Operator
Good afternoon and welcome to Ignitis Group's earnings call for the first nine months of 2026. Today, we will take you through our operational, financial, and strategic performance for the reporting period, followed by a Q&A session.
Before we begin, please note that today's presentation contains forward-looking statements based on management's current expectations and assumptions. These statements are subject to risks and uncertainties, and actual results may differ materially from those expressed or implied.
With that, I will hand over to the management team to begin the presentation.
Darius
Good afternoon, all, and thank you for joining our earnings call. Over the first nine months of 2026, we delivered robust financial performance, reflecting continued strategic progress with key highlights as follows.
First, our adjusted EBITDA reached €430.4 million, representing a 6% year-over-year increase. Second, we continued our strategic progress across green capacities portfolio delivery, with 2.1 GW of installed capacity and 0.7 GW of assets under construction, an increase of 0.1 GW in the first nine months of 2026.
This increase reflects to the financial investment decision for the 107 MW and 215 MWh Tume battery energy storage system in Latvia. Third, we preserved a stable balance sheet with net debt to adjusted EBITDA at 3.4 times, and BBB+ credit rating reaffirmed by S&P, and inaugural Baa1 credit rating assigned by Moody's, both with stable outlooks.
Last, the dividend increase, supported by the group asset rotation gain realized from the partial disposal of Vilnius CHP in Q1 2026. In accordance with our dividend policy, we intend to increase the dividend for 2026 by 10% compared with 2025, to €1.504 per share, or to €108.9 million in total.
This would establish a higher base for the future dividend growth of at least 3% annually and increase DPS floor for strategic period over 2026 to 2029. As part of our intention for the nine-month period ended 30 September 2026, we propose to distribute a dividend of 40 euro cents per share, or €29.0 million in total, subject to decision of our EGM to be held on 10th of December.
Let me now take a deeper dive into our strategic progress during reporting period. First, looking at our progress at our green capacities projects under construction, just recently, the last Friday, we announced the reaching COD at 174 MW Tume solar farm in Latvia.
This led to our installed capacity increase to 2.3 GW. With total investments of up to €106 million, the project is one of the largest solar farms in Baltics and is expected to meet the electricity demand of around 85,000 households annually.
On top of that, we have five further projects under construction, with a total capacity of 0.5 GW and investments of around €317 million. The portfolio includes one hydro expansion project and four BESS projects.
To start with Kruonis 110 MW pumped-storage hydroelectric power plant expansion project, we have already invested €118 million out of total 150. The project is around 90% completed.
All main components have been assembled and civil works are nearing completion, with final adjustments and auxiliary equipment installations ongoing. The project will increase the plant's total capacity to 1.1 GW and significantly improve the flexibility and reliability of Baltic energy grid.
Next, our four BESS projects under construction, with total capacity of almost 400 MW. Starting with 147 MW Kelmė BESS project, we have invested €22 million out of total 63.
Deliveries of all battery units were completed. The project is co-located with the 314 MW Kelmė wind farm, allowing it to benefit from shared high-voltage infrastructure.
Moving on, 99 MW capacity Kruonis BESS project, we have invested €15 million out of total 47. Deliveries of all battery units were completed.
As a standalone project, it will unlock up to 1.1 GW of flexibility through operational synergies with Kruonis pumped-storage hydroelectric power plant. Next, 45 MW Mažeikiai BESS project, we have invested €6 million out of total 21.
Deliveries of all battery units were completed. The project is co-located with 63 MW Mažeikiai wind farm, allowing it again to benefit from shared high-voltage infrastructure.
Finally, 107 MW Tume BESS project, we have just recently made the final investment decision for this project. It is co-located to 174 MW Tume solar farm, here we are maximizing the project's efficiency through shared grid infrastructure and unified connections.
Moving to our sustainability performance, over the first nine months of 2026, our net green share of generation increased by 22 percentage points to 88%. Our electricity generated decreased by 18% to 2.5 TWh.
The decrease was driven by lower generation at Elektrėnai Complex, which was partially offset by higher generation from green capacities. Looking at carbon intensity, our carbon intensity decreased by 23% as a result of lower electricity generation from natural gas at Elektrėnai Complex.
Lastly, on our safety, safeguarding the health and safety of our employees and contractors is among the group's highest priorities. However, during the reporting period, we had one fatal contractor incident.
We are committed to take every possible measure to prevent such tragedies in the future. Our employee TRIR increased to 1.6, driven by extensive network restoration works following the severe storm in Lithuania in August, while contractor TRIR improved to 0.63.
Finally, let me elaborate on intended dividend increase. We intend to increase the dividend for 2026 by 10% compared with 2025, to €1.504 per share, or to €108.9 million in total.
This intention is supported by group's asset rotation gain realized from the partial disposal of Vilnius CHP in Q1 2026 and is in accordance with our dividend policy. The increase would establish a higher base for future dividend growth of at least 3% annually and increase DPS floor for strategic period of over 2026-2029.
The updated DPS floor is around 7% above the original plan, reaching €1.64 per share in 2029 versus €1.54 previously. Following the dividend payment of 70.4 euro cents per share for the first half of 2026, we intend to distribute a further 80 euro cents per share for 2026.
We therefore propose to distribute half of this amount as a dividend for the nine-month period ended 30 September 2026, representing 40 euro cents per share, or €29.0 million in total, subject to decision of our EGM to be held on 10th of December. Decisions on the remaining dividend amount are expected to be made when allocating group's profit and loss for 2026.
With the strategic overview complete, I will now hand over to Jonas for financial update.
Jonas
Thank you, Darius. Let me start with our financial highlights for the first nine months of 2026.
Adjusted EBITDA grew by 6% year-over-year and reached €430 million, driven by stronger performance in Customers & Solutions and Networks. Adjusted net profit decreased by 18% and amounted to €146 million, mainly due to higher depreciation and amortization and lower financial activity results, which offset the adjusted EBITDA growth.
Our investments decreased by 18% year-over-year and amounted to €432 million, mainly due to lower investments in green capacities as several projects reached COD in 2025. Networks investments are at all-time high levels.
Return on capital employed decreased by 1.2 percentage points to 6.9%, mainly due to lower adjusted EBIT in green capacities and reserve capacities. Our net debt amounted to €2 billion, increasing by 2.5% due to continued investments.
Net debt to adjusted EBITDA improved to 3.4 times, and our FFO to net debt improved by 0.4 percentage points to 21.4%. Additionally, S&P Global Ratings reaffirmed our BBB+ credit rating, and while Moody's assigned an inaugural Baa1 credit rating, both with stable outlooks, confirming our strong financial position.
Finally, we paid a dividend of 70.4 euro cents per share for the first half of 2026 and intend to distribute a meaningfully higher dividend for the second half of 2026, as already presented by Darius. Let us now review our key performance indicators, beginning with adjusted EBITDA.
Firstly, Networks grew by 7% and amounted to €206 million, mainly due to higher RAB driven by increased investments. Secondly, green capacities decreased by 9% to €196 million, mainly due to lower captured prices and lower result of balancing capacity services.
Thirdly, reserve capacities decreased by 40% to €21 million, also mainly due to lower result of balancing capacity services. Finally, Customers & Solutions adjusted EBITDA amounted to €13 million, compared to -€43 million for the same period last year.
The increase was driven by the recognition of compensation for prosumer-related losses according to the new regulation and lower imbalance costs. Moving on to segment-level EBITDA performance, starting with Networks segment, 7% growth in Networks adjusted EBITDA was mainly supported by higher regulated asset base, which increased by 6% from €1.8 to €1.9 billion, driven by continuous continued investments in the electricity network.
It is important to highlight that after the reporting period, the continuity and stability of the network regulatory framework was maintained, with no significant changes to the methodology for the upcoming 2027-2031 electricity regulatory period. In addition, the regulator approved the regulatory parameters for 2027, including regulated asset base increasing by €0.3 billion to €2.2 billion, weighted average WACC increasing by 0.09 percentage points to 5.83%, and an additional tariff component of €30 million.
Next, green capacities segment. The main driver behind 9% year-over-year decrease was firstly, lower prices captured by our green generation assets, with the hedge price decreasing from €130 per megawatt-hour last year to €82 per megawatt-hour this year.
Secondly, lower result of balancing capacity services, mainly due to lower prices following market maturity. However, the decrease was partly offset by higher generation volumes, as well as lower imbalance costs and OPEX.
Next, let's move to reserve capacities segment. The segment posted 40% year-over-year decrease, which was mainly driven by lower result of balancing capacity services as the market is maturing, and and planned major overhaul of unit 7 at Elektrėnai Complex.
Finally, Customers & Solutions, adjusted EBITDA amounted to €13 million, compared to -€43 million last year. The increase came mainly on the electricity side, where the improvement was driven by the recognition of compensation for prosumer-related losses according to the new regulation and lower imbalance costs.
Having reviewed the segment results, let me now take you through our investment activities. In the first nine months of this year, our investments amounted to €432 million and were 18% lower than last year.
The decrease was driven by lower investments in green capacities as several projects reached COD in 2025. This decrease was partly offset by higher investments in the Networks segment, which are mainly driven by electricity distribution network maintenance investments, which includes cabling program.
Networks investments remain at all-time high levels. Turning to free cash flow, it amounted to -€35 million, as investments are still exceeding cash flow generated from operations.
Let us now review our leverage metrics. At the end of September 2026, our net debt amounted to €2 billion, increasing by €49 million, mainly due to continued investment program.
Our main credit metric, FFO to net debt, improved by 0.4 percentage points to 21.4%, supported by an increase in FFO. Our net debt to adjusted EBITDA improved to 3.4 times from 3.5 times at the end of 2025.
Finally, let us let us now look at our guidance for 2026. Following our strong results in the first nine months of 2026, we narrow our full-year adjusted EBITDA guidance to between €575 to €600 million.
Our previous guidance was €550 to €600 million. We have also updated the directional guidance of the reserve capacities segment.
We now expect lower year-on-year adjusted EBITDA, compared to stable previously, reflecting lower than expected results from balancing capacity services. Directional guidance for the remaining business segments remains unchanged.
Finally, we reiterate our full-year 2026 investments guidance of €590 to €690 million, with the main drivers remaining unchanged. With that, I will now hand over to Darius for the concluding remarks.
Darius
Thank you, Jonas. Let me now summarize our earnings call.
Over the first nine months of 2026, we delivered robust financial performance, reflecting continued strategic progress with key highlights as follows. First, our adjusted EBITDA reached €430.4 million, representing a 6% year-over-year increase.
Second, we continued our strategic progress across green capacities portfolio delivery, with 2.1 GW of installed capacity and 0.7 GW of assets under construction, an increase of 0.1 GW in the first nine months of 2026. This increase reflects to the final investment decision for the 107 MW and 215 MWh Tume battery energy storage system in Latvia.
Third, we preserved the stable balance sheet with net debt to adjusted EBITDA at 3.4 times, and BBB+ credit rating reaffirmed by S&P and inaugural Baa1 credit rating assigned by Moody's, both with stable outlooks. Lastly, the dividend increase, supported by group asset rotation gain realized from the partial disposal of Vilnius CHP in Q1 2026.
In accordance with our dividend policy, we intend to increase the dividend for 2026 by 10% compared with 2025, to €1.504 per share, or to €108.9 million in total. This would establish a higher base for future dividend growth of at least 3% annually and increase DPS floor for the strategic period over 2026 to 2029.
As part of our intention for nine-month period ended 30 September 2026, we propose to distribute a dividend of 40 euro cents per share, or €29.0 million in total, subject to decision of our EGM to be held on 10th of December. Lastly, we narrow our adjusted EBITDA guidance to between €575 to €600 million, with reserve capacities now expected to be lower year-over-year.
Also, we reiterate our investment guidance of €590 to €690 million. With that, thank you for listening.
Operator
Thank you to the speakers. We will now begin the Q&A session.
The first question is: In Customers & Solutions, €27.6 million year-over-year EBITDA increase in Q3 was mostly helped by the accrued compensation of a portion of prosumer-related losses incurred from March 2025 until the end of the reporting period. Can you please quantify it for Q3 and nine months of this year?
Jonas
In Q3 and also the same number for nine months, we have accrued around €30 million of compensation. After accounting for this compensation, the net result from prosumers in nine months of 2026 is around -€6 million.
It's still a negative number, but much more manageable than before. The regulation is in line with what we had expected in the beginning of the year.
Operator
The second question: The proposed dividend increase by 10% for 2026 will raise the DPS floor across the strategic period from 2026 to 2029, meaning higher cash distributions. At the same time, the group proposed higher CAPEX in Networks, +26% to €4.4 billion, under the updated 10-year investment plan.
These two separate actions look a bit contradictory. Could you help us understand the logic behind that?
Jonas
In our view, they are not contradictory. I think the dividend increase reflects the capabilities of the group.
On the investment side in Networks, this particular decision on the gross investments level, indeed, that's a sizable increase. If to look at net investments, the actual expected increase for the next four years strategic period is around 3%, not material, because majority of the extra CAPEX in Networks is expected to be funded through subsidies.
Operator
Third question: How is the dividend floor adjusted at least by 3% CAGR from the current basis? Within this, what is your target floor for 2029?
Jonas
Correct. The minimum growth which we have in our dividend policy is at least 3% annually.
With a proposed increase of 10% for 2026, that will have an impact for the whole strategic period and will result in dividend floor for 2029 of €1.64 per share.
Operator
Fourth question: What is the current status of Kruonis PSPH fifth unit expansion project?
Darius
We continue Kruonis PSPH construction works. The main components have been assembled, with civil works and interim inspections currently in progress.
Operator
Next question: What is the current status of Kruonis data center project and partner selection process?
Darius
Data center, on 11th of August 2026, we launched a partner search and selection process for development of data centers. Scope of the partnership includes transfer of controlling stake of UAB Kruonis DC and potentially other data center companies currently controlled by the group to potential experienced partner to lead further development, construction, operation, and management of large-scale data center project or projects in Lithuania.
The group notes that the start of the process does not imply that transaction will take place or it will take place in the foreseeable future and or to the extent indicated. Information on binding agreements reached with potential investor or investors will be published according to the effective legal requirements.
Operator
We have one more question: In which quarters of 2027 are the first battery storage projects in Lithuania expected to become operational?
Jonas
The Lithuanian BESS projects are expected to be launched in the first half of 2027.
Operator
The following question: Do you expect the temporary profit-sharing mechanism to expire at the end of 2026?
Jonas
Yes, in our view, the profit-sharing mechanism should expire at the end of 2026 because, again, we see that the market has reached certain level of maturity, the profit-sharing mechanism should be no longer applicable.
Operator
One more question on Polish battery project: What is the current development stage of the recently acquired 49 MW battery project in Poland, and when it is expected to become operational?
Jonas
The project is acquired in the development stage, we have not yet made a final investment decision for that project. When we make and if we make that decision, then we will communicate the dates expected for the launch of this project.
Operator
Next question: Can you please quantify the positive effect from the CHP asset disposal?
Jonas
Just a reminder, the total inflow from 49% stake sale in Vilnius CHP is €120 million. The invested amount into that project for 49% is equal to around €25 million, hence the gain was close to €100 million.
Operator
The following question: What is the driver of increased low end of the guidance?
Jonas
The main reason for the narrowing of the guidance is that we are coming towards the year-end, we have good comfort in our progress so far, hence we are narrowing the guidance range.
Operator
The following question: Provide the amount of one-off gain related to prosumers in the Supply segment, and the amount of one-off cost related to the storms in Networks, please.
Jonas
Yes, on the prosumer side, as mentioned before, the accrual in Q3 is around €30 million. The important element to note that it's not entirely a one-off because the regulation is continuous, for every year there will be a certain compensation included for prosumer losses.
Not entirely a one-off, and the amount accrued is around €30 million. On the Networks side, the amount of one-off costs related to the storm which were suffered and are mainly compensations to the customers is around €6 million.
Operator
Another question: Could you elaborate on the prosumers effect in Q3 on Customers & Solutions segment result? How much did it still dilute the results, and what was the effect of regulatory change?
Jonas
Again, as mentioned before, the €30 million accrual, after the accrual, the net negative result is around -€6 million for C&S for nine nine months of this year.
Operator
Another question on guidance: If Reserve Capacities have been revised lower, what has been updated upwards? What can we expect at the net income level for 2026 after nine months mark?
Jonas
On the Reserve Capacities, yes, we have revised it lower. No updates upwards.
It's just the comfort of seeing the good progress across the board, with some exception in Reserve Capacities. That's why we are narrowing the guidance for the remaining few months of the year.
On the net income level, we are not providing the guidance on net income for full year.
Operator
Additional question received: What has structurally changed with the Curonian Nord offshore wind project that you are submitting a proposal to postpone it?
Jonas
On Curonian Nord, it's the same things which we flagged already a year ago. It's both the demand forecasts are not materializing, and also on the supply chain side, also the CAPEX per megawatt has increased.
Operator
The following question: Despite growing adjusted EBITDA, adjusted net profit declined by 18% and return on capital employed fell to 6.9%. When do you expect these metrics to recover as new projects become operational?
Jonas
In short, of course, our main goal is to make sure that not only EBITDA, but also net profit grows. That is high on our agenda, and of course, new projects are expected to contribute positively to the net profit figures.
Operator
Another question: Is there a possibility that future dividend payments become tied to earnings or free cash flow instead of fixed annual growth rate?
Jonas
Currently, we don't see such an option. We are very much committed to a fixed rate plus minimum growth rate.
Sometimes that growth rate will be higher than the minimum rate, as demonstrated this quarter. We think that this policy provides a very good visibility to the investors, and we plan to continue with the current dividend policy in place.
Operator
The last question: When will you publish adjusted EBITDA guidance for 2027?
Jonas
EBITDA guidance for 2027 will be published together with the annual results at the end of February next year, as usual.
Operator
This concludes our earnings call. Thank you for joining us today.
Should you have any further questions, please reach out to our investor relations team. Thank you, and stay safe.
Already premium?