
Manish Somaiya
Thank you, Manan. Then just lastly on roads for me.
Now that Ganga Expressway is operational, how should we think about the recurring toll and annuity income becoming sort of the dominant force when it comes to earnings? Because that's something that I think we have yet to see.
I'm hoping you can help us with some of the key milestones we should be watching for over the next few quarters.
Manan Vakharia
I think starting last quarter, we have fairly entered into an area where the numbers in the P&L or the reported numbers reflect the annuity income as well as ongoing toll income. What we should expect going forward is the increase or the optimum utilization of the roads where the toll incomes are to be generated.
As the traffic grows and as the traffic picks up across the lines of newly commissioned toll roads, including Ganga Expressway, you will see those ramp-up number coming in. When you compare year-on-year, because of how the Ind AS accounting works for the service concession accounting, you will see some kind of variability in the revenue numbers.
I understand pretty much that is your questions. Otherwise, you will see the normalization has already happened, and you will see this continue for a few quarters in the next period.
As the construction starts for the new projects, you will see that again being reflected in the P&L.
Manish Somaiya
Okay. That's super helpful.
I'll get back in the queue, and I appreciate the time. Thank you.
Operator
Thank you. We have the next question from the line of Mohit Kumar from ICICI Securities.
Please go ahead.
Mohit Kumar
Yeah. Good evening, and thank you for taking my question.
My first question is on the Bangalore tunnel project. I think we were L1.
Is there any update on that project as you can share?
Manan Vakharia
No, it is at the same level. That is what we know from the authorities that we are L1, and there's no further development there as of now.
Mohit Kumar
Understood. Coming back, one suggestion for the road EBITDA, of course we understand that we are doing SCA accounting.
Is it possible to share the operational EBITDA going forward, given that of course foremost our last three projects have got operational for Ganga Expressway? Is it possible to share the operational EBITDA going forward in the PPT?
That'll be helpful for us. Yeah.
Manan Vakharia
Sure, Mohit. We can include this.
For your reference and for the benefit of everybody, we will share the numbers over the call as well. Our EBITDA for roads business for Q2 is ₹354 crore, and Q1 was ₹288 crore.
That takes us to half-yearly number of around ₹642 crore of EBITDA for roads.
Mohit Kumar
Understood. Going back to the airport business, I think we were expecting to commence the work on phase two of Navi Mumbai.
Can you just update us on that, given that of course the traffic is below par? Are we postponing that CapEx?
The second question on the airport business is, of last year, if you look at the non-aero business, I think we took over the ground handling, I think somewhere in Q1 FY26, right? That particular revenue is not present in the base quarter, while you see that number is present in the Q1 and Q2 FY27.
Can you help us understand that line item?
Arun Bansal
I'll take the first question, Arun here, and then Rajesh will help you with the second question on exact numbers. Phase two of Navi Mumbai has already kicked off.
We have already onboarded the international consultant, and the design work is ongoing. We have also in the process of finalizing the GC contractor, which will be onboarded very, very soon.
Phase two of Terminal 2 of Navi Mumbai, the actual work will start within the month of November this year.
Mohit Kumar
Understood. On the ground handling, sir?
Rajesh Poddar
Yes, in case of ground handling, Rajesh here. In case of ground handling, we had commenced the operations at Mumbai, Ahmedabad, Navi Mumbai through 100% subsidiary AGH Port.
During this particular H1, we have earned a revenue of around ₹339 crore for a six months period.
Mohit Kumar
This was not present last fiscal completely, is it right?
Rajesh Poddar
It was. Rajesh.
Manan Vakharia
Mohit, the entity was acquired and sourced somewhere in the middle of November. It actually was present for approximately three or four months in the last financial year.
Yes, if you look at the half year number, it was not materially there.
Mohit Kumar
Understood, understood. My another question on the solar and wind.
Sir, on this particular quarter, do you have any idea how much is sold in the rooftop? Are you thinking about setting up ingot and wafer now?
Muralee Krishnan
There are two questions. One is that on the rooftop, actually 56% of our sale was into the rooftop market.
In terms of ingot wafer, I would say that we already have 2.2 GW of ingot wafer capacity, and the balance capacity will come up by 2028, which we are already working on. The engineering work is already started.
That will well align with the ALMM 3 policy.
Mohit Kumar
You have commenced work on the balance 8 GW of ingot and wafer. Is that understanding correct, sir?
Muralee Krishnan
It will be actually a bit more than 6 GW, because if you look at technically, the yield factor is approximately around 87% to 88% to the nameplate capacity world over. Accordingly, the capacity installed will be slightly higher than the cell capacity what we have already in hand.
Mohit Kumar
Understood, sir. Is it possible to share the solar order book and the wind order book at the end of Q2?
In general, I can only say that
Muralee Krishnan
our capacity is already booked for it, both for wind as well as solar. We will not be in a position to give you the exact numbers at this point in time, but I can assure you that the order book is already full.
Mohit Kumar
Understood, sir. Last question, sir, how much was CapEx done in H1, and is it possible to give us the broad breakup of the CapEx segment-wise?
Muralee Krishnan
Mohit, what we have done is we have included standard FAQs as a part of our earnings presentation where we have included full breakup in the appendix for the CapEx share. Sure,
Mohit Kumar
sure. Understood.
Sir, one more question if I may ask, in your PPT of data center, I think there was a contract reservation, right, which was 1.2 GW? I think this was shared, I think, by end of F26.
Do you have similar number by end of Q2 FY27?
Muralee Krishnan
Sorry, come again?
Mohit Kumar
In a investor PPT, which you had shared earlier, there was a data center capacity of 1.2 GW which were under contract reservation. Can you help us understand the definition of contract reservation, and what is that number at the end of Q2 FY27?
Muralee Krishnan
You can refer our data center slide, what we have included as a part of our earning presentation. We are constructing data centers of 1.4 GW capacity already.
Those are at a various stages. Out of these, the capacity of 1.2 GW is already tied up and is at a different level of implementation and the project construction.
The remaining capacity is open, which can be taken up by anybody.
Mohit Kumar
Understood. Maybe I'll take it offline.
I'll speak to sir later. Thank you.
Thank you for answering my question. Thank you.
Bye-bye.
Operator
Thank you. We have the next question from the line of Prateek Kumar from Jefferies.
Please go ahead.
Prateek Kumar
Good evening. Congrats for great set of results.
My first question is on airport business. Can you discuss progress on real estate CapEx and any specific milestone you're looking at by end of FY27, FY28 for city side development?
Rajesh Poddar
City side developments, we have signed the contract, the HMA, for all the hotels we are building basically with our partners. The work is ongoing at five assets: Mumbai, Navi Mumbai, Ahmedabad, Lucknow, and Guwahati.
The work at Jaipur will start very, very soon. The phase one, as I call it, we will be live at Ahmedabad by October '29, and Mumbai, Navi Mumbai by March 2030.
Then we are undertaking some major CapEx project on aeronautical side. As I said before, we are building a completely new terminal, Terminal 2 at Navi Mumbai.
We are doing a redevelopment of Terminal 1 at MIAL, which will start from Q1 next year. We are building a completely new integrated terminal at Ahmedabad in line with Commonwealth Games, which Ahmedabad city will host in October 2030, so that terminal will be ready.
We are doing some minor additions of capacity at Terminal 2 in MIAL, building additional capacity at Trivandrum, and a new terminal at Jaipur. There are a lot of CapEx, heavy CapEx items, which are work in progress from now until 2029-2030.
Prateek Kumar
Sure. In the data center business, can you discuss the recent joint venture Jabil-Adani, Jabil partnership, what is the scope of that business and Is this a new CapEx with the company's envisaging?
Other question on data center is we do read about a lot of position for data center setup, particularly in Vizag and Navi Mumbai, and where we are looking to setup large projects. Can you discuss status of land acquisition or whatever is required for this project which just suggest that our projects are on time and we are looking at 2 GW capacity by probably FY30?
Manan Vakharia
Hi Prateek, thank you. You have two parts in your data center questions.
I'll take first on Jabil. Yes, the present joint venture which is with EdgeConnex is a completely a data center play in terms of it operates in building and constructing the data centers, core and shell, MEP solutions, and other related stuff, which you know about this.
What goes inside the data center is generally within the scope of customers. Now what we seek to do with Jabil is, and it's a completely new development different and separate from AdaniConnex, where Adani Enterprise and Jabil are looking to manufacture the AI racks and the data servers and related equipments, and the manufacturing facility will be set up in the country.
It is still at an MOU stage, and we are looking to finalize the definitive agreement over a few months. Once we have those signed, we will come up with the proper disclosure in line with the regulatory requirement, and we'll have the details included in our CapEx and other segments.
That was part one of your question. On part two, yes, the various data center locations which we have defined in our earnings presentation, we have access to majority of those lands, and are already acquired and or are in the very advanced stage of completing the acquisition.
We are very confident that these projects will be completed as planned and as envisaged.
Prateek Kumar
Just to confirm, you said operational capacity moves from current 95 to 120-150 by '27, and 500 by FY28. That the number you said?
Manan Vakharia
500 over next, yeah, 18 months, yeah, practically yes.
Prateek Kumar
Sure. On road segment, the performance or progress or ramp-up at the new projects seems a bit slow.
Is that underwhelming versus company's own estimates, and how do you see kind of progressing on a quarterly basis?
Manan Vakharia
I think it is progressing well, but they are slightly off the mark where we would otherwise like those numbers to be in terms of the capacity ramp-up at the toll projects. This is practically Q2 being seasonally rainy season plus the heavy floods and other situation in the north part of the country.
We will discount that, but as we speak today, we are seeing a good progress and the increase towards what we are expecting the number to be. Yes, it's slightly off the mark currently, but yes, we will catch up in next two quarters.
Prateek Kumar
Last two questions. Firstly, on ANIL, we have commissioned new capacity of module.
What is the run rate of volumes with the significant increase in capacity which we have now over the next few quarters?
Manan Vakharia
We are expecting about 2 GW for the next quarter, and that will be the run rate at which we will be going with the new capacity coming in.
Prateek Kumar
Thank you, sir. In this, what is the mix of volumes, like rooftop or to captive volumes?
Will it significantly increase to Adani Green, or how do you expect to sell this volumes?
Manan Vakharia
As I have already mentioned previously that the capacity for the cell is expected to be commissioned during this financial year towards the back end of this financial year. As this cell capacity coming in, actually the DCR content will be increasing, and that will increase the rooftop because that requires the DCR requirements.
We will be also having OCR capacity which will be used for the captive in the next two quarters considerably.
Prateek Kumar
Sure. Last question on mining service and IRM: These two segments have also seen slower volumes recently.
How should we look at their annual volumes for these two segments?
Manan Vakharia
I think seasonally these two quarters are comparatively lower, but we expect them to grow from here in the remaining two quarters, and we should be at least 10% to 15% higher than where we ended last year.
Prateek Kumar
Sure, thank you for answering all my questions.
Manan Vakharia
For mining services particularly. Coal trading or the IRM is typically it's more of a market-driven thing.
It will be difficult to give you any outlook given the cold shortage situation in the country.
Prateek Kumar
Sure, thank you all and for answering all my questions.
Operator
Thank you. Participants who wish to ask a question may press "*" and "1" on your touch-tone telephone.
We have the next question from the line of Biplab Debbarma from Antique Global. Please go ahead.
Biplab Debbarma
Good evening, everyone, and congratulations on the excellent numbers. My first question is on the non-aero revenue that saw significant year-on-year jump.
Could you please highlight what led to such significant jump in non-aero revenue?
Arun Bansal
Thanks for the question. Non-aero, our strategy has been threefold basically.
Number one, we are heavily investing in digitization. We are working with Adani One app, which we have revamped to focus only on airports, and hence we are able to increase the penetration year-over-year.
This quarter, we had almost 25% of our non-aero transactions happened over digital. As a result of that, we are able to increase the average transaction value per passenger.
We are able to increase the penetration. The third thing is we are able to premiumize most of our shops.
We have brought in new lounges on board, and of course, Navi Mumbai initial ramp-up also helped because Navi Mumbai there was no non-aero revenue last year. Combination of all those has helped, and partly also the ground handling services, as one of the colleague asked.
There was no ground handling last year, which got incorporated this year. Multiple factors contributed to a strong non-aero growth.
Biplab Debbarma
Okay. Now, Mr.
Operator
Mr. Biplab, request you to come kindly closer to the microphone, as we are unable to hear you very clearly.
Biplab Debbarma
Okay. Hello, is it okay now?
Operator
This is much better, yes.
Biplab Debbarma
Thank you. My second question is on the CapEx commitment.
You have quite significant CapEx expected in airports, in data centers, I think even in defense. Could you give us some kind of color on the CapEx commitment over the next three, three to five years, and which business segment will have significant CapEx?
That's my second question.
Manan Vakharia
Hi Biplab. We have given the CapEx which is already incurred as a part of our standard details in the presentation itself.
In terms of the outlook, we will stick to what we outlined in our earnings call during Q1. We expect to do the CapEx at a run rate of around ₹40,000 crore.
We may be somewhere in the ₹35,000 to ₹40,000 crore, and which is a run rate we expect to continue over next couple of years. Yeah, ₹35,000 to ₹40,000.
The heavy lifting will be done obviously by airports, data center, and PVC.
Biplab Debbarma
That's great. Just wondering, sir, you had an excellent result, and what kind of EBITDA do you think in FY27 we'll end up with, and the kind of margin that we think that we'll do in FY27, '28?
Manan Vakharia
I think, Biplab, we refrain from giving any specific financial guidance, my apologies for not being able to answer this.
Biplab Debbarma
Yeah. That's fine.
Thank you, and all the best. Congratulations.
Operator
Thank you. We have the next question from the line of Alok Deora.
Please go ahead.
Alok Deora
Sir, good evening and congratulations on decent numbers. Sir, just had couple of questions.
The copper business has seen significant traction. Do we see this run rate kind of continuing or would we even see better run rate in coming quarters?
That is question one. The second question is that we have been seeing that airlines being a little hesitant to move from that T1, T2 airport to Navi Mumbai.
What kind of implications can it have on us or if you can just throw some light on that or is there any impact at all?
Arun Bansal
Let me answer the airline question, and then Manan, my colleague, will answer the copper question. Airlines, of course, this is a very consultative and long-drawn process where we need to get the confidence of airline that infrastructure is ready at Navi Mumbai, and it's always happens whenever new infrastructure comes in.
As you would have seen on this Sunday and Monday between three domestic carriers, we have announced the movement of between those three, 18 international flights from existing Mumbai to Navi Mumbai that cater for roughly yearly volume of 3 million, and we are in discussion with more airlines to move the traffic for us to be able to redevelop the T1. We are fairly confident, as I said earlier, that we will end financial year '27, '28 with a run rate of 20 million, which is a peak capacity of Navi Mumbai.
Over to you, Manan, for copper question.
Manan Vakharia
Thank you, sir. Hi, Alok.
We have two very good quarters in terms of Q1 and Q2, and the Q2 has been very good. If you look at the margins that we make on our revenue, EBITDA as a percent of revenue, it has been around 7% to 8.5% is the range where we have operated during.
On a long-term basis, our estimate is because this is very a commoditized business and the prices have ramped up in some of the byproducts like sulfuric acids. That is something which have contributed to the good set of numbers.
On a long-term basis, yes, our utilization of the plant and the ramp-up will increase from 64% in Q2 to around 80%-85% as we close this current financial year. The absolute number will definitely increase in terms of revenue, but our operating range for current fiscal may be slightly higher, but yes, on a long-term basis, it will be around 4% to 6% is the range where we will operate as a margin.
Yes, as we increased our plant utilization, the absolute number can be around the same number where we are.
Alok Deora
Got it, sir. Sir, just one follow-up on the airlines answer which you had given.
Just wanted to understand if there is any delay in remaining airlines willing to shift the operations, does it have any implications on us or it really does not change anything as far as we as an airport operator is concerned?
Arun Bansal
No, the timeline to start the redevelopment or demolition part of T1 is fixed. We will start from summer schedule, which is April 2027.
Airlines will have to make its choice, certain airlines, not all. Either they move to Navi Mumbai or temporarily stop flying to Mumbai.
I'm mainly talking about international airlines. There are very few discussions left, and I'm fairly confident that collaboratively in next 4 months we would be able to come to a conclusion with those airlines also.
There might be one or two airlines who decide not to operate from Mumbai for couple of years, but that will have almost no impact on the overall passenger count.
Alok Deora
Got it, sir. That's very helpful.
Thank you, sir. All the best.
Operator
Thank you. We have the next question from the line of Prateek Singh from IIFL Capital.
Please go ahead.
Prateek Singh
Hi, good evening. Thanks for the opportunity.
The first question is on the solar business. Just looking at it, it looks like realizations have fallen on a Q-o-Q basis, but EBITDA margins or EBITDA per unit have gone up.
What are the key two, three parameters which are driving it?
Manan Vakharia
If you look at the Q1 results what we have given, as well as in the earnings call, we mentioned that we have close to some of the advanced authorizations, which is approximately around ₹89 crore impact that has come up. That is one of the main reason for this impact.
Does it answer your question?
Prateek Singh
Understood. Now second on the data center business: As you are incrementally signing pre-lease contracts with multiple hyperscalers sequentially every quarter, on a leg-to-leg basis, I understand it might be difficult, but on a leg-to-leg basis, are you seeing an increase in rental rates over time in dollar terms?
Manan Vakharia
We can get you the specific details and come back on this, but broadly there have been some increase in the rates over last 6 months, but they are not material in terms of where we are looking at those numbers. Broadly the ROCE or the return on capital which we were making earlier are stable in terms of the data center that is our scope of work in the AdaniConnex.
Prateek Singh
Understand. Given that we lock in capital 60 to 80 crore per megawatt and we have seen commodity price inflation, there is a tightness in equipment supply as well, there might be a risk that CapEx per megawatt would be going above what we earlier thought maybe 6, 7 months back.
Is this something when we negotiate with hyperscalers, they agree and they agree to higher rates or we are still in the process where we want to lock in as much capacity as possible and at slightly higher rates than needed? See,
Manan Vakharia
when I answered you earlier, what I meant was we protect the return on capital employed that we want to make as a part of this business. Wherever we are seeing the increased CapEx, that will be factored in when the billing is considered for the new sign-off or the new sign-up of the project which we are doing.
Given that the discounting for that, everything the rates are more or less stable in the broad same range where we were operating earlier.
Prateek Singh
Understood. My third question is on the copper business.
We have been hearing a lot of these TC/RC are negative, availability of concentrate is very tight globally. Have you been facing any issues sequentially in procuring supply or things are fine right now and we are able to procure supply at decent costs?
Manan Vakharia
Far as the procurement of raw material is concerned, we have not seen any significant challenge in terms of what we are hearing otherwise in the market, because we have some of the long-term contracts tied up to a significant part of our requirement. That insulates us from the such variations in the market.
As of now, we have not seen any situations where we are not able to procure the copper concentrate.
Prateek Singh
Thanks. Just two bookkeeping questions very quickly.
Your investments in JVs and associates is around ₹2,400 crore in first half, similar level which we did in entire FY26. Is safe to assume it's largely data centers?
Manan Vakharia
It's primarily data center, yes. You are saying investment in equity accounted investments, right?
Prateek Singh
Correct.
Manan Vakharia
That is data center.
Prateek Singh
Okay. The last question, I can take it offline also.
The other expenses line item in our P&L at ₹6,500 crore this quarter is the lowest in 3 years. What exactly is driving it?
Manan Vakharia
That will boil down to again the Ind AS accounting of the service concession contracts where the construction of road activities are generally passed through P&L. That's why you see the P&L bloated to the extent of revenue and expenses both, because the construction expenses are passed through your P&L.
That is something which is causing the variation in the other expenses line.
Prateek Singh
Oh, very well. That explains it.
Thanks. Thanks a lot and all the best.
Operator
Thank you. We have the next question from the line of Kartik Kohli from Kotak Securities.
Please go ahead.
Kartik Kohli
Hello, sir. Thank you for taking my question.
My question is more related to non-aero part where we are seeing very strong growth. Is there an element of fixed portion of this non-aero revenue being accounted for which is related to new shops being opened, let's say, in Navi Mumbai Airport or say the newer renovated shops open in Mumbai Airport?
Is there a fixed element to this which is contributing to the growth on a Y-o-Y basis? That'll be my first question.
Arun Bansal
No, thanks for the question. There is one element which was specific to Q2, and that is the new hangar sale we have done at Navi Mumbai, which got recorded in Q2 financials.
Rest all the new opening of shops, new lounges, everything is a recurring business which will continue. Understood.
Kartik Kohli
My second question is on data centers. It is more on a broader business sense.
We wanted to understand that since you're signing up with more hyperscale partners, some of them do
Manan Vakharia
You are not clearly audible. Hi, Kartik.
You are not clearly audible.
Operator
Mr. Kartik, request you to kindly come closer to the microphone so that we can hear you loud and clear.
Kartik Kohli
Sure, is this better?
Operator
Yes, we can hear you now.
Kartik Kohli
Sorry. The last thing on data center, we wanted to understand from a broader business perspective, now that you're signing contracts with a lot of hyperscalers across the globe and a lot of these players have undertaken a lot of debt.
Is there a fail-safe in your agreement with such hyperscalers in terms of take-or-pay agreements and any such protections that would allow you to recoup at least part of the revenues if such hyperscaler customers end up not taking up capacity in the event of their at least on their individual finance is not working out? Is there a fail-safe for that?
Manan Vakharia
I think it is there as a part of normal contractual commitment. It is always there.
There are safeguards and the guardrails which are built out in any agreement, those general contractual guardrails are there. On specifics of take-or-pay, I think we will have to check and come back after the contract and the legal review, yeah.
Kartik Kohli
Understood. Secondly, on the services business within AdaniConnex, just wanted to understand what sort of services are being envisaged there and what sort of contribution to overall margins that can come from there?
Is there a sense we can get here?
Manan Vakharia
You said AdaniConnex, right?
Kartik Kohli
Within the business, there is a managed service element and O&M element. Just wanted to get a sense of what sort of EBITDA contribution or at least on our margin contribution that can come from there.
Manan Vakharia
I think we have not even or publicly disclosed as a part of our earning presentation the data center number yet, which we plan to do somewhere in towards the end of the year. We will have the financial disclosure coming up then.
I think that is where we will try to include those breakups as well. Largely, the majority part of the revenue and the EBITDA will flow from the lease rental kind of mechanism where the offtake is taken up by the hyperscalers.
Kartik Kohli
Understood. Just to slip in one last question, because you mentioned on Kutch Copper that a major chunk of your raw material from the perspective of the copper business is already taken care of, could you specify to what degree that you have a contract in place for your capacity utilization?
Manan Vakharia
In terms of offtake or the procurement?
Kartik Kohli
Both offtake and procurement, whatever numbers that can be provided.
Manan Vakharia
Yes. In terms of offtake, if you really look at, we have two joint ventures which are in-house in terms of the copper tube.
That gives us assurance of the offtake for around 12% to 15% of our capacity. Excluding that, copper is something which gets imported in the country.
We are always demand-heavy country against the supply available in the country. That's where we are not very much worried about the offtake is concerned.
In terms of procurement, we have already tied up approximately 50% to 60% of our long-term requirement on the long-term basis, and on a short-term basis another 20% is already contracted. We expect the plant to continue to operate towards the end of the year by 80%-85%, as I highlighted earlier.
That's where I think, in that sense, we are fully secured from the supply chain economics as well as the offtake requirements.
Kartik Kohli
Understood, sir. Thank you so much for answering questions.
Operator
Thank you. Participants who wish to ask a question may press "*" and "1" on your touch-tone telephone.
We have the next question from the line of Prateek Kumar from Jefferies. Please go ahead.
Prateek Kumar
Thanks for the opportunity again. I just had one question.
We had acquired this JPA assets via NCLT route earlier this year. Cement business and power business were divested to other companies.
This hotels and F1 and big land parcel in Greater Noida all kind of remained with Adani Enterprise. What are the plans for all these assets as F1 restart happen in Adani Enterprise itself or in a separate entity?
Manan Vakharia
Hi Prateek, you're right. The bidding entity was Adani Enterprises, but the implementing agency for it was not Adani Enterprises, it was private entity called Adani Infra India Limited.
Nothing of the JAL acquisition remains with us, and is completely off the table for Adani, so far as AEL is concerned.
Prateek Kumar
The hotel projects and the land parcel all is now off the company's, okay. Yes.
Manan Vakharia
Yeah.
Prateek Kumar
Thanks for clarifying.
Manan Vakharia
We have not contributed any equity or any funding also in the project, it is completely off for AEL.
Prateek Kumar
Sure, thank you.
Operator
Thank you. We have the next question from the line of Deval Shah from RBSA Investment Manager.
Please go ahead.
Deval Shah
Hello? Hello?
Operator
Deval, we're not able to hear you very well. Request you to kindly come closer to the microphone.
Deval Shah
Hello. Hello, is it audible now?
Hello?
Operator
Yes, we can hear you now.
Deval Shah
I just wanted to get some more insight on the primary industry. I see that we have significantly increased our EBITDA, and this includes the metals, minings, and the iron specialist manufacturing.
Significantly, probably would be contributed by the copper, but I want just to get some more insight into this ₹5,000 crore EBITDA.
Manan Vakharia
You're right. Primarily, the increase which you see on the first slide or the second slide of the presentation is come from the copper.
Apart from that, the major contributors are integrated resource management and the mining services, for which we disclose the results and the segmental numbers separately. One more part which is part of the primary industry is Carmichael mine, and that is where, against the last year, because of the coal prices are good and the mine is running at an optimum capacity, the EBITDA has started flowing from that mine as well.
That is where for the quarter two, we have done an EBITDA of around ₹470 crore, and cumulatively for the half year, the EBITDA has been at ₹840 crore, which was generally our expected run rate. Because of the good prices, those numbers have come out good, and that is what I think will make up for the remaining part which you are looking at.
Deval Shah
Okay. About the specialist manufacturing, can you please give some more insight into it at what sort of capital we are committing and the size which probably we are thinking of so in terms of the revenue and EBITDA?
Manan Vakharia
The specialized manufacturing is primarily defense that we refer to. In terms of the overall numbers that we are presenting, those are not very significant, and that's why they do not pass the criteria of segment reporting and hence those are not separately reported.
Yes, we are doing meaningful work there, but nothing which can be reported as of now.
Deval Shah
Okay. Since last, what I've seen that we have almost about 18% to 20% of our capital has gone into PVC.
Can you please give us the more insight on the timelines about the PVC business and where we are? Some more insight into the entire segment.
Manan Vakharia
Yes, we are constructing 1 million metric ton capacity plant at Mundra, and where it's approximately ₹26,000 crore CapEx plant that we are building up there. Out of which, I think we have already crossed 60% mark in terms of the project spend as well as the construction on ground, which we propose to do there.
As per timeline, the first part of the overall CapEx is expected to get commissioned in the next fiscal. That's where you will see some kind of numbers coming in this, and after it gets commissioned over a period of next 6 to 9 months, the plant will get stabilized and we'll see the numbers flowing in.
That's where we are in the PVC. The plant is progressing well and on schedule.
Deval Shah
Okay. To our understanding that we only have a plan for manufacturing the PVC, right?
Is there anything else on the PVC line or it's just the PVC or anything else on the chlor-alkali?
Manan Vakharia
Yes, the chlor-alkali is also there. PVC and related chemicals and materials around it.
Deval Shah
Okay. Thank you.
Operator
Thank you. Ladies and gentlemen, that was the last question.
I now hand the conference over to the management for closing comments.
Manan Vakharia
Thank you so much for all the questions, and we close the session. Thank you so much.
Operator
Thank you. On behalf of Adani Enterprises, this concludes the conference.
Thank you for joining us, and you may now disconnect your lines.
Already premium?