Good day, thank you for standing by. Welcome to Bitdeer's Second Quarter 2026 Earnings Conference Call.

At this time, all participants are in a listen-only mode. After the speakers' presentation, there'll be a question-and-answer session.

To ask a question during the session, you will need to press *11 on your telephone. You will then hear an automated message advising that your hand is raised.

Please be advised that today's conference is being recorded. I would now like to turn the conference over to your first speaker today, Tesh Stier, Head of Investor Relations.

Please go ahead.

Tesh Dahya

Thank you, operator, and good morning, everyone. Welcome to Bitdeer Technology Group's second quarter 2026 earnings conference call.

Joining me today are Jihan Wu, Founder, Chairman and Chief Executive Officer; Haris Basit, Chief Strategy Officer; and Michael Potter, Chief Financial Officer. Today's call will begin with Haris providing a review of our recently announced Tydal, Norway colocation lease agreement, followed by Michael with a review of our business segments and second quarter financial results.

Before management begins their formal remarks, I would like to remind everyone that during today's call, we may make certain forward-looking statements. These statements are based on management's current expectations and are subject to risks and uncertainties, which may cause actual results to differ materially.

For a more complete discussion of forward-looking statements and the risks and uncertainties related to Bitdeer's business and industry, please refer to the company's filings with the U.S. Securities and Exchange Commission.

I also want to note that we will be discussing certain non-GAAP financial measures and operating metrics today. A reconciliation of these measures to the most directly comparable GAAP measures is included in our earnings release issued earlier today.

These non-GAAP measures should not be considered in isolation from, or as a substitute for, the most directly comparable measures prepared in accordance with GAAP. As a reminder, changes to the fair value of our digital assets are reflected in GAAP net income and may introduce non-cash volatility into our reported results.

With that, I will now turn the call over to Haris.

Haris Basit

Thank you, Tesh, and good morning, everyone. This is our first earnings call since we announced the execution of our $4.7 billion colocation lease at Tydal, Norway, and I would like to begin by putting that agreement in context.

Over the past several years, we have worked to build a power infrastructure portfolio that we believe is well-positioned to support both our Bitcoin mining operations and our expansion into AI infrastructure. Tydal represents an important step in converting that portfolio into long-duration, contracted revenue, and it establishes AI infrastructure colocation as an additional pillar of our business alongside our AI Cloud, Bitcoin mining, and ASIC development and manufacturing operations.

We are pleased with the terms of this agreement and with the caliber of Volta as our counterparty. We view Tydal as an important proof point for this strategy, and we intend to pursue additional opportunities of this kind as they arise.

Agreements of this scale and complexity reflect the work of our team over the past several years, and I want to thank everyone involved for their efforts in reaching this milestone. With that, let me walk through the terms of the Tydal transaction in more detail.

On August 4th, we announced that our subsidiary, Tydal Data Center AS, has executed a 16-year colocation lease and services agreement with Volta at our Tydal campus in Norway. Under the agreement, we are delivering 121 IT megawatts supported by approximately 133 gross megawatts.

This will be spread across four existing data halls and will be configured to run NVIDIA GPUs. The lease is expected to generate approximately $4.7 billion in contracted base-term revenue over the initial 16-year term.

An 8-year renewal option, if exercised, would increase the potential contract value to approximately $8 billion over 24 years, with a tenant termination right at the end of year 10. The lease is structured as a modified gross arrangement.

Volta pays a combined base rent and service fee with a 3% annual escalator, and electricity costs are fully reimbursed on a pass-through basis, which protects our margin from energy price volatility and provides a highly predictable cash flow. Over the 16-year base term, we expect this agreement to generate average annual revenue of approximately $2.4 million per IT megawatt.

Importantly, Volta's obligations are anticipated to be backed by an institutional-grade credit structure. This anticipated credit enhancement meaningfully reduces our counterparty risk and improves the financeable quality of these contracted cash flows, which supports our plan to access attractive debt financing terms to fund the remaining development at Tydal.

Our remaining capital expenditure is approximately $500 million, which we believe is significantly more capital efficient than a typical greenfield data center build. We expect to raise project-level financing to fully fund our remaining Tydal capital needs and to provide significant additional capital.

Delivery is structured across two equal-sized phases, targeting December 31st, 2026 for the first phase and March 31st, 2027 for the second. A word on our tenant: Volta is a compute infrastructure developer focused on large-scale AI and data center deployments in power-advantaged markets.

Volta has announced a $10 billion strategic partnership with an AI lab and a broader development pipeline exceeding 1 gigawatt. In selecting Volta as our partner at Tydal, we evaluated their technical ability to execute a large-scale GPU deployment, the quality and enforceability of their anticipated credit support, and their ability to move rapidly to match the anticipated Tydal construction timeline.

It is important to note that Tydal will incorporate leading-edge NVIDIA GPUs, has one of the highest-reliability grid connections in Europe, is 100% powered by renewable energy, and has an extremely high energy efficiency with a PUE of approximately 1.1. Our broader power and infrastructure portfolio stands at approximately 3 gigawatts of total global electrical capacity at the end of the second quarter, up approximately 12% year-over-year.

Furthermore, we continue to evaluate opportunities for additional grid-connected and behind-the-meter expansion sites globally across both new and existing sites. Our objective is straightforward: continue acquiring, building, and converting powered infrastructure.

We will share updates on our progress here when appropriate. I will now turn the call over to Michael to walk through our business segment updates and second quarter financial results.

Michael Potter

Thank you, Haris, and good morning. I'm happy to join everyone for the first time as Bitdeer's CFO.

Execution remains our top priority. While the Tydal lease that Haris described has now been executed, there is significant work ahead to prepare for the first RFS date.

We will update as appropriate as those milestones are achieved. The focus in our view is on the quality of offtake demand, robustness of the financing structure, and contractual protections.

We believe this transaction compares very favorably on these dimensions, and we look forward to demonstrating that through continued execution. Looking ahead, we see plenty of interest in various sites within our portfolio that could potentially be used as AI/HPC data centers.

A key advantage of our model is the ability to utilize capacity for crypto mining until an AI data center is ready, ensuring our power assets remain productive and secured. Turning to our Bitcoin mining business: self-mining hashrate reached approximately 73 exahash per second at the end of the second quarter, up approximately 342% year-over-year, supported by approximately 243,000 active self-mining rigs.

This is an increase of approximately 113% year-over-year. We mined 783 Bitcoin in April, 921 Bitcoin in May, and 990 Bitcoin in June.

Total second-quarter production was approximately 2,694 Bitcoin, an increase of approximately 377% year-over-year. Our co-mining hashrate also continued to accelerate meaningfully during the quarter.

This reflects our continued deployment of SEALMINERs into third-party facilities. It grew over 260% sequentially.

We believe our combination of self-mining, co-mining, and hosting gives us multiple channels to monetize our growing SEALMINER production. We have the flexibility to allocate hardware to the channel that offers the best returns as market conditions evolve.

Our SEALMINER platform continues to reinforce our structural cost advantage. The commercial launch of our A4 Ultra Hydro unit, operating at 9.45 joules per terahash at the chip level, continues to lower our internal cost per exahash.

During the quarter, we also launched the SEALMINER DL1 Hydro, our first machine designed for Scrypt algorithm mining. This broadens our product line beyond Bitcoin-focused hardware.

Our internal manufacturing capability means that we're not subject to third-party markups when deploying SEALMINER rigs into our own fleet. This remains a structural cost advantage relative to other mining operators.

In July, we broke ground on our first U.S.-based manufacturing site, a 187,000 square foot SEALMINER manufacturing facility in Sparks, Nevada. This is expected to be completed by the end of 2026 and will be capable of producing 10,000 units per month.

It is expected to create approximately 70 high-quality local jobs. At the Massillon, Ohio site, we have 174 megawatts of capacity currently online for mining.

With reconstruction of two previously fire-damaged buildings underway, a significant portion of that cost has been recovered through supplier insurance coverage. We believe the associated capacity to be energized in phases during the third quarter.

In June, we broke ground on our Fox Creek, Alberta site. A $155 million investment includes a fully permitted 101-megawatt on-site natural gas power plant with grid interconnection.

The site uses a closed-loop dry cooling system. Alberta's Bring Your Own Generation framework gives us the flexibility to curtail compute workloads and sell power back to the grid.

Our AI business continued to scale during the quarter. AI Cloud annual recurring revenue reached approximately $76 million at the end of June, an increase of approximately 77% quarter-over-quarter.

Utilization was approximately 95% across 4,248 deployed GPUs. We also signed a new 10-year lease for 21.7 IT megawatts of capacity in Malaysia, with handover expected in the first quarter of 2027.

It is designed to support 128 NVIDIA GB300 NVL72 systems. On the product side, we deployed NVIDIA's Nemotron 3 model onto our Bitdeer AI Model Studio on the first day of its launch.

Turning to our financial results: second-quarter revenue was approximately $228.8 million, an increase of approximately 47% year-over-year and approximately 21% sequentially. The year-over-year growth was driven primarily by the continued expansion of our self-mining hashrate and the associated increase in Bitcoin production, along with accelerating contribution from our AI Cloud business, which contributed $14 million, an increase of approximately 284% sequentially.

Total gross profit was -$8.5 million, with a gross margin of approximately -3.7%. Importantly, this represents a $30.5 million sequential improvement that demonstrates the operating leverage of our vertically integrated model.

This recovery was driven by two key factors: normalized seasonal power costs, which dropped approximately 15% sequentially, and an improvement in our blended fleet efficiency to 15.8 joules per terahash. On a year-over-year basis, our gross margins reflect continued but moderating pressure from the additional depreciation expense from our expanding mining fleet and the still challenging hash price environment.

Adjusted EBITDA was approximately $31.1 million, an increase of approximately 575% over the year and approximately 116% sequentially. This sequential improvement illustrates the operating leverage of our vertically integrated model as both hash price and power cost dynamics continue to stabilize.

Operating loss in the quarter was $101.7 million, and net loss per share was 37 cents. Turning to the balance sheet and cash flow: net cash used in operating activities was approximately $158.5 million, an improvement of approximately $188 million sequentially.

This was driven by the capitalization of SEALMINER-related inventory to PP&E as we're allocating those rigs for internal use. We ended the quarter with approximately $496 million in cash, cash equivalents, and restricted cash, compared to approximately $298 million at the end of the first quarter.

Total long-term debt was approximately $1.8 billion, a reduction of approximately $78 million sequentially. The increase in cash primarily reflects $457 million in proceeds from our at-the-market equity program during the quarter.

We view this as a prudent capital raise, establishing liquidity reserves necessary to execute on our AI/HPC pipeline, power and land acquisition priorities, and to help ensure that our Tydal site progresses on schedule. Today, we filed a new shelf registration statement since our previous shelf, which was about a year and a half old, had largely used up its capacity.

We now qualify as a well-known seasoned issuer, which makes us eligible for automatic shelf registration. Considering the increased size and scale of our business, we also filed a prospectus supplement to move our existing ATM program to the new shelf and takedown $1 billion for offering under that program.

Looking ahead, we expect to broaden our sources of capital, with much of our remaining 2026 financing needs to be met through project-level debt financing, anchored by our previously discussed goals of accessing the debt markets for Tydal. We expect this debt financing will also unlock significant incremental liquidity to support our broader AI/HPC pipeline.

Our preference is to prioritize non-dilutive project-level financing over equity issuance wherever the underlying contracted cash flows support it. Consistent with this, in Q2, our Bitcoin wafer spend was funded entirely through cash generated by our mining operations and debt collateralized by our wafer bank, not equity issuance.

In terms of guidance, we are revising our full-year crypto mining infrastructure capital expenditures to $200 million to $280 million, driven by additional infrastructure development opportunities we see in North America. As a reminder, this guidance excludes capex for SEALMINER hardware, GPUs, AI Cloud, or colocation development.

On expenses, we continue to actively manage our overhead as we scale the organization to support our expanding colocation and AI Cloud businesses alongside our core mining and ASIC manufacturing operations. We expect our general and administrative expense run rate in the second half to reflect the incremental headcount and infrastructure needed to support that growth.

To summarize, the second quarter was a solid quarter for Bitdeer. In the past few months, we have clearly demonstrated our ability to deliver against our HPC/AI objectives.

We executed our first major AI infrastructure colocation lease agreement at Tydal, officially launching our colocation data center business as a core pillar of our company. We reached this milestone on compelling terms and with a partner, Volta, we are excited to work with.

Our underlying power portfolio continues to scale, our AI Cloud business is demonstrating strong momentum, and our Bitcoin mining and SEALMINER platforms illustrate the benefits of vertical integration. Thank you for joining us this morning.

Operator, please open the call for questions.

Operator

Thank you. Ladies and gentlemen, as a reminder, to ask a question at this time, you will need to press *11 on your touch-tone telephone and wait for your name to be announced.

Please stand by while we compile the Q&A roster. Our first question coming from the line of Nick Giles with B.

Riley Securities. Your line is now open.

Nick Giles

Thanks, operator. Good morning, everyone.

Guys, congrats on getting the first deal done here. You spoke to the pipeline and looking at new opportunities globally.

I was just hoping you could frame up kind of some of the opportunities you're seeing outside of the U.S., how near-term these opportunities could be. Thank you very much.

Michael Potter

I want to make sure I understand your question. You want to know what our opportunities are outside the U.S.?

Nick Giles

Exactly. Just hoping to get a better sense for the pipeline ex-U.S.

How many megawatts are you assessing today, and what's the earliest that some of these megawatts could be brought online?

Michael Potter

I'm sure Jihan could give some additional color on this, but we do have a lot of large Asia-based potential customers that are slowly starting to turn online. Our existing GPUs in Asia are quite used up, and we're expecting to add more capacity as customers come online.

I don't know if Jihan has anything additionally he wants to talk about.

Jihan Wu

On the GPU deployment, I think in the near future, mostly it's in Malaysia. We have data center already signed up, and we've also have other opportunities in active discussion.

The demand side is also very strong, and usually it is multi-year, and highly profitable contract. The bottleneck right now is our execution.

We are quite busy on execute those AI cloud contract business in Malaysia. Then Norway will be the next.

We reserved like 50 megawatts. A little bit less than 50 megawatts IT load in Norway ourselves.

That will be a little bit later than in Malaysia. It is expected within next year.

Then we will have some of our U.S. data center activated, like in Tennessee and Washington.

Nick Giles

Thanks for that. No, that's helpful.

Would you consider any new sites outside of the U.S. for colocation purposes, or are you seeing any opportunities for expansion in your European footprint on the colocation side?

Jihan Wu

We are actively looking for other powered assets opportunities in Europe. Since we haven't done any deal yet, I think it's too early to really talk about our plan in Europe.

Right now our focus should be on execute the deal in Tydal. I think that's very important for us.

If we can execute that, we will generate revenue and cash flows. I think that's and it's also generate kind of credibility of our data center execution.

I think that's super important for us right now.

Nick Giles

Understood. Then maybe one more if I could.

I saw, if I read correctly, just at the Knoxville site, there was a full redesign of the project, and I believe the ready for service time was slightly pushed out. Can you just maybe provide some additional background on what drove that?

Was that potential customer driven? Was that to kind of better fit NVIDIA architectures?

What was the reason for that?

Michael Potter

I don't know if you want to talk about that, Haris, or you want me to jump in on it.

Haris Basit

I think probably best for you, Michael.

Michael Potter

When we have been going to market and looking at the requirements around our Tydal, Norway site, originally we'd expect the Tennessee to be two different projects, but the market demand is more for a single, more monolithic amount of megawatts offered in one place. We redesigned it instead of having two separate, smaller sites inside our bigger site to just be one data hall complex.

That was the redesign we did, and it's reflected from the discussions we've had with potential customers and what their requirements are.

Haris Basit

The expectation actually aligns with the second phase. There will be no phase one, phase two.

It's only one phase, and it will all be online at the same time. If we look at the expected phase two, I think it's actually not pushed out a lot, but there will be no phase one early activation.

Nick Giles

Got it. That's very clear.

Guys, I appreciate the update. I'll turn over, but nice work.

Operator

Thank you. Our next question in queue coming from the line of Mike Grondahl with Northland Capital.

Your line is now open.

Michael Grondahl

Hey guys, thank you. Could you spend a minute on how you decided on Volta and kind of what maybe their ultimate demand is?

Then secondly, Rockdale and kind of Clarington, what are next steps at both of those sites? Thank you.

Haris Basit

Maybe I'll start with the Volta side and then can have Michael or Jihan speak to the other sites. Why we chose Volta was really they have done a great job actually in finding innovative ways of addressing this business in both the capital markets, the customers that they have obtained and their contracts with the customer.

They also were able to move rapidly, which is something that we wanted to see at the Tydal site since that site is coming online in just a few months. In general, the commercial terms were also very favorable.

We thought that they were the right choice for us at the Tydal site. Their ultimate demand can be much larger, but of course they're just getting started.

The initial lease is for 121 IT megawatts.

Michael Grondahl

Got it. Then just an update on next steps at Rockdale and Clarington.

Michael Potter

I don't know if Jihan wants to add some further color, but we're continuing to build out the power infrastructure as per our previously discussed timeline in Rockdale. That was something that was predating the batch zero, the allocation of power in the site.

We're preparing in the background what we believe we need to do if we want to do an AI data center at that site. Clarington, we're developing it for crypto mining right now.

The power is available coming up soon, and we'd like to be able to make sure we use it fully. There's no big update on the lawsuit in Clarington now.

The motion to dismiss that we had filed was turned down by the judge, which is pretty common in these trial things, and it's gone into a discovery now. We continue to believe that the lawsuit doesn't have any merit, and we continue to work on that.

Michael Grondahl

Got it. Thank you.

Operator

Thank you. Our next question coming from the line of Kevin Cassidy with Rosenblatt Securities.

Your line is now open.

Kevin Cassidy

Thanks for taking my question, and congratulations on landing Volta. Two things on that.

Maybe with the Texas government putting a pause on a new data center grid, maybe, Haris, you might have touched on that, but how does that affect your colocation opportunities in Texas?

Haris Basit

Michael, do you want to answer that one?

Michael Potter

It's still a little bit early to make strong comments on that because the actual criteria haven't come out yet. The one big site we have in Texas, which is Rockdale, all the activity there is pre-batch zero and not related to that we're working on.

As the actual news gets out and the criteria come out, I think we'll be in better position to be more specific in our comments.

Kevin Cassidy

Great. With Volta's a large neocloud and worldwide, is there a chance to just expand your relationship with them to other sites?

Haris Basit

There is that potential, of course, with Volta, but we haven't released any information on that yet.

Kevin Cassidy

Okay. Maybe I'll ask one other is how should we be modeling SEALMINER rigs going forward and for externals sales?

Michael Potter

Right now, the existing wafer inventory that we have, we've designated for internal use with the very challenging hash rate and our desire to expand our ability to do self-mining and co-mining. We made the decision to use it internally.

We have the capability and the capacity to deploy it, and that's the best way to get that working and earning us some cash. It is an example of our model being extremely flexible in that we do have a fair amount of powered land that's in earlier stages of development for other uses that we can quickly deploy cryptocurrency mining into it and make sure we generate cash off the power.

Also, if you keep using the power, it's less likely that the utility will try and move it away from the land. It's important that we can quickly react when we do get land into our portfolio and use it, and the crypto mining that we do is a big advantage there.

Kevin Cassidy

Okay. Great strategy.

Thank you.

Operator

Thank you. Our next question in queue coming from the line of John Todaro with Needham.

Your line is now open.

John Todaro

Hey, thanks for taking my question, and congrats on the lease. First question, just as it relates to the lease, it was 133 gross megawatts.

I think we had that site marked for 225. Just trying to understand why Volta didn't go for the full amount.

Are you keeping some for cloud? If so, yeah, I guess why and the strategy there?

Then I have a follow-up.

Michael Potter

The full amount of power there is actually 180 gross megawatts. Of that 180 gross megawatts, we're leasing 133 gross, which would be 121 IT megawatts, to Volta, and then retaining 47 megawatts gross for our own AI Cloud use there.

As this market is dynamic. There's a lot of activity in both the colocation and AI Cloud space.

We think there's still a lot of opportunities for us in Norway with the 47 megawatts that we've retained. We haven't made final decisions on exactly how that would be deployed and for whose benefit in terms of the ultimate tenants there.

We think that's significant potential upside for us, and we felt it would be beneficial for us to retain that power for ourselves.

John Todaro

Understood. Then just one on the credit guarantee.

We've seen some in the past where you have kind of a neocloud in your offtaker is like an Anthropic-like entity, but there's still either the chip manufacturer or a hyperscaler involved in the credit guarantee. I guess can you just walk us through a bit more how that process worked and what maybe some of the other avenues you were looking at before ultimately settling on the way it's structured now?

Michael Potter

Yeah. I don't want to speak about the alternatives that we looked at since those are proprietary in many cases.

The letter of credit structure here I think is quite useful, and it might be quite useful to the industry as a whole because for the first time, it has backing or credit backing from someone other than, as you said, someone who's a chip vendor or a hyperscaler. It opens up additional funding opportunities.

It is a very high rating for letters of credit from the types of banks that we expect these letters of credit to come from. We know this is innovative and new to the industry, but we think it's going to be something that catches on.

John Todaro

Got it. Understood.

Thank you for that, and congrats again on the lease.

Operator

Thank you. Our next question in queue coming from the line of Brett Knoblauch with Cantor Fitzgerald.

Your line is now open.

Brett Knoblauch

Hi guys, thank you for taking my question. I guess I have a few.

Haris, on the Tydal lease, you kind of talked about an additional $500 million of capex needed. Curious how much money you guys have put into that site excluding the additional capex you need.

Haris Basit

Actually, let me ask Michael to answer that question for how much has actually been put in. We've put hundreds of millions of dollars of development into the site already, some of which has actually been spent around the AI data center and originally developing the site to be used as a cryptocurrency site.

We've made a reasonably significant investment in there in the past, which prepared us so that we could act very quickly when this opportunity came up. This is more of a brownfield or semi-developed site than a complete greenfield, it allowed us to act very quickly and meet the timeline that Volta was hoping for.

Brett Knoblauch

Understood. Thank you.

Then just high level, how should we think about how you're going to allocate capital between maybe leasing some of the powered land you have and building your own AI or expanding your AI Cloud business? I guess, if we think about Volta and your AI Cloud, to some extent, they probably compete against each other.

You're both selling compute. Is there a preference for you to want to be bigger on the cloud side?

Is this going to be a mixed approach? I guess how are you guys thinking of it internally?

Michael Potter

I think Jihan can give some deeper color on that, but we're remaining flexible. If there's a good colocation deal that we feel it's in the best interest of the company to do, we can still execute on something like that.

If we look at what we can do around owning the GPUs ourselves or providing the GPUs ourselves and serving a customer ourselves, that's something that we strongly consider as well. We haven't said that we're going to do one or the other as the exclusive way to do it.

Brett Knoblauch

Awesome. Then maybe if I can just follow up with one more.

As I look at kind of 3 gigs of kind of existing power and power coming online over the next several quarters, I guess is there a site that we should be focusing on that is kind of most ready or the next catalyst to either be leased or either be converted or anything we should think about future catalysts ramp here?

Michael Potter

I think Jihan talked about this a little bit earlier that in Asia, we have ability to grow quickly in Malaysia because of the new site that we've signed up in Malaysia. In the very short term, I think Malaysia is the one you see the most activity on.

If you look at the table we provide, Washington state and Tennessee are the two that are sort of designated specifically for that we're actively working on and doing construction and such. In terms of any soon news, those are two that are most likely to come out.

The other sites, it's really depending on where we are with our discussions with customers and what we decide to turn on that. As that happens, we'll make sure we update everybody.

Brett Knoblauch

Awesome. Thank you, guys.

Appreciate it.

Operator

Thank you. Our next question in queue coming from the line of Mike Colonnese with H.C.

Wainwright. Your line is now open.

Mike Colonnese

Hi, good morning, guys. Congrats on the Tydal deal.

Great to see. I have two, first on the AI/HPC business.

Haris, you touched on this a bit earlier, but I just want to follow up on it. If you could just talk about the preferred use for the additional 47 megawatts of gross capacity at Tydal.

At this stage, it sounds like you're considering either the GPU-as-a-service type model or another colocation deal. If you were to do a colocation type of contract, would Volta be interested in this incremental capacity, or would you be marketing that out to new prospective tenants?

Michael Potter

I don't really want to speak for Volta here on this call, but there is a lot of interest from Volta in expanding our relationship, and we will consider it along with other options. Then

Mike Colonnese

just given where GPU pricing is, obviously you guys have had some success in that business as well, would you say you're more or less likely to deploy your own GPUs to use that additional 47, or do you think at this juncture, colocation model would be the preferred way?

Michael Potter

We haven't made any final decisions for the 47 megawatts, but if you're looking for a forward-looking comment there, I don't know, Jihan, if you want to add some color there.

Jihan Wu

Actually, there are already some interested customers talking with us on those capacities. For any GPU deal, we need to considering about the financing and the deployment, technical together.

I think right now, it's not quite the right time to talk about too much. Our execution line, I think Malaysia right now is more in the front of it.

If we have a lot of interest from customers, and we will focus to discussing with some Malaysia capacity. After that, we will start to execute those Tydal's 47 megawatts of AI Cloud.

Then

Mike Colonnese

one more for me, just on the Bitcoin mining side. Bitdeer has been one of the few miners that has continued to aggressively expand capacity in this environment, really positioning you well for the next stage of the cycle here.

Just curious how we should think about hashrate growth in the back half of the year. Sounds like you have the wafer inventory to develop, deploy, manufacture your own SEALMINERs for your proprietary use.

Just trying to think through the best way to model hashrate expansion from here.

Michael Potter

I think in general, for modeling purposes, if you look at the steady increase we've had over the last few quarters, it'll be similar to that, where we'd be deploying about the same amount of mining machines per month going forward. I don't think we'll be greatly accelerating from where we are, but I think steady deployment at a reasonably high rate as we've shown over the last few quarters.

Mike Colonnese

Very helpful. Thank you for taking my questions.

Operator

Thank you. Our next question coming from the line of Brian Kinstlinger with Alliance Global Partners.

Your line is now open.

Hi, this is Kevin for Brian. Thanks for taking our questions.

For the Tydal site, what tasks does Bitdeer need to accomplish between now and the beginning of both phases one and two?

Michael Potter

The phases one and two are full RFS, right? They will be completely ready for the customer's GPUs at that time.

Haris Basit

Effectively, all of the long lead-time items have been ordered. The scheduled arrivals are before the respective RFS dates.

We have to finish installing those. There's a commissioning part of it that is also very critical.

It's in very good state right now. We've had an engineering analysis, and it looks like we're going to hit our target dates.

There's probably a hundred things to do. Off the top of my head, I can't name what they are, but there's hundreds of people on site working on this, and it's moving ahead.

There's no specific item that stands out that is more critical than the others that could potentially cause a problem. We feel like we're in a pretty good position to hit those dates.

Got it. Thank you.

Then Bitdeer recently announced it will lease a 21.7 megawatt data center in Malaysia for AI Cloud. Can you share some more details like the costs and how you finance the GPUs and any other infrastructure needed?

When you expect this data center will be ready for your customers, and then maybe could you share a range at full capacity of what the annual revenue run rate would be for this data center?

Michael Potter

It's a little bit early to talk about specifics and forward forecasts on that. I'm sure that Jihan can give some additional color, but we do have several customers that are interested in it, and the GPU financing will depend on whatever contract we have and how it needs to be done based on that contract.

When you have a good quality customer backstopping the use of the GPU, it's normally much more straightforward to find financing for GPUs.

Operator

Thank you.

Thank you.

Operator

Our last question coming from the line of Ben Sommers with BTIG. Your line is now open.

Ben Sommers

Hey, good morning, guys, and thanks for taking my question. Haris, you mentioned exploring behind-the-meter opportunities, and I know you guys are doing some on-site generation in Alberta.

Any additional color you can provide on preliminary conversations or steps you have taken to develop some behind-the-meter power moving forward?

Haris Basit

Other than us talking about Alberta in the past, I think it's too early to talk about that at any other site. If any of those things develop further, we can mention it in the future.

Michael Potter

We have talked about Alberta that this being the first site, but that we do have the ability to expand it. This is sort of a test of concept for us in Alberta underneath the program they have there of Bring Your Own Power and the availability of stranded gas in quite a few locations in Alberta, which sort of ensures you get reasonable supply at reasonable costs.

It is a site that if this Fox Creek works well for us, we can expand in, using the same model and the capability we've been developing internally. We have looked at other sites that we can do more in, and if we decide to do it, we'll update everybody at that time.

Ben Sommers

Super helpful. Then just on the AI Cloud business quickly, we've touched on the expansion there.

Just curious what you're seeing in terms of term length for new GPU Cloud contracts and maybe how that's compared or how that's changed over the past 90 days.

Michael Potter

Haris or Jihan, do you have any comments on that?

Jihan Wu

Right now, when we are discussing with our customers on the GPU contract, mostly focusing on those long-term contract. 5 years.

We are not spending pretty much time on talking contracts that's shorter than that. Our expansion will mostly be supported by this kind of long-term contract.

Ben Sommers

Super helpful. Thank you, guys, for taking my questions.

Operator

Thank you. There are no further questions in the queue at this time.

I will now turn the call back over to Michael Potter for any closing comments.

Michael Potter

Thanks, everyone, for joining us, and we look forward to speaking again soon. Operator, you can end the call.

Operator

This concludes today's conference call. Thank you for your participation.