Operator

Ladies and gentlemen, good day, and welcome to Transformers and Rectifiers India Limited Q4 and FY26 conference call, hosted by Nuvama Wealth Management Limited. This conference call may contain forward-looking statements about the company, which are based on the beliefs, opinions, and expectation of the company as on date of this call.

These statements are not the guarantee of future performance, and involve risks and uncertainties that are difficult to predict. As a reminder, all participant lines will be in the listen-only mode, and there will be an opportunity for you to ask questions after the presentation concludes.

Should you need assistance during the conference call, please signal an operator by pressing star, then zero on your touchtone phone. I now hand the conference over to Mr.

Vikram Datwani from Nuvama Wealth Management Limited. Thank you, and over to you.

Vikram Datwani

Thank you. Good evening, everyone.

On behalf of Nuvama Institutional Equities, I welcome you all to the Q4 FY26 results conference call of Transformers and Rectifiers India Limited. We are joined today by Mr.

Satyam Mamtora, Managing Director and CEO, and Mr. Mehul Shah, CFO.

I would now like to hand over the call to the management for their opening remarks. Thank you, and over to you, sir.

Satyam Mamtora

Good evening, ladies and gentlemen. I am Satyam Mamtora, Managing Director and CEO of Transformers and Rectifiers India Limited.

Thank you for joining us today for our FY26 earnings call. We are pleased to connect with you as we close another year with a remarkable performance in terms of all key parameters and happy to share our performance highlights, both for Q4 and full year.

As you are aware that our Board of Directors had approved the audited financial results for the quarter, year ended 31/3/2026, and the same has been uploaded on our website of stock exchanges, along with investor's presentation. The financial year 2025 and '26 has further strengthened TARIL's position as a leader in transformer industry, as the company achieved robust operational and financial performance through operational efficiency, process excellence, effective financial management, strategic growth initiatives, and technological developments, and strong corporate governance.

As this has resulted into second successive year of giving record-breaking revenue and profitability numbers. We have achieved highest-ever production in the company's history, manufacturing 33,763 MVA, up from 29,118 MVAs in FY26.

This has directly translated into record high revenue growth, supported by strong execution and healthy diversified order book. This year, we have been intentionally selective in taking new orders as now the company has decided to take orders which are more lucrative in terms of profitability, payment terms, and flexibility in delivery times.

We deliberately moderated fresh order intake during the year to align with extended delivery schedules and capacity planning. In spite of that, our total order inflow FY26 stood at INR 2,374 crores.

This robust inflow has resulted in an unexecuted order book of 5,000-plus crores as of March 31st, 2026, ensuring clear revenue visibility for the next 18 months. During the year, the company has received HVDC transformer repair order from PGCIL, which makes TARIL the first Indian company to get an order of such nature.

We are highly energized by this order as it will pave the way forward for TARIL's entry into HVDC sector upon successful completion of this order. Such types of orders strengthen the company's position as industry leader and enhances customer trust.

We are pleased to inform you that all our fully automated radiator facility has got approval from PGCIL. Now, we have initiated the process of getting our tank manufacturing facility approval from PGCIL also.

Apart from our capacity expansion at Changodar, Moraiya, we are also ramping up our testing facility to cope up with the higher number of transformers at those plants. As you are well aware that we have tested a record number of transformers during FY26, both in terms of MVA, in total units, underscoring our internal capabilities of streamlined operations.

The backward integration journey is well on course. Site readiness is progressing well, and the plant and machinery orders for the long-lead items have already been placed.

This backward integration, along with technological tie-up will enhance our in-house capabilities, reduce our dependency on external sources, and improve our supply chain resilience. We have already started getting CRGO from our newly acquired CRGO processing unit.

All in all, backward integration journey is well on track and to deliver its results in the very near future. These steps will further increase our margin profile by 150 to 200 bps.

Looking ahead, as we transition into FY27, our focus remains firmly on strong order book execution through continued operational efficiency, leveraging our expanded capacity, further consolidating our resources, and sustainable improving margins. Our long-term vision to become $1 billion revenue company within next few years remains intact, and we are confident of achieving it through consistent execution, customer-centric innovation, and robust financial discipline.

Our strategies include strengthening backward integration, investing in automation and digital transformation, focusing on clean, sustainable energy solutions in line with India's power sector ambitions. With strong fundamentals, industry-leading capabilities, and high-quality orders in pipeline, we are well positioned to navigate the opportunities and challenges of the coming year.

On behalf of the entire leadership team, I extend my heartfelt gratitude to all our stakeholders, customers, employees, suppliers, board members, and investors. Your continued trust and support remains the cornerstone of our journey.

Together, we are building a future-ready organization that not only leads in the transformer industry, but also contributes meaningfully to India's evolving energy landscape and Viksit Bharat by 2047. Thank you, once again, for joining us today.

I now hand over the mic to our CFO, Mr. Mehul, to take you through the financial performance of the company in greater detail.

Thank you. Jai Hind.

Mehul Shah

Yeah. Good evening to everyone who are present over this investor concall to discuss quarter four, financial year '26 financial performance of the company.

Thank you, Satyam sir, for your insightful leadership remarks and for setting the strategic context right for the current quarter. It gives me great pleasure to discuss with you all our quarter four, financial year '26 performance, a quarter that clearly reflects the strength of our execution capabilities, resilience of our business model, and the benefits of strategic initiatives that we have been implementing over the past several quarters.

I am pleased to report that quarter four has been a strong quarter for the company, which is showing consistent improvement across all the key financial parameters. Revenue on the standalone basis from the operations stood at INR 752 crores as compared to INR 740 crores of quarter four '25.

The growth was driven by the higher capacity utilization, timely execution of order, improvement in supply chain management. The momentum seen during the last couple of quarters will give us confidence for the next quarters of consistent, improved performance.

EBITDA for the quarter came to rupees INR 117 crores with a margin of 15.1%. The margin is slightly down due to additional increase in the employee cost on account of ESOPs.

Profit after tax stood at INR 77 crores, reflecting not only the strong operating performance, but also the disciplined financial management across the organization. Revenue on the standalone basis for the full financial year stand at INR 2,395 crores as compared to INR 1,950 crores for the full financial year.

EBITDA for the year come at around INR 370 crores with the margin of 15.1%. Profit after tax stood at around 225 crores with the margin of 9.2%.

Further, on the consolidated basis, revenue for the quarter stood at 783 crores against INR 737 crores during quarter four, financial year '25. EBITDA stood at INR 141 crores and PAT at 91 crores.

On the basis of full financial year, consolidated number, revenue is 2,509 crores, up from 2,019 crores. EBITDA stood at INR 444 crores and PAT is around 272 crores.

Importantly, quarter four also marks a turning point in terms of consistent growth with margin sustainability. We are very much confident of maintaining the improved margins due to our capacity expansion, backward integration plans, and structured margin improvements.

The backward integration facility and the developments are expected to further enhance the cost efficiency and reduce external dependency over the medium term. Looking forward, we enter the next financial year with strong visibility of our order books, new capacities coming on board, starting of our backward integration projects.

Our order book remains robust, execution pipelines are healthy, and the plant utilization levels are expected to remain [unclear] for the full financial year. Before I conclude, I would like to express my sincere appreciation to our team across operations, finance, supply chain, projects for their relentless focus and execution excellence.

I would also like to thank our board and investor for their continuous trust and support as we work towards building a strong, more resilient, and a future-ready organization. With that, I conclude my remarks.

Thank you, once again, for joining us today. We are now happy to take your questions.

Thank you.

Operator

Thank you so much, sir. We will now begin with the question-and-answer session.

Anyone who wishes to ask a question may press star and one on their touchtone telephone. If you wish to remove yourself from the question queue, you may press star and two.

Participants are requested to use handsets while asking a question. Ladies and gentlemen, we'll wait for a moment while the question queue assembles.

The first question comes from the line of Abhishek Vijay from Global [Constant?] Research.

Please go ahead.

Abhishek Vijay

Hi. Am I audible?

Operator

Yeah.

Satyam Mamtora

Yes.

Operator

Yes, you are.

Abhishek Vijay

Yes. When I was seeing the results, I can see that the cost of materials consumed has increased a bit disproportionate to the revenue, and I'm guessing that this is because of the copper price surge due to the Hormuz disruption.

Could you throw some more light on what other raw materials is disrupted due to this Hormuz closure?

Satyam Mamtora

Abhishek, see, mainly copper is slightly disturbed. Other than that, not because of Hormuz issue, but because of overbooking for all other ancillary parts like bushings and stuff, there is a slight disturbance.

Plus, the porcelain is being made in gas-fired kiln. Gas is also becoming slightly problem, there are certain issues that we are facing because of Hormuz, but not very much.

Abhishek Vijay

Sure. One more thing is that we are foraying into HVDC, and I wanted to understand the competitive landscape in HVDC from you.

I've seen that a lot of MNC players are already in the thing. What is the competitive advantage that we have?

Satyam Mamtora

There are only four major players in HVDC: Hitachi, Siemens, GE, and I think TBEA. TBEA is not able to compete with us in the other tenders.

Only three major competitors are there. Other than that, we are the only players who will be entering into HVDC.

Abhishek Vijay

I'm sorry, but I couldn't quite decipher what the competitive advantage was.

Satyam Mamtora

HVDC is a very highly technical product, and because of the limited number of players in this HVDC side, the margins are also better in HVDC.

Abhishek Vijay

Sure. I was also reading Siemens's concall that only about one to two tenders are floated every year for HVDC.

What are our odds on getting that contract compared to these four players that you just mentioned?

Satyam Mamtora

Yes, currently there are only about one to two tenders of HVDC, but going further, the numbers of tenders that are going to be in pipeline should be around 10 to 12. Each tender should have about three units of HVDC, there is a good scope in HVDC in the future, coming future.

By that time, we will also be successfully empanelled in HVDC transformers.

Abhishek Vijay

Yeah. Thank you very much.

Operator

Thank you. Our next question comes from the line of Vaibhav Mishra from Finvestor.

Please go ahead.

Hello, sir. Good evening.

Sir, my question is regarding this West Asia conflict. How can it affect or is it affecting us in any way like in supply chain or from the delivery side?

Are we affected in any way from this?

Mehul Shah

No. Basically, see, if you look at our export numbers etc., there is very minimal exports that what we are currently doing.

From the West Asia region, there is a very minimal import that has been coming to India for us. There is no major impact as far as this conflict is concerned.

The only issue that we are looking at is availability of gas for our fabrication units and stuff like that, but we are mitigating those issues also.

All right, sir. Sir, regarding the guidance bit, actually in the last three quarters, I think this is the second quarter where we have missed our guidance, like the revenue guidance of, I think, 2,600 crores in Q3 call it was told.

Also order book, it was very confidently said that closing order book will be 8,000 crores, but it's still 5,000 crores. What is leading to this recently, actually, has the history of not meeting its guidances.

What is happening for the last two, three quarters?

Satyam Mamtora

See, we are deliberately not taking orders currently because we want, as we have previously told, that we want to limit our exposure to not more than 18 to 24 months, and we want to be very selective in which orders we take in terms of delivery and in terms of the price that we quote. We are being extremely selective of what orders to take, and we do not want to take any order which is beyond 24 months of delivery.

That is where we stand at right now. As long as we are not free for next 24 months, we do not want to take any further orders.

Okay. Sir, I think this was the stand in the

Satyam Mamtora

We are continuing to be extremely selective for this.

All right. Sir, I think this stand was in the last call itself, sir, and that we were selective and we were already Yes, and

Satyam Mamtora

we are maintaining our stand that we do not want to take any orders that are beyond 24 months.

All right, sir. Sir, our backward integration plans that we have for the next Q1, Q2, Q3, Q4, four quarters, are they on track?

Is there any change in timelines of them? No,

Mehul Shah

no. That is all on track.

We already started the site preparation. Plant, machinery, which is having a higher lead time, has already been ordered.

By say starting of next financial year, we'll start the impact of this backward integration plans that we have.

All right. One last question, sir, regarding FY27.

The revenue target that we have in mind for FY27 or the consolidated margins that we are targeting for?

Mehul Shah

I think as of now, we have not say finalized what we will be looking at, but what we can say is around 3,250 crores is what we are looking at revenue. Revenue.

All right, sir. All right.

Thank you so much, sir, and all the best for the future.

Satyam Mamtora

Thank you.

Operator

Thank you. Our next question comes from the line of Bala Subramanian from Arihant Capital Market.

Please go ahead.

Bala Subramanian

Good evening, sir. Thank you so much for the opportunity.

Sir, I'm trying to understand gross margin side. In FY26, we have a gross margin of 31%.

Sorry, 31%, 32% kind of range. We are trying to reach 35% by FY28 and 40% with deeper integration.

I'm trying to understand how this gross margin improved in terms of RIP bushing internalization, CTC internalization, CRGO sourcing efficiency, and price increases. Which single item contributes the most weightage?

If you could share some clarity on that.

Mehul Shah

Yeah. Basically, currently, you are right.

We are at 30%, 31% margin, and due to this capacity expansion that what we are doing at our Changodar and Moraiya project, plus the efforts that has been done to do the operational efficiencies, etc., this will give us some margins in terms of next, say, two three two to three years. Plus the backward integration plans, which will start from the next financial year, which will also give us some, say, 200 to 300 bps of additional margin.

That's how we are looking at around, say, 35% margin. Sir.

Bala Subramanian

Yes, sir. Also, sir, I think already mentioned we are on track for backward integration.

I'm trying to understand I think we have a 60% increasing capacity of MVA, and how this I think the industry issues not remain resolved in terms of supply constraints. Whether we have a hard sourcing agreements or MOU already in place for the incremental CRGO, bushing, and CTC volumes?

Satyam Mamtora

Yes, we already have agreements in place, sir. Sir.

Bala Subramanian

Okay. Sir, my last question, if you could help us understand on furnace transformers, renewables, and green hydrogen.

On that furnace transformers side, we have seen only market size only 200 to 300 crore despite having high technical barriers and low competitions. Why the addressable market is so small, and whether we can expect substantial growth in those area?

Secondly, renewable side, the margins are I think at lower level for renewable transformers and solar transformers, typically lower margins. Whether we can able to see margin improvement or volume improvement in those area?

Thirdly, green hydrogen Yes, sir. Go on,

Satyam Mamtora

go on with your question.

Bala Subramanian

Yes, sir. On green hydrogen side, I think we have not started any projects or any supplies.

Trying to understand when we can expect demand for green hydrogen side, especially like any specific policy or project milestones or any tender awards or any street pipeline approval are in place?

Satyam Mamtora

As far as renewable transformers for renewable energy is concerned, see, with our backward integration and with our manufacturing with 75,000 MVA manufacturing capacity, our purchasing power becomes significantly higher. The margins improvement there are going to be very high.

I completely understand that right now there is no much margin improvement there, but with the backward integration and with the purchasing power of 75,000 MVAs, there should be a substantial decrease in our purchasing price. This is going to affect our margins effectively.

Green hydrogen, the projects are still not coming up live. We are also working at a few prototype transformers, which need to be short-circuit tested and done some testing.

As soon as the projects come up live, we will start getting some feedback on the green hydrogen transformers.

Bala Subramanian

Sir, on the furnace transformer side, sir?

Satyam Mamtora

Furnace transformer will see some improvement as the steel industry in India starts moving at a faster pace.

Bala Subramanian

Sir. Thank you.

Satyam Mamtora

Thank you. Moderator, can we limit to one question per person, please?

Otherwise, everybody won't get a chance.

Operator

Sure. Ladies and gentlemen, in order to ensure that the management will be able to address all the questions from the participant, we request you kindly limit your question to one question per participant.

If you have a follow-up question, please rejoin the queue. Our next question comes from the line of Deepak Poddar from Sapphire Capital.

Please go ahead.

Deepak Poddar

Am I audible, sir?

Satyam Mamtora

Yes, you are audible.

Deepak Poddar

Thank you very much for this opportunity, sir. Sir, just I will ask two questions, very quick questions.

Sir, our capacity got delayed, right? This Changodar plant now it's slated to start by second quarter, right?

What's the reason?

Satyam Mamtora

Yeah. Extended monsoons was one of the biggest reasons in terms of delay in the usefulness of the plant.

Deepak Poddar

Okay. Understood.

When is the Moraiya plant expected to come on stream?

Satyam Mamtora

Moraiya plant, we are planning after this year's monsoon.

Deepak Poddar

By 3Q FY27?

Satyam Mamtora

Yeah.

Deepak Poddar

Okay. Ideally, then your first half growth will be quite muted, right, because already

Satyam Mamtora

No, no. See, Moraiya, we have Moraiya plant is working at about 75% plant utilization.

We are working on maximizing that plant utilization before we start anything else.

Deepak Poddar

Understood. What's the capex on this?

Operator

I'm sorry to interrupt you, sir, but please rejoin the queue for more questions.

Deepak Poddar

This is the follow-up, yeah.

Operator

You may rejoin. Thank you.

Our next question comes from the line of Ashish from Leo Capital. Please go ahead.

Oh,

yeah. I had a question regarding how the industry works.

How fungible is installed MVA capacities across voltage classes? Can capacity allocated to, let's say, 220 kV be redeployed to higher kV or vice versa, or are they largely dedicated voltage-specific lines?

Satyam Mamtora

See, basically, there are three things: from 400, we can go down to 20 220. From 220, we will not be able to go up to 400 if the plant is not designed for 400.

There's a testing facility, crane capacity, winding machines capacity. There are four, five items because of which from 220 going up to 400 is going to be a challenge.

Coming down from 400 to 220 is easy. It's not vice versa, but from 400 to 220 can be done.

From 400 from 220 to 400, as long as plant is not designed for 400 kV, it will not happen.

Okay. To summarize, let's say someone has a distribution transformer capacity in MVA, that can't be scaled to a EHV 220

Satyam Mamtora

or

400 capacity? No, no, no.

What are the limitations, exactly?

Satyam Mamtora

Crane capacity, let's say, the height of the building, testing facilities, there are many factors, winding machine capabilities. There are many factors that will affect it.

Okay. I got it.

Thank you.

Satyam Mamtora

Thank you.

I'll rejoin the queue for my next question.

Operator

Thank you. Our next question comes from the line of Kaushal Sharma from Equinox Capital Venture.

Please go ahead.

Kaushal Sharma

Hi, sir. Am I audible?

Very good evening.

Satyam Mamtora

Yes, you are.

Kaushal Sharma

Good evening. Sir, my question is on the industry side, due to the extended monsoon, how does it affect overall industry transmission utility industry?

Are we seeing any slowdown in the capex, or is it temporary, like one or two quarter execution spillover? No,

Satyam Mamtora

no, there won't be any delay as far as capex plan is concerned.

Kaushal Sharma

We are not facing any delay in dispatching any order, current order book and all?

Satyam Mamtora

No.

Kaushal Sharma

Sir. Thanks.

Operator

Thank you. Our next question comes from the line of Vineet from Toro Wealth Managers.

Please go ahead.

Vineet Khatri

Hi, sir. Good afternoon.

Satyam Mamtora

Good afternoon.

Vineet Khatri

Sir, my question is around the supply enhancement that has been going around in the entire power value chain, right? Like, most of our vendors as well in the transformer value chain are enhancing the capacities.

I just wanted to know what's our view on if we can negotiate with our suppliers when they have increased capacity?

Satyam Mamtora

Sorry, Vineet, we didn't understand your question.

Vineet Khatri

Sir, I'm asking in this phase where the capacities are being enhanced by most of our vendors, what is our position in negotiating on prices with our suppliers?

Satyam Mamtora

See, Vineet, honestly, there is still hand-to-mouth in terms of most of the items that transformer manufacturing is concerned. We can only negotiate in terms of delivery time for each product that we need.

That is one of the basic negotiations that can happen currently.

Vineet Khatri

Okay. Demand is so strong that only we can negotiate on the delivery timelines, but on the pricing side, it's more or less will be same.

Mehul Shah

Yes.

Vineet Khatri

Got it, sir. Thank you, sir.

Operator

Thank you. Our next question comes from the line of Yash Gupta from Ashit Kotecha Family Office.

Please go ahead.

Yash Gupta

Sir, my first question is on the capacity. Could you please help us understanding the trajectory of our upcoming capacity addition?

Is it reasonable to expect that around 50% of the utilization will come by H2 FY27? How should we think about capacity expansion plan over next two to three years, and how cash flow will be utilized from it?

Mehul Shah

See, basically, Changodar facility will be up and running from this, say, quarter two, and after that, we will take up this Moraiya plant expansion. After these two plants, the capacity would be, say, from 40,000, it will go up to 75,000.

Yash Gupta

How our utilization will be for second half of FY27 and '28 of upcoming capacity?

Mehul Shah

Of upcoming capacity, Changodar will start in H2, but initially it would be low since it is a new plant, etc. From the, say, next financial year, it would be running at around 75%, 80% capacity.

Satyam Mamtora

I think by end of quarter three, we should be almost at 80% capacity in Changodar plant.

Yash Gupta

Do you think it will impact our EBITDA margin in the first half and maybe Q3?

Mehul Shah

No. Because, see, our orders are already in the pipeline, and we are working on that, so that won't be any impact.

Definitely, the quarter three numbers will be on a higher side because of this new capacities, but this, say, first half, the numbers would not be affected by this.

Satyam Mamtora

Yash, like we said before, we are very selective in what orders we want to take right now. We are not taking any orders that are beyond 24 months.

Being selective on the type of orders that we are taking, there is not going to be any effect on the EBITDA of the company.

Yash Gupta

Sir, higher in Q3 means in terms of higher margin or in the amount you're talking about?

Satyam Mamtora

Both. Not margin, but in terms of revenue.

Mehul Shah

Revenue.

Yash Gupta

Margin will be this only, 16.5% to 17%?

Satyam Mamtora

Yeah. Margins will remain at 16.5%

Yash Gupta

to 17%. Sure.

Thank you, sir.

Operator

Thank you. Our next question comes from the line of Yash Rathi from Mangal Keshav Service.

Please go ahead.

Yash Rathi

Good afternoon, and congratulations on good set of numbers. We are going backward integration on the CTC plant itself.

Just wanted to understand, would that also require a additional PGCIL approval if we are using that for the captive purposes into our 465, and moving forward, when we get a HVDC approval as well, we would be using our CTC for the captive purposes. How the PGCIL approval would look like?

Satyam Mamtora

PGCIL approval will definitely be needed, and the plant that we are putting up for CTC and the plant that we will be putting up for pressboard, both these plants are world-class plants. We've already taken into account what all PGCIL requires for approval of the plant.

Since it is our own captive consumption, the approval becomes very easy from PGCIL.

Yash Rathi

Can we just get some timeline on the same? Also,

Satyam Mamtora

Timeline on what, getting approval from PGCIL?

Yash Rathi

Yes.

Satyam Mamtora

I think within a month of starting the production capacities, we should get the approval. See, as it is, PGCIL and we are also facing some issues regarding the deliveries of CTC conductor.

It is of utmost importance for PGCIL also to make sure that they have one more vendor in India which delivers CTC production.

Yash Rathi

Okay. Just one more thing on the CTC front itself.

It won't cater to our whole production for the transformer, how much we would still look to outsource, or it would be enough for our annual transform manufacturing capability?

Satyam Mamtora

The current plant is to cater to 100% need of TRIL, and going forward with certain more expansion, we will be also looking at selling in the market, third-party selling also we will be doing.

Yash Rathi

Understood. Thank you so much, sir.

Satyam Mamtora

We will basically be also CTC suppliers to other transformer manufacturers.

Operator

Thank you. Our next question comes from the line of Shubham Damshina from Thinksight Advisory.

Please go ahead.

Am I audible?

Satyam Mamtora

Yes, you

Mehul Shah

are.

Sir, any update on the World Bank issue?

Satyam Mamtora

Mehul Shah sir will give you a reply.

Mehul Shah

Yeah. As per the timelines, etc., we have filed the reply to the World Bank, and we are awaiting any response also.

Recently also, we have filed that before taking any decision, etc., we should be given a opportunity to be heard in person. We are awaiting the feedback from the World Bank on this.

Okay. When can we expect the reply?

Satyam Mamtora

I think it should be closed in 45 days, that's what our belief is.

Thank you.

Satyam Mamtora

Thank you.

Operator

Thank you. Our next question comes from the line of Abhijeet Singh from Systematix.

Please go ahead. Yeah.

Abhijeet Singh

Yes, sir. Thank you for the opportunity.

My question is on HVDC. What is the scope of our offering in the HVDC scope overall?

For example, the OEM typically has about 45% to 60% of the overall project cost. You mentioned that you will be able to supply three to four units in a substation for HVDC.

What is the scope in percentage of the overall project cost for HVDC for us?

Satyam Mamtora

We didn't understand your question. Please, can you come back again?

Abhijeet Singh

Yes, sir. Out of the total project cost for an HVDC

Satyam Mamtora

Yeah,

Abhijeet Singh

what is our scope? What is our scope?

Let's say we are supplying HVDC transformer, right, three to four units per project.

Satyam Mamtora

Yeah.

Abhijeet Singh

What is that as a percentage of overall capex on the project?

Satyam Mamtora

That should be around 40% of overall capex of the project.

Abhijeet Singh

Right, sir.

Satyam Mamtora

Because HVDC transformer is going to be the largest equipment and the most expensive equipment in the project, around 40% should be our cost

Abhijeet Singh

Right, sir. Thanks.

Sir, when do we expect the approval from PGCIL for this particular product?

Satyam Mamtora

Once we've successfully repaired this transformer and given back to PGCIL, after six months of working in satisfactory conditions, PGCIL will start the process of approving us as one of the HVDC manufacturers in the country.

Abhijeet Singh

Right, sir. Sir, just one last thing

Operator

I'm sorry, but please rejoin the queue for more questions.

Abhijeet Singh

Sure.

Operator

Thank you. Our next question comes from the line of Prathmesh Salunkhe from PL Capital.

Please go ahead.

Prathmesh Salunkhe

Hi, sir. Thank you so much for the opportunity.

Sir, my question is again on the HVDC space. I just wanted to understand, now that we plan to supply only the equipment, the HVDC transformers in the project, and it may take some time for the approvals to come in, and at the same time, I recall in the last few calls, management had mentioned that we are not really doing LCC or VSC.

We are trying to come up with our own technology. For next two, three years, all the projects that are in the pipeline have already been established, whether as an LCC or VSC project.

How will TARIL be able to compete for this project against the established MNCs?

Satyam Mamtora

What is LCC project?

Prathmesh Salunkhe

Sir, technology of the HVDC, LCC and VSC.

Satyam Mamtora

We are coming up with our own process of HVDC.

Prathmesh Salunkhe

Yeah. Sir, my question was the same.

Since there are two, three projects in the pipeline, right, for next two, three years. All those two or three projects have already been decided whether they are coming with LCC technology or VSC technology.

If the projects are coming in LCC and VSC, and we are not supplying either of these technologies, how will TARIL be able to participate in this tender? Basically, we will have to wait for a project for next four, five years before we can participate.

Is that the right understanding?

Satyam Mamtora

No, that is not. There are other projects that are coming up with EPC contractors also, where we will be participating.

Prathmesh Salunkhe

Okay. Other EPC contractors, these projects will not primarily come from a player like PGCIL.

Is that right? No.

Satyam Mamtora

Yeah. All right.

Prathmesh Salunkhe

All right. Thank you.

Thank you so much.

Operator

Thank you. Our next question comes from the line of Raj Saraf from Finvestors.

Please go ahead.

Sir, am I audible, sir?

Satyam Mamtora

Yes. Yeah.

Thank you very much for giving me opportunity. Sir, I am tracking and I'm investor in the company since last 2 and 1/2 years, and I appreciate the journey TARIL has been through.

Sir, from last one year, what I'm seeing that there is a delay in some projects. If I compare the investor presentation of FY25 and now FY26 on the chairman's comment, what I can see that all capex have been delayed by at least one year, and all the integrations are also delayed with the same timeline.

Even the guidance also delayed. When I watch interview which is given by your Director Finance, Mr.

Satyen Mamtora, what he guides on television and what we come through the conference call, there is a very significant difference in these two outcomes. I want your take on that.

Satyam Mamtora

What are you exactly referring to, if I may ask? Are you talking about the order input?

Sir, there are numerous things, sir. Like order inflow, what you are mentioning that we are very concerned about the margins and the quality of the order we are taking.

Despite questioning on the same line to Director Finance, he very confidently on TV interviews putting the number of 8,000 and close to 7,500 order book closer by FY26, the first thing. The second thing, the projects or capexes we are right now executing, the timeline of the project is right now delayed by at least 1 year, all the projects delivery Changodar or Moraiya.

The third thing is on the margin front. What we are expecting as an investor from last 1 year that all the projects which are right now being done will increase the margin, whereas what we are seeing in even in the last this Q4, the recent concluded Q4, in spite of we are having a greater number on the top line, the margin is still consistent, which we would have liked that it would have come the best margin of the year.

All these things, sir.

Satyam Mamtora

As long as the outlook on the margin, we've always maintained that the margins will remain at 15% to 16%. We have never changed that.

In terms of the order book, yes, we have miscalculated the orders that were supposed to be coming to us, and like we say, we are very careful in selecting which orders we really want to execute because right now the market is such where we can be slightly choosy about what orders to take. As far as the new projects are concerned, there was a delay because of extended monsoons, which has delayed the project by one quarter.

Sir. Sir, on the guidance side also, sir,

Satyam Mamtora

I will, once again, reiterate that orders input will be very selective, and we will make sure that we do not take orders that are beyond 24 months.

Sir, my concern is on the top line, sir, not on the order book, sir, which you have clarified now.

Satyam Mamtora

Top line, Mehul sir will give you an answer. Yeah.

Sir, the top line which was guided in the commencement of FY26 was 3,500, which was reduced mid-year after very subdued Q2. That was again told 2,500 to 2,600.

Even on the 3rd 3rd or 4th March, Director Finance came on television, and he reiterated the guidance that we are very sure that we will be closing above 2,500. This 100 crore guidance is okay, but the confidence which has been shown initially in the year, and right now the tone of the management in this Q4 conference call is not matching.

Mehul Shah

That's true that initially we have targeted that number, but that has been later on realized, and we have categorically come up and revised that guidance during the quarter two conference call.

Okay. Sir, my point is that, sir, we are doing very phenomenally well.

Let us be, it's up to you, sir, be conservative and deliver more, rather than being more Raj,

Satyam Mamtora

we have realized this, and that is why this year we have given a outlook of 3,250 crores, not beyond that.

Sir. I appreciate this, and thank you very much, sir.

I'm concerned about the company because I'm an investor from last 2 and 1/2 years. Thank you very much, sir.

Sure,

Satyam Mamtora

sure, Raj.

Operator

Thank you. Our next question comes from the line of Karan Gupta from ACMIIL.

Please go ahead.

Karan Gupta

Hi. Am I audible?

Satyam Mamtora

Yes.

Karan Gupta

Yeah. My question is more on the margin side.

Considering the competitive bidding in the industry, what will be the margin on EBITDA level consol basis over two to three years? This one thing is the competitive bidding in the industry, and the second thing is that you're doing backward integration, and you're saying 2% to 3% kind of lever in the margin you can get.

My point is in the next two to three years, what will be the margin side? It will be compensated by the backward integration you are doing, or it will improve further from the mark of 16%, 17%?

Mehul Shah

See, as we are saying that margins will remain in the range of, say, 15% to 17% as currently. Through this backward integration coming up, you may see some increase in that number.

About 200 to 300

Karan Gupta

bps. Okay.

What about the cash flow side? The working capital compared to FY25 to '26, receivable side and inventory side doubled, I think.

What we are doing for this working capital side, how we are getting mitigated this thing?

Mehul Shah

See, compared to our financial year '25 numbers, definitely the receivable number and inventory numbers are high. On the receivable side, I think due to this last minute, March numbers, we have missed certain collection.

In the first, say, 15 to 16 days' time, we almost collected around 200-odd crores. There are some delays as far as the utilities is concerned because their budget, etc.

has by March, they have released payments in the new financial year.

Karan Gupta

Okay. Typically, payment did got delayed?

Mehul Shah

Yeah.

Karan Gupta

Thank you.

Mehul Shah

Okay.

Operator

Our next question comes from the line of Deekshant from DB Wealth. Please go ahead.

Deekshant Boolchandani

You mentioned that we are looking at alternative sources for our gas, which will help us continue our production. What is it that we are doing to mitigate this risk right now, so that our production can ramp up?

Satyam Mamtora

We had invested a few years back in some laser-cutting technology. We have also invested in plasma-cutting technology.

All that is coming on line, and this gas prices have helped us improve our efficiency on those cutting CNC machines.

Deekshant Boolchandani

Instead of using gas as a power source, we will be using electricity as a power source?

Satyam Mamtora

Yes, yes, yes, that is correct.

Deekshant Boolchandani

Is there any other way that we can make sure that we don't get into any problems for expanding our capacity, because now that we are going to a new phase of expansion, this seems to be a risk that seems to be very likely.

Satyam Mamtora

What is the risk that we are talking about? The gas risk are you talking about?

Deekshant Boolchandani

Anything that is going to make our production capacity go down or our capability to deliver go down. Gas is one of it, right?

Satyam Mamtora

No, no, no, there is no issue as such for the utilization of the capacities. We don't see any risk in utilization of the capacities, Deekshant.

Deekshant Boolchandani

Sir. Thank you so much.

Operator

Thank you. Our next question comes from the line of Aditya Vora from Soham AMC.

Please go ahead.

Aditya Vora

Hello. Hi, good evening, sir.

I had a question on margins. You alluded to the fact that I think 15%, 16% is a good number to look at currently.

Structurally, I just wanted to understand that most of our peers, in spite of being in low kV class, are doing superior margins to us, and also they are not backward integrated. What is the reason for our margins to be at 15%, 16% where majority of the peers are 18%, 19%, and even 20% to some extent?

That was the understanding which I wanted. Also at a time when the transformer industry is at an explosive growth, shouldn't we be getting better margins and faster growth?

Mehul Shah

See, this backward integration margin is yet to come into the picture. We are talking this margin, say, of 15%, 17% is without any margin improvement in terms of backward integration.

But

Aditya Vora

No, I understand what you're trying to say, but the peers also don't have backward integration, that is one. Secondly, what I'm trying to highlight is that peers are in relatively lower-margin, lower-kV class while you are predominantly into 220 and above.

So, 220 and 400 is what you are targeting while if you look at majority of our peers, they are getting to 220 or 400. In fact, if you look at say Atlanta, it recently got into 400, Voltamp and others are getting there.

Ideally, our margins structurally should be much higher than them, and I'm assuming even their backward integration, leaving aside say Atlanta, their backward integration is the same as us. I don't know why our margins are at only 15% structurally.

Mehul Shah

That's the reason why we are very selective in terms of taking orders, etc. going forward.

As we must have seen, that these orders we must be executing which we have taken, say, 12 months, 15 months back. That is the major reasons why we have decided that, yes, we will not take any orders which is coming our way, and we will be very selective in terms of margins, etc., as well as the delivery schedules, etc., matching with our production lines.

That is the reason why we would be selective, and our margins will improve.

Aditya Vora

Sure. Just one thing on your guidance going forward, would you like to give any guidance for FY27 in terms of growth percentage, if not the absolute number?

Mehul Shah

It could be roughly around, say, 35%, 40% growth in terms of revenue.

Aditya Vora

Order book, any sense on that, considering you curtailing incremental order inflows to focus on the quality of orders?

Mehul Shah

I think if we do 3,250 crores, let's say I don't know. Rather than putting this numbers, we would like to restrict ourselves to we will take the order, say, up to 24 months.

Aditya Vora

And 35% to 40% is a revenue growth what you're talking for FY27?

Mehul Shah

Yes. Okay.

Aditya Vora

Sure, sir. Thank you, sir.

Operator

Thank you. Our next question comes from the line of Sagar Gandhi from Invesco Mutual Fund.

Please go ahead.

Sagar Gandhi

Sir. My question is on the inquiries under PowerPoint presentation, that is 23,000 crores that you have mentioned.

Now you highlighted you are looking at orders only under 24 months. Of this 23,000 crores, how much is for 24 months?

Satyam Mamtora

After quarter one, there should be around 18,000 MVA order inquiry that will be in 24 months.

Sagar Gandhi

Thank you, sir. Sir, you confirmed that the receivables that have gone up by around 410 crores, of 200 crores of this 410 crores have come in the first 15 days of April?

Satyam Mamtora

Yeah.

Sagar Gandhi

That has happened, right?

Satyam Mamtora

Yeah.

Sagar Gandhi

Thank you so much, sir. That is it from

Satyam Mamtora

Moderator, we would like to take last few questions, please.

Operator

Sure. Our next question comes from the line of Neville S.

Shaft, an individual investor. Please go ahead.

Neville S. Shaft

Good evening, sir. Thanks for taking my question.

My question would be on the order book mix. Recently, we've seen a good amount of orders coming from the government utilities.

Could you tell us that out of the outstanding order book of 5,000 crore, how much percentage consists of this utility players, and how much is the private portion?

Satyam Mamtora

Let's say around 55% will be utilities, 20% would be EPC contractors, and remaining all private customers.

Neville S. Shaft

Got it. Another thing that now with backward integration facilities in place, which will be coming into effect from the first half of 20 FY27 and latest by FY28, so that would lead to shorter lead times and also give us some cost advantages.

Would we be approaching more private players who still prefer the suppliers for transformers, or we stick to this mix?

Satyam Mamtora

No, we would be approaching many private customers, but provided we are getting deliveries and quality of the order inflow is going to be the key area of focus in the next year.

Neville S. Shaft

Sir. Got it.

Thank you very much.

Operator

Thank you. We'll be taking the last question from Shashiranjan from Anandan Capital.

Please go ahead.

Good evening, team. Thank you for the opportunity.

I heard that we have order book of around, say, 5,000 crore approx. Previous discussion, we also learned that we were not able to pass on to the rising cost because the orders that was there was older one.

We're not able to pass on the increased tariff. How many such order book that we have which are not giving us more margin out of that 5,000 crore rupees order book?

Satyam Mamtora

I think everything that has been there, we have already executed. Now, since last six months, we have been very critically analyzing every order that we want to take, and we are very selective in taking orders.

None of the orders that are in this 5,500 crores have any issues in terms of our margins or cost.

Last one, sir, if you may allow, what is the current capacity that we are running at, and how far we intend to pull this capacity utilization in next two quarters?

Satyam Mamtora

We are currently running at around 75% capacity, this year we should go at around 95% capacity.

Thank you so much, sir. Thank you for the opportunity.

Operator

Thank you, ladies and gentlemen. Due to time constraint, that was the last question.

Any pending question may be sent to the Transformers and Rectifiers India Limited investor relations team, and they will get back to you. With that, I'll hand the conference over to the management for the closing remarks.

Thank you, and over to you, team.

Satyam Mamtora

Thank you, once again, for joining us today. I extend my heartfelt gratitude to all our stakeholders, customers, employees, and board members, and investors, and all of you who has attended this investors call.

Thank you very much, everybody.

Operator

Thank you so much, sir. Ladies and gentlemen, on behalf of Nuvama Wealth Management Limited, that concludes this conference.

Thank you for joining us, and you may now disconnect your lines.