Q3 FY2026 · Earnings Call TranscriptApril 30, 2026

Operator

Welcome to the Liontown March quarterly call. Following the formal presentation, there will be a Q&A session for investors and analysts.

Participants can ask both text and live audio questions during today's call. To ask a text question, select the messaging icon, type your question in the box towards the top of the screen, and press the send button.

To ask a live audio question, press the request to speak button at the top of the broadcast window. The broadcast will be replaced by the audio questions screen.

Use the dial-in number and access PIN provided to ask your question via the phone. Alternatively, for those on a home or personal network, you can ask your questions via the web by pressing join queue.

If prompted, select allow in the pop-up screen to grant access to your microphone. If you have any issues using the platform, dial-in details can also be found on the homepage under asking audio questions.

Text questions can be submitted at any time, and the audio queue is now open. I will now hand over to Tony Ottaviano, Managing Director and Chief Executive Officer of Liontown.

Tony Ottaviano

Thank you, Luka, and good morning, everyone. Before I launch into the presentation, I'd just like to introduce who else is going to accompany me on this presentation.

There's Ryan Hair, Chief Operating Officer; we've got Greg Jason, our CFO; and we've also got Grant Donald, our Chief Commercial Officer. I'll start by saying this is a defining quarter for Liontown.

If we go to the next slide, please, Luka. There are five things I want you to take away from today, and mirroring what's been said on this slide.

Firstly, cash on hand grew by $33 million this quarter, closing at $424 million. Operating cash flow alone was $55 million, and Greg will show this in a later slide.

For the first time since production commenced, the operating cash flow funded the business in full. After capital investment in the asset and net financing flows, we will still end the quarter well ahead.

This is the strongest financial quarter since production commenced. It's also worth noting that the Port of Geraldton was closed for several days at the end of the quarter due to the cyclone threat by Cyclone Narelle.

That delayed two of our shipments. One slipped into April, and the other departed the last day of March.

The cash receipts associated with that 31st of March shipment was approximately $64 million. The underlying cash-generating capacity of the business this quarter was even stronger than the reported $33 million.

Secondly, the market conditions are strong, and our realized pricing reflects that. Our average realized price for the quarter was $1,845 per dry metric ton on an SC6 equivalent basis, up 87% quarter-on-quarter.

The structural setup in the lithium market is compelling, and we're now capturing this through our contracted sales. Again, Grant will go through the market in some detail in his section.

We are delivering on plan. We've achieved our 1 million, 1.5 million ton per annum underground run rate target early in the quarter, ahead of schedule.

The ramp-up is tracking to plan. The orebody is performing as modeled, and the grade reconciliation against the resource model remains strong.

Again, Ryan will go through this in some detail in his section. Fourthly, costs remain on track.

Unit operating costs for the quarter were $981 per ton, and were within our FY26 guidance range. We're continuing to manage the ramp-up, the transition through a variable feed mix, and the fuel crisis by ensuring our business optimization focus remains strong and disciplined.

Finally, the pathway to 70% recovery is now confirmed. We've demonstrated 70% recovery on clean ore, underground ore, as we had planned and as we have identified to the market.

This is sustained across three, the first three weeks of April. The plant is performing as designed and as expected.

Now let me go through a little bit more detail in the next slide, please. This slide gives you the quarter at a glance.

As the subtitle says, we are delivering on all fronts as the underground ramp-up continues. Let me walk through each of the tiles for you.

We've had production of 96,000 tons. As we highlighted in our half-year results, Q3 had fewer calendar days, and we ran a planned plant shutdown during that period.

Production is on track. We've had sales of 84,000 tons across five parcels.

We finished the quarter with significant inventory in port, around 26,000 tons of salable concentrate. As I mentioned earlier, the inventory build reflects the Cyclone Narelle impact at Geraldton.

It's a timing issue, not a market issue. Pricing, I've already spoken about the $1,845 a ton.

The costs, unit operating costs of $981 per ton. This is a fully loaded unit operating cost, right?

It has leasing costs in there, inventory movements. It's a fully loaded unit operating cost, consistent with our prior disclosure around unit operating costs.

We want to make sure that we are being compared on an apple-for-apple basis. It's an 8% increase on Q2, reflecting the transitional feed mix and the ramp-up.

This remains within our FY26 guidance range. Finally, the cash, and again, the headline number of $424 million is the $33 million of positive net cash flow generated this quarter.

I've already mentioned around the operating cash flow for the first time fully funding our business. As the banner shows, FY26 guidance is maintained across all metrics: production, costs, all-in sustaining, and capital expenditure.

I'll now move on to Ryan to give us the health and safety and environment update.

Ryan Hair

Thanks, Tony. I am on-site today at Kathleen Valley, apologies in advance if there's any unintended background noise.

Our renewable power penetration held at 85% for the quarter, reflecting the investment in our wind, solar, and battery hybrid system, and reducing our exposure to gas and diesel. On safety, whilst our TRIFR has moved from 11.55 to 10.53, that movement is well within normal variation on a quarter-to-quarter basis.

We're not reading anything into it, and we are continuing to stay focused on building a safety culture that prevents injuries and reduces high-potential incidents. A healthy level of safety observations is a leading indicator of engagement, and we want to continue to see this indicator and the quality of safety interactions continue to build.

Next slide, thank you. I'll now walk through the operational story for the quarter, starting with mining.

As Tony indicated, we hit our 1.5 million ton per annum underground run rate ahead of schedule. The target was set for the end of March.

We achieved it early and sustained it through the quarter: 402,000 tons mined, up 31% on Q2. As we've highlighted previously, and as Tony mentioned, the orebody continues to perform as expected with grade reconciliation and stope dilution outcomes in line with expectations.

Our fleet capacity continues to build. An additional jumbo and an additional haul truck arrived and went into production during the quarter, lifting both development and haulage capacity.

This improvement and increase in fleet capability will continue, particularly as we get into developing the new development areas for the expansion in the Northwest Flats orebody. Looking forward, ongoing level development will unlock wider ore zones.

The next material step-up in our extraction rates is expected in Q2 FY27 as we ramp towards the 2.8 million ton run rate by the end of FY27. Next slide, thank you.

Turning now to the plant, the plant performance this quarter reflects exactly what we expect at this point in the open pit to underground transition. Plant availability was 90%, reflecting the planned shutdown schedule.

Combined with fewer calendar days in the quarter, we processed 614,000 tons and producing 96,000 tons of concentrate. Global recovery for the quarter was 61%.

Through Q3, the underground to open pit feed split was similar to Q2, but the quality of the open pit material was lower than the previous quarter, leading to a slightly lower recovery. As Tony did mention in his opening remarks, at the quarter end and into the first part of April, while processing clean underground ore, the plant delivered 70% recovery, exactly what it was designed to do.

As we've said in previous updates, plant recovery is fundamentally a function of the feed mix. Looking forward, the feed mix will be predominantly underground, with the remaining open pit stockpiles blended in during FY27 and Q4 of this year.

Turning to the next slide, I'll explain the recovery trajectory in a bit more detail. On recovery, reading left to right across the full March quarter, the underground mix was 48%, and recovery, as we've said, was 61%.

For the whole of the March month, underground stepped up to 60% of the feed, and recovery lifted to 64%. In the first three weeks of April, underground was 67% of feed, and recovery had been running steady at 70%.

These results are very clear. As underground ore becomes the dominant source across Q4 and beyond, which it is now, we expect to sustain that 70% recovery target.

It validates the recovery pathway that we have been outlining for some time and underpins our confidence in delivering FY26 guidance, which we reiterated today. With that, I'll hand back to Tony to talk about guidance in more detail.

Tony Ottaviano

Thank you, Ryan. Guidance is maintained across all metrics, as I alluded to in my opening.

Concentrate production guidance between 365 to 450,000 tons is maintained, and so are the unit operating costs and all-in sustaining costs. This is against a backdrop of fairly challenging conditions through the geopolitical unrest and the headwinds we're receiving from the various fuel-related input costs.

There are three forward-looking statements that is worth flagging. Firstly, the feed mix is transitioning.

Underground ore, as Ryan has explained today, is expected to be the dominant feed source in Q4. We've already seen this trend accelerate.

In the first three weeks of April, we've seen the recovery improvement. Second point I want to note is the FY26 guidance is being maintained despite the geopolitical headwinds, which I've alluded to.

I think the rising fuel prices have had minimal impact on Q3 costs. Our business optimization focus remains strong and disciplined, as I said in my opening, and we will continue to look at ways of mitigating any of those headwinds to the best we can.

Thirdly, and this is an important point, we're reviewing the 2027 costs through our budget process. That's ongoing right now, and we're working through both the geopolitical issues and how they have an impact on our FY27 budget, but also the interaction of the planned brownfield expansion that we mentioned in our announcement the other day around the early works.

How that interaction goes with a brownfield expansion in an operating plant, and we will establish that as part of our study work and its impact on the budget when we announce the scope and the feasibility study at the end of September quarter. Then on the early works piece, the early works and long-lead item procurement has just been announced for the Kathleen Valley expansion.

These are additional to the current FY26 guidance on capex. They're not embedded in the unit costs or capital numbers we issued at the start of the year.

We expect the $15 to $18 million that we've mentioned expansion-related capital expenditure in FY26, separate from the figures on this slide. I will cover those numbers in a little bit more detail in the expansion slide.

To the next one, please. I'll now hand over to Greg Jason, our CFO.

Greg Jason

Thank you, Tony. Good morning, good afternoon, everyone, depending on where you are in the country.

I'm going to begin with this cash flow slide. As Tony said, quarter three was the strongest financial quarter we've had since production commenced, with operating activities funding all investing and financing cash flows to give us a net cash flow of $33 million.

Operating cash flow improved significantly again from break-even in quarter two to $55 million for this quarter. We had $165 million of receipts, which was a $37 million increase on the prior quarter, and it reflected the higher realized prices.

As Tony also said, we'd have had another $64 million in the quarter if Cyclone Narelle hadn't delayed a shipment until 31st of March, and we subsequently received $64 million Aussie in April. Production and other operating cash costs decreased to $113 million, and that reflects the completion of open pit activities and the fact that the underground mine is still ramping up to 2.8 million by the end of FY 2027.

Therefore, the amount of mining cost hasn't taken the place of the open pit that's come to an end. We had $22 million of growth capex in the quarter, very similar amount to Q2, and again, it predominantly related to underground development.

$4 million of sustaining capex was a couple of million dollars higher than the prior quarter with different projects being executed across those two quarters. We received a $10 million refund from EFA, and that reduced a security bond arrangement with Zenith for the Kathleen Valley Power Station.

There's still $10 million of bond related to that. We closed the quarter with $424 million of cash, 26,000 tons of salable product in inventory.

I know it's old news, but we also recorded the LGES conversion of debt into equity. There was $482 million of liabilities in debt and derivatives at 31 December that were removed from our balance sheet in February.

Our net cash at 31st of March was $61 million Aussie. Of course, that puts us in a really strong position for the continued ramp-up, the expansion that we talked about in the announcement yesterday, and other growth projects.

Could you please move to the next slide, which is the quarterly financial metrics? Looking at the other metrics beyond the cash, our revenue increased by just over 50% to $197 million.

The increase in realized price significantly outweighed the reduction in tons shipped during the period. The cyclone also caused a 12,000-ton parcel to be delayed from March until April, and so there was almost $30 million of revenue that moved from March to April because of that delay.

Tony's talked about the increase in realized price, 87% on an SC6 equivalent basis. The Aussie dollar equivalent was a bit lower because of appreciation of the Australian dollar relative to the US.

As always, the realized price, 1,845, reflects the contract mix, the exposure to different indices of the mix of QPs, some of which are forward and some of which are backward-looking. We had a $71 increase in the unit operating cost to $981, and that was fundamentally driven by the lower production tons, which in turn was driven by the feed mix, as Ryan talked about.

Fuel prices had a minimal impact on unit costs during the quarter. Our supply is contracted.

It has not been interrupted to date. Like everyone, we continue to watch it closely.

We are maintaining full-year guidance of unit operating cost, $855 to $1,045. All-in sustaining went up by $192 to $1,251.

The unit operating cost impact of $71 flowed into that. We had almost $80 per ton higher induced by the higher price driving higher royalties, a couple of million dollars of extra capex in sustaining, and the lower tons accounts for the rest of the difference.

I'll now pass back to Grant or to Tony to talk about the market outlook.

Grant Donald

Thanks, Greg. If we can go to the next slide, thank you.

Look, the market has been very strong during the quarter. We've seen significant physical tightness in the market, which is demonstrated by the drawdown in weekly lithium carbonate inventories you can see in the chart on the top right here.

Even more pronounced when you convert this from total tons to days of inventory as the market's grown. Typically, the market sat at around 40 to 45 days' worth of inventories.

We're now down below one month, well below one month of inventories. This is, I guess, against the normal seasonality you would see in this time of year, as you can see from the chart and the yellow line that's deviating from prior years.

This has been exacerbated by some supply disruption, which continues to create uncertainty both in terms of volume and also in terms of restart timelines. Brownfield restarts will start to come in towards the second half of this year.

This is really the only source of new supply with any near-term prospectivity, with greenfield supply taking three to five years of permitting, financing, construction to come into the market. On the demand side, we, as I said, seen very strong demand from customers.

We've just back from a trip to China where, I think the demand continues to be extremely robust with an ability for us to place many more tons than we actually produce in this current outlook. I think, importantly, we're also seeing a significant increase in pack sizes across vehicles in China and globally.

This is actually accelerating lithium demand over and above a pure EV sales growth. We have also, I guess, benefited from the uncertainty and increased fuel prices in terms of that having an impact of driving increased EV demand.

We've seen that in local markets, but we've also seen that phenomenon globally. This is, in my view, not just a short-term factor that goes away when oil prices go back to normal, but is a fundamental step shift in demand profile for EVs and electrification.

With that, I'll hand back to Tony.

Tony Ottaviano

Thanks, Grant. A good segue, strong market.

Here's the commitment we've made as a company to the early works for Kathleen Valley expansion. Yesterday, we announced we're proceeding with the early works and long-lead item procurement for the Kathleen Valley expansion.

This is ahead of FID, which we planned to publish at the end of quarter one FY 2027. Now, there's two elements to this.

There's a strategic rationale, which I'll talk about in a minute, but there's also a risk mitigation rationale. Committing to the long-lead items and mobilizing the team now mitigates schedule risk and equipment pricing risk in a tightening market.

We've seen the impacts already start to percolate through from the fuel crisis. We want to get ahead of that.

It supports a robust capital cost estimate at FID by having some of these early things put away and position us to execute immediately once the board approves the expansion. The committed program is set on this particular slide.

It has six elements covering the ball mill, which is a critical piece and part of the critical path; pre-development drilling; underground development at Northwest Flats, which we've been flagging to the market for some time about the optionality that gives us, plus accessing it from the bottom of the open pit, as this diagram here indicates. There's also stage one of the permanent mine services area, which was a piece of infrastructure that we deferred during the downturn in an attempt to preserve capital.

Then there's the third paste pump that we want to put in to allow us to feed both Northwest Flats and Mt Mann simultaneously. Now, there's the capital component.

We've mentioned that these early works is between $15 to $18 million, and we're going to commit about $77 million of capital expenditure ahead of FID, right? Further capital and operating cost details, we'll provide you in the FID announcement.

Then finally, the strategic logic. Expansion at Kathleen Valley is currently our most value-accretive growth option.

These commitments lay the foundation for growth, and demonstrate our confidence in both the market and, more importantly, the operation. If I go to the final slide, please.

Just to recap the overall presentation, I won't go through each of these, but just to say that in closing, Liontown is now a producing, cash-generating, self-funded, Tier 1 lithium operation. We've simplified our balance sheet.

The market is structurally tightening, and we have a defined pathway to expansion with the early works program underway. The team is now building for what comes next.

We enter the June quarter with genuine momentum. On that point, I now turn to some Q&A, and I'm happy to answer it with the team.

Operator

Thanks, Tony. If you have not yet submitted your text question or joined the live audio queue, please do so now.

I will introduce each caller by name and ask you to go ahead. You will then hear a beep indicating that your microphone is live.

We will limit questions to two per caller. Our first question comes from Austin Yun of Macquarie.

Austin, please go ahead.

Austin Yun

Thank you. Morning, Tony, Ryan, the team.

Just two questions. The first one is on the run rate.

Good to see it's already running at a 1.5 million ton underground. How should we think about the continued ramp-up?

Is that a step change, or is that kind of a linear run out till your target? Thank you.

Tony Ottaviano

Austin, I'll let Ryan give you his response.

Ryan Hair

Thanks, Tony. Thanks, Austin.

I think the best way to think about this, Austin, is that over the next two quarters, we will be consolidating this run rate. Being part of what we wanted to demonstrate was that, in fact, if you do the math, slightly ahead of the 1.5, at the 1.6 rate for the quarter.

We'll consolidate that over the next two quarters as we're continuing to develop out the levels below. As we've said in the announcement, from Q2 FY27, you'll see another step change.

From that point, think about it as fairly linear. We'll have developed those levels, and then that will continue to ramp to 2.8 by the end of the FY.

Austin Yun

Cool. Thank you.

That's clear. Second one is just on the recovery performance.

Understand this quarter was impacted by the feed mix, and the early numbers, that is already showing a marked improvement in April. Keen to understand, when you switch to 100% of the clean, high-grade ore from underground, what's a kind of achievable recovery rate you'll be looking at?

Can we get close to 75% or 78%? Thank you.

Ryan Hair

Thanks, Austin. It's a good question.

Look, what I would say in answering that is that what we try to provide in that slide, which shows the 67% underground and 70% recovery, is that is actually a blend. That's actually got effectively 2/3 underground, 1/3 open pit material, and 70%.

I think it's fair to extrapolate from that that at 100% clean ore, that it is higher than 70%. I think you'd be fully aware of our DFS numbers around that kind of mid, maybe creeping into the high 70s.

Still think that the plant is capable of doing that. On any given day, on a clean underground mix, the plant does demonstrate that.

Again, for those who run these types of plants or who have observed how they run, doing that consistently is what we're focused on. I think in the longer term, you can assume that we'll be higher than the 70s and trending towards the DFS numbers over time.

Operator

Thank you. Our next question is from Stuart Howe of Bell Potter Securities.

Stuart, please go ahead.

Stuart Howe

Thanks, Tony. Just on guidance, is unchanged for production, and if you look at year-to-date, it implies a wide range for Q4.

Just wondering, what are some of the risks apparent to maintain such a wide range for Q4?

Tony Ottaviano

Thanks, Stewie, and for the question. Look, for us, we've got three quarters of actuals, you've got one more quarter left, and we can extrapolate basically where we'll fall within guidance.

To us, we are still transitioning, as Ryan has already mentioned, and we're still ramping up. We're quite confident with that guidance.

Stuart Howe

Okay. Just secondly from me on fuel supply, you noted that it's all secured under contract and remains uninterrupted.

I guess can you talk a little bit more about this? Is there anything to give us further comfort that you will have security of supply and perhaps some sensitivities if you've arranged any?

Tony Ottaviano

That's also a good question, Stewie. I'll break it up into two parts.

I'll answer the first bit, and then I'll get Ryan or Greg can jump in on a few metrics. For us, what is been crucial, I think it's been a systematic strategy from the get-go.

We wanted to partner with major strategic partners in the supply and construction of our operation. Our fuel contract is with Viva, and so they're a Tier 1 producer, and therefore we've got confidence in their schedule.

Equally, our transportation is done by Qube, primarily for our product, and there are a number of others that do the supply of our consumables to site. Again, Qube has the size and the scale to manage their fuel supplies, we're very confident that they will continue to produce.

Partnering with these large partners under proper contracts has served us good to this stage. Now, in terms of some of the financials, maybe I'll turn to you, Greg.

Greg Jason

Yeah. When we looked at the diesel, as Tony said, it's a small component relative to the overall business because of the renewable power generation that we have.

Nonetheless, we do have that cost, and it was sub a couple of percentage points of our cost base before the Middle East crisis drove price increases. On a dollars-per-ton basis, approximately $1 per liter on diesel or Jet A-1, which impacts the aviation for the charter flights, is worth somewhere around $25 to $30 per ton unit operating cost finished product.

That's for as long as it prevails.

Operator

Thank you. Our next question is from Jacob Li of Barrenjoey.

Jacob, please go ahead.

Jacob Li

Hey, morning, Tony, Ryan, team. Could you please provide some early color into your thinking around pathway to 4 million ton per annum expansion?

If 4 million ton per annum is still the number, I guess my question is in two parts. First, you talked to a capital-efficient incremental debottlenecking process previously.

Apparently, you've got key approvals and major infrastructure in place with some additional tonnage you can unlock from Mt Mann and Northwest Flats, which were part of your original 3 million ton per annum plan before full expansion. Then I guess, what about other lead items to 4 million ton per annum, the addition to ball mill, paste pump you've already committed to, ventilation raises, paste fill plant works, water, etc.?

In the last update, I think we talked about $100 million for the process plant and $150 for the mine development. Is that still the right ballpark?

Sorry, don't want to start front-run this, just wanted to get some early color into your thinking around your pathway to 4 million ton per annum expansion, please. Thanks.

Tony Ottaviano

There was a lot in that question, thank you for that. What I will say on the capex side is, and I'm not going to do any early predictions, we're going to let guys and girls do the work and properly, given how dynamic the market is, properly scope this and properly analyze the capital and operating costs.

We'll give you that when we're ready in Q1 of next year, financial year. In terms of what's the ultimate number, well, again, that's part of the study, right?

Capital costs, what I will say is when we published those numbers you quoted, that was in the DFS. That's 5 years ago.

I'll leave it to you to decide whether there's any inflation on that number. In our capital costs, there will be costs associated with the expansion.

There's costs in these early works around accelerating. When we did the Northwest Flats piece, it wasn't just to service the 3 million tons, it was also to develop the operations for the 4 million, because we were going straight from 3 to 4.

When the downturn came, we mothballed Northwest Flats. I think to answer your question in conclusion, you've got to let us do the work first.

Jacob Li

Okay. Thanks, Tony.

Just a follow-up. Is there opportunity to sort of unlock 3 million ton per annum in the next one or two years before the full expansion?

Was probably my question just now. Thanks.

Tony Ottaviano

Okay. Sorry, as I said, there was a lot in that question, I apologize if I missed that bit.

I think the nature of this expansion that we've already identified to the market is this debottleneck, unlock capacity. Things like buying some more flotation cells, which is part of the area that needs upgrading, will deliver that; putting the ball mill will deliver that.

If you're saying to me, is there a possibility to go to 3 million tons in the next couple of years, well, it all depends on the underground ramp-up, because we've said the underground ramp-up will be at 2.8 million tons per year run rate at the end of financial year 27. We're mine-constrained until that point is reached, and then beyond that, we will unlock more capacity as we unlock more capacity from the underground.

Jacob Li

All right, that's clear. Thanks, Tony.

Appreciate it.

Operator

Thank you. Our next question comes from Ben Lyons of Jarden Securities.

Ben, please go ahead.

Ben Lyons

Thank you. Good day, Tony.

Tony Ottaviano

Hi, Ben.

Ben Lyons

Maybe just further on that last question. To talk about the mine constraints, but you've still got a heap of the OSP material on hand, and presumably you just balance that versus that sort of 1.5, 1.6 run rate that's coming out of the underground.

You can still run the plant, let's call it, I don't know, 2.5, 2.6 capacity, allowing for your shutdowns and maintenance. Is that the right way to think about it, just a consistent processing of the OSP, which supplements every time that comes out of the underground for the next 12 months or so?

Tony Ottaviano

Thanks, Ben. Not exactly.

The stockpile of OSP has been reduced substantially in order to get us to where we are now. We're going to be less reliant on OSP stockpiles going forward, and therefore that's why we're saying FY27, end of FY27 for 2.8.

It won't be supplementing the feed right up until that point.

Ben Lyons

Okay. Cool.

Do you have a sense for, is it maybe 800,000 tons remaining or 600, 700?

Tony Ottaviano

I'll let Ryan answer that.

Ryan Hair

At this stage, we've got a little under 400,000 tons of OSP remaining. Post-sorting, bearing in mind that part of the sorting process separates the ore and waste, and so the actual accepts feed will be somewhat lower than that.

It's probably circa 200 to 250,000 tons. As Tony has indicated, we will continue to feed that OSP accepts material through the plant, and that will kind of be blended in with the underground, but that will not last until we fully ramped up the underground mine, Ben.

I hope that makes sense.

Operator

Thank you. As we have no more questions in the queue, I'll now hand back to Tony for closing remarks.

Tony Ottaviano

Thanks, Luka. In closing, for me, the numbers this quarter reflect timing and not trajectory.

The cyclone closed the Port of Geraldton, which would have made our numbers even stronger than they are today. We're looking forward to the next quarter and the next 12 months.

There's a lot of work going to be planned with the expansion and further growth. We're very strong, and we're fully committed to the next phase of our operations.

Thank you, everyone, for listening, and I thank my team for the hard work that's gone into producing today's materials and the results.