Q3 FY2026 · Earnings Call TranscriptApril 28, 2026

David Boshoff

Good morning, everyone, and welcome. I'm David Boshoff, and with me is our CFO, Steve Fewster.

We're pleased to be joining you today for this March 2026 quarterly update. Before we get underway, I'd like to mention that today's presentation should be read in conjunction with our March quarterly report.

This is available [available?] on the BCI website.

Also, as we move through today's session, please feel free to add your questions to the live Q&A tab on the right-hand side of your screen. We will definitely respond to these questions at the end of the session.

I also just want to, before I move to the next slide, just talk a little bit about the images on your screen. These are taken from our first crystalliser, and as you can see on the left-hand side, that's the salt pavement already forming at the bottom of the crystalliser.

As of this morning, we're at 9 thick of pavement. This is more than double what we were last week at the same time.

A very exciting time for BCI. Slide is not moving...

Just give me one second... There you go.

We always begin with this slide because it reflects how we do things at BCI, with our values guiding every decision we make. This quarter was no exception.

We delivered consistent progress across operations, construction, and financial performance, a clear demonstration of our values in action, particularly our "we do what we say" value. This has been the commissioning of our primary crystallisers with high-density brine now from Pond 9.

As of today, we have brine in the first two crystallisers, and as you saw from that picture, salt pavement is forming in those crystallisers. This milestone is the result of strong collaboration across our teams and contractors.

While the sun has done its job in driving brine density, it's the preparation, coordination, and commitment of our teams and contractors that enabled this system to perform and the brine to flow. Mardie is now firmly established as a working salt operation.

That values-driven approach is exactly what underpins the business we're building at Mardie. Mardie is already Australia's largest solar salt operation and the third largest globally.

Our focus is clear: delivering high-quality salt and associated minerals to our customers. With salt now in operation, we're focused on achieving a safe and efficient ramp-up as quickly and as efficiently as we can.

We believe salt bitterns represent a valuable opportunity to support additional product streams over time, and that's why sulphate of potash trial is an important step towards proving it as our next major revenue stream. With its scale, coastal location, and integrated port infrastructure, Mardie is exceptionally well positioned to meet expected rising demand across Asia.

The port provides us connectivity to our customers, along with additional upside through its spare capacity, creating potential for third-party revenue and strategic partnerships over time. Slide's stuck...

We'll still try to move back to the right slide... The March quarter marked a pivotal period for BCI, delivering outcomes that'll shape the year ahead.

In safety, we've continued to strengthen our key fatality prevention controls and maintained a focus on field leadership, completing over 380 leadership in the field safety interactions. Operationally, as mentioned earlier, we've commissioned our first two crystallisers, along with the brine channel and the first two lift stations, marking another important step forward for the operation.

During the quarter, the Pilbara also experienced two tropical cyclones, and I'm pleased to share with you today that there was no material impact to our people, plant, equipment, or infrastructure, and we had no loss of brine. Construction is now progressed to 81% complete, with the salt wash plant advancing well and concrete installation works remaining on schedule.

In relation to sulphate of potash, the KTMS trial crystallisers have transitioned from batch testing to steady-state operations, with performance in line with expectations. On the corporate front, construction remains within budget, and BCI continues to maintain a strong financial position.

During the quarter, we drew $50 million from our syndicated debt facility, taking total debt drawn at the end of March to $496 million. On the 11th of March 2026, we've reached a critical milestone, we've commenced flooding of our first two crystallisers with high-density brine, as you can see on the screen.

This represented a critical step in the salt production process, enabling the formation of salt pavement and marking a significant milestone on our path to first salt production. Strong asset reliability has continued to underpin our operational performance, supporting a safe and efficient movement of high pump volumes throughout the quarter.

During the quarter, tropical cyclones Mitchell and Neville passed through the Mardie site, with no material impact to our people, plant, equipment, or infrastructure, and importantly, we had no loss of brine. Our cyclone preparedness and response plan was executed as designed, allowing us to safely restart operations in a phased and controlled way, by detailed inspections, asset validation, and the progressive recommissioning of key infrastructure.

The rainfall associated with Tropical Cyclone Neville in March was significant. We had between three and four times the March average.

This level of rainfall reduced the pond's density levels, as one can expect, and delayed the crystalliser lining program. Brine density is strongly influenced by seasonal evaporation rates.

During peak summer periods, we get better evaporation, and then, of course, during the cooler months, slower evaporation. The revised density profile, as you can see in blue on your screen—it's a blue shaded area—reflects this more gradual profile that you see during the cooler months, with density expected to progress back into operational density range during the next two months.

If you look on the screen, you can see the orange circle represents the pre-March density, and then we are closing back on that level as we progress towards the end of April. BCI is refining also our Mardie salt production ramp-up profile based on our operational experience, the site performance, and insight from BCI's digital twin.

As indicated in prior updates, our first salt on ship timing remains weather-dependent. We are assessing the effects of recent weather events on salt production ramp-up with a view of delivering first salt on ship in a timely and efficient manner.

BCI's Mardie operation is located in the Pilbara, where for decades, salt has been produced. This chart, if you can see on the screen, is the annual export volumes from the Pilbara of salt for the last 20 years, as published by the WA State Government.

We've overlaid on this chart the tropical cyclones that were either category 4 or category 5. As you can see from the historical data, that there is no suggestion that there's any correlation between tropical cyclones and the export volumes in Western Australia, as you can see from the established salt producers and the volumes that they produce each year.

During Mardie's ramp-up phase, however, tropical cyclones may disrupt our salt operations until the salt pavement matures and we have got enough inventory on hand. These were some of the pictures that I referred to earlier.

The one on the left is a plate that you place in the bottom of the crystalliser. This plate gets pulled out, and then you measure the thickness of the pavement with a vernier, the ability then to measure it accurately to the millimeters.

As of this morning, the production report indicated that our pavement is now 9 thick, and that's double what thickness was of last Tuesday. Positively, since the end of the quarter, the operations have resumed, pond density has been increasing, and salt is reforming in our crystallisers.

This is a clear indication that the salt growth is on track, and this is something we are now seeing progress of every day. We're continuing to make good progress towards our construction milestones, with cumulative capital expenditure now totaling $1.1 billion.

While construction progress was interrupted during the quarter with cyclones Mitchell and Neville, there was no material impact to our plant, equipment, and infrastructure, and post-cyclone maintenance kicked off. During the quarter, lining of the first two crystalliser cells was also completed, enabling a safer and more predictable harvesting environment.

Lining of cells 3 and 4 also resumed on the 12th of April. The remaining crystalliser cells will continue to be lined progressively as we ramp up towards steady-state production.

The design phase of the salt wash plant also continued to advance, reaching 92% completion, with major procurement items remaining on track for delivery in the June quarter. Construction is progressing alongside the commencement of concrete installation works.

At the Port of Cape Preston West, construction of the marine package continued to advance, with a contract awarded for the remaining detailed works, including navigation aids, berthing and mooring piles, and the installation of catwalks. Importantly, with all key approvals secured and contractual arrangements in place, I'm pleased to share with you that as of yesterday, we've officially commenced dredging our channel of our port.

Steve will now take us through the financial highlights.

Steve Fewster

Thanks, David. Total construction costs now sit at over $1.11 billion, having spent $67 million this quarter.

The largest packages of works that remain include the dredging, and you just saw a photo of that, the balance of the crystalliser sealing, which will happen progressively, and the salt wash plant. The progress being made on these three major construction areas continues to support our confidence of remaining on track and on budget.

As mentioned earlier, we drew $50 million from our syndicated debt facility during the quarter. At the end of the quarter, BCI had available liquidity totaling $522 million.

With construction costs at $1.11 billion and our pre-revenue operating expenditure at $259 million, BCI has invested almost $1.37 billion in the Mardie Salt operations. With approximately $333 million required to complete construction and available funding of $522 million, we remain fully funded to complete construction, as well as meet our working capital requirements through ramp-up.

To date, we have successfully completed 10 drawdowns totaling $496.8 million as at the end of March. The Port of Cape Preston West is a strategically valuable asset for BCI and for the region.

This is a multi-user port designed to export around 20 million tonnes per annum of bulk commodities, including salt, SOP, and potentially iron ore. At nameplate capacity, Mardie Salt-only operation needs are around 5.5 million tonnes per annum, leaving approximately 14.5 million tonnes of surplus capacity.

This presents a real opportunity to support other proponents in the West Pilbara who require access to this valuable port infrastructure. At the end of March, construction of the marine package had progressed to 94%.

As David mentioned, we commenced dredging of the berth pocket and navigation channel this week. This is a critical step in enabling the loading of deep-sea, ocean-going vessels with industrial salt from the Mardie operation.

I'll now hand back to David to talk about SOP.

David Boshoff

Thank you, Steve. Sulphate of potash is a key byproduct of our salt operation and an important future revenue stream for BCI.

SOP is a high-value, premium fertilizer, different from the more common muriate of potash. Unlike MOP, SOP contains sulphur as well as potassium, making it ideal for high-value crops such as fruits, vegetables, and nuts.

It plays a critical role in improving crop quality, yield, and food security, particularly in regions with nutrient-depleted soils. During the March quarter, the KTMS SOP crystallisers transitioned from batch operation to continuous operation in steady-state performance, marking a very important step in proving up the process at scale.

We've also completed structured technical and commercial assessment of submissions for the SOP pilot plant preliminary engineering design, and this is the Class 4 capital estimate. Following this process, two proponents have been selected to progress to the next phase, with work now advancing in line with our expectations.

Subject to final outcomes, the successful proponent will then be engaged to commence the FEED study, moving us one step closer to de-risking and progressing the SOP pathway. While our focus remains on safely ramping up our operations and completing construction, we continue also to prioritize sustainability.

This included quarterly monitoring of the mangroves, samphire, and algal mats, marine turtle monitoring, and migratory shorebird surveys, to name just a few. We've also continued to deepen our engagement with traditional owners, working closely with the Wirrawandi Aboriginal Corporation and its newly established commercial arm, Minari Enterprises, to progress initiatives that support sustainable economic participation.

A key example of this is the development of a commercial partnership policy. This is designed to enable WAC members to establish viable, low-risk service businesses aligned with on-country activities.

This has already been brought to life in practice, with Wirrawandi-owned businesses delivering an in-person cultural awareness training at our Perth head office during February, facilitated by Yaburara and Mardudhunera elders. This program will now also be rolled out across Perth and the Mardie teams.

We're also proud to extend our partnerships with Karratha Senior High School in 2026, reinforcing the ongoing commitment to local education, delivering long-term, positive outcomes for our community. As we close out this quarter, we do so by consistently applying our values and doing what we said we would do.

Our salt operation and production ramp-up is well progressed as we create sustainable, multi-generational benefits for our shareholders, local communities, as well as the broader Australian economy. This brings us to the end of the presentation, and we will now move to questions.

If you haven't already, please submit your questions in the live Q&A tab on the right-hand side of your screen. Thank you.

Moderator

Thank you, David and Steve. We've got a couple of questions that have been lodged.

The first one is: can you elaborate on the differences between the primary and secondary crystallisers, and how the salt moves to the secondary if it falls out of suspension in the primary?

David Boshoff

It's a great question, thank you. The primary crystallisers is where our production happens.

Some of those pictures that you saw on the screen was our primary crystallisers. That's where you harvest salt.

When you've crystallised the majority of your salt in your brine, the brine then would flow through to your secondary crystallisers. The secondary crystallisers then used to drop out other chemical components before the brine water is then introduced into the KTMS crystallisers.

That's the full circuit, of course, the SOP circuit. After the KTMS crystallisers, the brine is then returned to Pond 8, and that then recirculates back into Pond 9 and then returned back into crystallisers.

The reason why that's designed in that way is to ensure that the maximum salt is extracted, and of course, KTMS SOP is extracted from the brine. That is then recirculated through the system until it's finally discharged into the ocean.

Moderator

Thank you, David. Steve, we've got a question around what proportion of our cash flow do you expect SOP to provide?

Yeah.

Steve Fewster

SOP at the moment, our forecast is our salt-only business will deliver EBITDA of around $285 million, and that's at full nameplate capacity. When we get SOP up and running and if it achieves that 140,000 tonnes per annum production that we anticipate it will, it's expected that will generate around about $100 million in EBITDA.

Between now and when that EBITDA arrives, we need to complete the trial, the pilot program, which we feel confident will occur. In all likelihood, an FID, or final investment decision, on the SOP plant is most likely going to happen towards the back end of next year after we run the trial for 12 months.

Moderator

Excellent. Thank you, Steve.

That concludes the questions that have been lodged.

David Boshoff

Great. Thank you, everyone, for joining us today.

Steve Fewster

Thank you.