Q2 FY2027 · Earnings Call TranscriptOctober 29, 2026

Operator

Ladies and gentlemen, good day and welcome to the Q2 and H1 FY27 earnings conference call of ACME Solar Holdings Limited. As a reminder, all participant lines will be in the listen-only mode, and there will be an opportunity for you to ask questions after the presentation concludes.

Should you need assistance during the conference call, please signal an operator by pressing star then zero on your touchtone phone. I now hand the conference over to management.

Thank you, and over to you.

Ankit Verma

Thank you. Good afternoon everyone, and thank you for joining us today.

I am Ankit Verma, Director of Corporate Finance. I am joined by our Chairman, Mr.

Manoj Kumar Upadhyay, Mr. Nikhil Dhingra, Joint MD and CEO, and Mr.

Arun Chopra, CFO. It is my pleasure to present the highlights of our performance for the second quarter and the first half of FY27.

Let me begin with our financial performance. Total revenue for the quarter stood at INR 1,007 crore, which is up 67.5% year-on-year, while EBITDA increased 63.6% to INR 874 crore, driven primarily by short-term peak power BESS operations and renewable capacity additions.

Our blended EBITDA margin was 86.7%, which comprises 90.8% from renewable generation and 78.3% from BESS operations, where the cost of power purchased to charge the batteries sits within the operating expenses. Profit after tax rose 133.5% Y-o-Y basis to INR 269 crore, which represents a PAT margin of 26.7%.

Our asset base grew by INR 11,466 crore over the year to INR 28,462 crore following the commissioning of BESS and RE projects. Coming to our business and execution updates, we made strong progress across commissioning, PPA signing, and short-term peak power BESS contracting.

We have commissioned approximately 5.2 GWh of BESS capacity till date, which is the second-largest BESS capacity in India as of date, and we achieved our initial half-yearly target of 5 GWh, which we mentioned in the last call. With this BESS and solar commissioning, 1.9 GW of our contracted projects are now partially commissioned.

In addition, 1.7 GW of modules have been delivered to site, out of which 1.1 GW are already installed across multiple projects. Out of this installed 1.1 GW module capacity, 200 MW peak of modules is already charged, and the balance is expected to be charged by November-December of this year.

We signed 430 MW of FDRE PPAs during the quarter. Additionally, we yesterday signed another 400 MW FDRE PPA with NTPC, taking the overall PPA signed portfolio to 92% out of the total contracted portfolio of 8,370 MW.

Through short-term BESS contracts, we have locked in more than 1,600 crore of revenue for partial sale of FY27 capacity and more than 1,500 crore for partial sale of capacity for FY28, with the balance to be tied up through future bids. Our CUF for the quarter improved from 24.1% to 27.8% year-on-year, and power generation grew 19.6% to 1,840 million units.

Additionally, we sold 324 million units through short-term peak power BESS contracts. The weighted average cost of debt for our fully operational projects is around 8.4%.

Around 65% of these borrowings are from PFC, REC, IREDA, and NabFID, whose rates follow their own long-term cost of funds and which limits interest rate volatility. Further, CRISIL has upgraded ACME Solar Holdings rating outlook to AA- positive from AA- stable.

Turning to the key sector and regulatory updates, below are the favorable steps taken by the government benefiting all the stakeholders. First, BESS connectivity: CTUIL has initiated the grant of BESS connectivity under non-Rooftop route, speeding up deployment.

For us, it helps build a large BESS pipeline at preferred high GHI sites in Rajasthan. Second, Green Energy Corridor Phase-III: the Union Cabinet has approved INR 1.36 lakh crore for interstate transmission, intrastate transmission, and INR 50,000 crore for 50 GWh of BESS, targeting the evacuation of 135 GW of renewable energy.

This is expected to open up new opportunities for us in the state-connected renewable projects. Third, the Pradhan Mantri Surya Sarovar Yojana: the scheme targets 5,000 MW of floating solar with at least 2 hours of co-located storage and provides central financial assistance of up to INR 1 crore per megawatt after commissioning.

This opens up new business opportunities for us in the floating solar market. Lastly, use of curtailed energy for BESS charging: wherever the GNA is delayed, curtailed solar under the PPA can now charge BESS for merchant sale.

This gives us the opportunity to commission our solar capacity ahead of scheduled GNA and utilize that energy in BESS. Overall, these developments reduce risk, widen the opportunity set, and support our focus on BESS deployment.

Looking ahead, let me share our upgraded capacity roadmap. Given our execution momentum and the scale of the opportunity, we are raising our targets across all three timeframes.

FY27: BESS commissioning guidance raised from 10 GWh to more than 12 GWh, driven by our early deployment strategy. By 2030, our renewable target rises from 10 GW with 25 GWh of BESS to 15 GW and 50 GWh of battery, doubling the storage component.

Below are the several factors that support delivery of this roadmap: a strong tender pipeline, 20+ GW of upcoming tenders across solar plus BESS, FDRE, CFD, and PHSP; 50 GWh of peak power bids already rolled out till September '27, and another 200 to 250 GWh of short-term peak power contracts expected in the near to medium term; and 20 GWh of medium-term peak-only tenders expected shortly. As we speak today, SECI has launched a large 4 GW/16 GWh auction for 4 hours of assured peak power, which requires commissioning within the required 12 months.

The tender also carries VGF funding of INR 15 lakh per megawatt-hour. Secondly, about 10 GW of RE connectivity inventory that we have, which is secured and applied, for upcoming bids over and above our existing portfolio, and 5 GW+ of BESS connectivity already granted.

Third, about 19 GWh of BESS already contracted with reputed suppliers including CATL, Lithion, Ganfeng, Trina, and CLOU. I would now hand over to Manoj sir to discuss strategic priorities for the company going forward.

Manoj Kumar Upadhyay

Thank you, Ankit. I would like to extend my sincere gratitude to our shareholders, our board of directors, and my team, who have continuously supported and guided the company in the right direction.

Our strategy going forward will rest on five pillars. Together, they are building a return-led, self-financing renewable platform with contracted, visible cash flows.

First, return on capital and profitability: we allocate capital to the highest-return opportunities. Megawatts matter, but the measure we put ourselves to: earnings, growth, and the quality of these earnings.

Second, BESS as a cash engine: on a rolling basis, we expect to operate around 10 GWh of BESS, subject to tariff realization. Its cash flows fund our growth and reduce the equity needed for new projects, making this a self-financing platform.

Third, execution excellence: we are focused on higher CUF, continued BESS additions, and keeping solar and balance of the system ready for upcoming projects. Being ready ahead of the grid improves margin and hedges us against transmission delays as our assets can start earning before full GNA.

Fourth, margin improvement: curtailed solar can now charge our BESS, energy that would otherwise be lost lifts BESS EBITDA and cash flow. We have tied up capex for both BESS and solar below budgeted cost, building better margins in from day one.

Fifth, contracted revenue visibility: long-term PPAs anchor our portfolio revenue, while short-term peak power contracts monetize our BESS capacity, giving us high visibility of future cash flows. With that, I conclude my remarks.

Thank you for your continued support. We'll now be happy to take your questions.

Thank you.

Operator

Thank you very much. We will now begin the question and answer session.

Anyone who wishes to ask a question may please press star and one on the touchtone telephone. If you wish to remove yourself from the question queue, you may press star and two.

Participants are requested to use handsets while asking a question. Ladies and gentlemen, we will wait for a moment while the question queue assembles.

First question is from the line of Puneet from HSBC. Please go ahead.

Puneet Gulati

Thank you so much and congrats on great performance and looking forward to your targets. My first question is, given the context of delays in transmission, what is the revised number of capacity addition that you intend to do for FY27 for power generation, and also what should one think of as annual capex and capitalization plan?

Nikhil Dhingra

Right, Puneet. Of course, we understand the delays in the GNA, right, and we have reoriented our strategy around it in terms of the BESS commissionings which we have done.

As you would have noted in our quarterly presentation, we have partially commissioned around 1.9 GW of capacity through a mix of solar commissioning and BESS commissionings, as you would have noted. As we are commissioning these capacities, we are realizing the revenue, which is seen in these quarters.

If you look at the complete commissioning of an FDRE plant or a hybrid plant, that is dependent on the GNA commissioning coming online, right? As per the current timeline, we are hopeful that we will be able to do 1.5 GW, right, but it could be more, it could be less by a quarter depending on the GNA commissionings.

Of course, as far as the partial commissioning go, it will be substantially higher, maybe 2.5, 3 GW because as far as DC commissioning go, we've already charged 2.5 GW of capacity in terms of that. If you look at revenue generation elements, as we have clearly mentioned, we have charged 1.9 GW of capacity commissioned because given these FDRE constructs and you can say the peak power constructs, right, these are now distributed across multiple CTU substations.

Tracking the full commissioning, right, does not mirror the revenue generation, right, because the BESS comes online early. Like in one of our two of our actually plants, we have charged solar also, right?

Because the GNA is not live, we are using it to charge the BESS, right? The GNA is partially available, let's say at Bikaner-III, we are supplying to NTPC during the day whenever the GNA is available, rest of the time, it is going to the BESS, right?

The plant is commissioned, but, of course, since the GNA is not available, we are using it very productively by reducing our cost of production. That's how we'll continue to share the details also in terms of the commissioning and also in terms of the elements commissioning.

Puneet Gulati

Right, get that. The 2.9 GW includes all this.

Sure.

Nikhil Dhingra

Sorry, just to complete the reply on the capex, right? Capex also is something you asked.

We have done around 10,000 crore of capex this year till date.

Puneet Gulati

3, 6,000,

Nikhil Dhingra

sorry, 6,000 crore of spend, out of which 3.5 is capitalized and 3 is CWIP. So 6,500 crore is what we have done already, and I think we will do similar amount or a higher amount in the second half of this year.

Puneet Gulati

Capitalization also, similar number? Yes,

Nikhil Dhingra

yes, because we are targeting to capitalize whole of 12 GWh of BESS in this financial year only. I think the number will substantially go up from what we have done in the previous half year because the BESS is ordered, the LCs are getting opened, and we have money lying, as you would have noted, there is a lot of cash because of the disbursements we received in September, all of this will be utilized into capex.

Puneet Gulati

Right. On the generation side, the 3 GW, where should it end of FY27, including what you used to power your

Nikhil Dhingra

own BESS? I think what you mean to ask is, there is BESS and there is generation to charge that BESS or to supply to the grid, right?

You want to know that number. It will be upwards of 1.5 to 2 GW in terms of that generation, in terms of the megawatt peak we will install.

Of course, bulk of it will be driven by Fatehgarh II, which has around already installed of around 700 MW peak is already installed at that. We are just awaiting the GNA going live.

Our transmission line is more or less ready. Then Neemuch, and then Bikaner-III, these three only will take this above 1.5, and, of course, we have Ananthapur also coming, which will take it to around 2 GW+.

On the generation side, right? This could go upwards.

I'm just saying the basic three, four projects which we see as coming online before March depending on the timelines of their GNA. At not at all places we are using this to charge battery.

Because Ananthapur, because the substation is coming live earlier, we may charge the solar first and the battery may come later, or battery may come concurrently also.

Puneet Gulati

Understood. On the debt side, how should one think about your cost of debt going into the future?

You also have a credit rating upgrade, but at the same time, there's also interest rate rising.

Nikhil Dhingra

Yes, yes. You're right.

It's, of course, the global and the Indian situation is moving towards a stabilization or some increase in the interest rates, of course. As Ankit mentioned, we've analyzed this issue, and we have reviewed that 65% of our debt is from institutions which borrow very long term, right?

If you noticed PFC, REC, IREDA, and, of course, NabFID, these institutions borrow very long term. Only 20% of their book is on a 5-year duration borrowing, which they refinance every 5 year.

Rest of their book is fairly stable. These guys, if you notice their behavior in last 5, 10 10 years, they have not increased their base rates as frequently as an MCLR-linked institution would do.

We don't foresee interest rates hikes from, let's say, 10,000 crore out of our 15,000 crore debt book, operational debt book, which is there. On the under-construction debt, of course, as once the project gets operational, there is a substantial reduction in the interest rate, which purely happens because of credit risk reduction and nothing to do with the interest rate cycle prevailing.

Let's say 9%+ interest rate which we are paying in a lot of these projects which are under construction will move down to, let's say, 9% substantially sub-9% rate. That's something which is independent of the macro.

It is a micro related to our company, which will also play out. As we are seeing even during the under-construction phase, we are getting two projects refinanced, which is in progress, where the battery is commissioned, the solar is very close to commissioning, but we are getting it refinanced.

That is also going on because the risk is currently out of the picture in terms of the commissioning of both the elements that battery is commissioned and solar is very near commissioning, and the GNA is also going to get commissioned, we are getting good demand for such where even during the construction phase, we are able to refinance.

Puneet Gulati

Understood. That's very clear.

Just lastly on my side, on the 400 MW NTPC tender that you signed, who is the offtaker, and has the tariff been reduced to 4.37 from earlier 4.7, and what's driven that?

Nikhil Dhingra

NTPC is the offtaker for that FDRE PPA, right? Tushar, we have not reduced the tariff in that one, right?

In the NTPC? There is a GST 5% and 12% impact, right, it's a tentative estimate of that tariff.

That is not a tariff reduction. That is basically the GST reduced to 5% from 12% post the RFS, right?

There is no tariff reduction in this particular PPA. I think we have increased the hour of battery, 1 hour of battery.

Right. 4 and

Manoj Kumar Upadhyay

a half hour battery. Yes,

Nikhil Dhingra

we have increased the battery from 4 hour to 4 and a half hours, but we have not reduced tariff in this one.

Puneet Gulati

Understood. That's very clear.

Thank you so much and all the best.

Operator

Thank you. Next question is from the line of Amit Bhinde from Axis Capital.

Please go ahead.

Amit Bhinde

Hello, sir. Am I audible?

Nikhil Dhingra

Yes, yes.

Amit Bhinde

Yeah. Congratulations for a great set of numbers and the revised guidance.

Just a few questions. One, in the previous question, you mentioned that you have done a capex of around 6,000 crore and you will do similar probably in the H2, so that's a revised guidance of 12,000 crore.

I think earlier we were talking about 15 to 17,000 crore. Any change in thought process because of the transmission connectivity or any other reasons?

Nikhil Dhingra

Right. We have done a capex of 6,500 crore already, right?

We have around 7 GWh of battery with us today at sites, and we are yet to receive 5 GWh of batteries for which we have opened LCs and they have not been capitalized or they are not part of the capex. It will be a substantially higher number than 6,500 crore, which we are hoping to do.

We are also getting modules for sites where we are able to charge these batteries. We are quite confident that it will be a higher number than 6,500 crore.

I don't have a ready number with me right now in terms of the H2 capex exactly, but we will be able to share with you. It should be higher going by these two things.

In terms of the GNA dependency, right, for these capex, for battery, we have no GNA dependency because we are only doing battery installations at places where GNA is available, right? For modules also, we are only doing where we are able to either charge our battery or supply to the grid.

Which is a big runway for us because we have a large amount of megawatts which we can install at places where we have batteries or where we have GNA. That will not be a limiting constraint for capex for us.

Amit Bhinde

Got it. The second question that I wanted to understand is that you have mentioned that you have done 1.9 GW of partial commissioning of the projects.

If I just take a 25% PLF on that for this quarter, it would mean about 1,050 million units, and your BESS have supplied only 324. In a way, are we implying that we had around 650 to 700 million of curtailment?

Nikhil Dhingra

Sorry, I missed your query. Could you come again?

Amit Bhinde

You have 1.9 GW of capacity, which is pre-commissioned, right?

Nikhil Dhingra

Now,

Amit Bhinde

if I just take a 25% PLF on that, it means about 1,050 million units generation in the quarter. BESS is only 324, and we have also taken external purchases.

In a way, is it right to conclude that curtailment was close to around 700 million units?

Nikhil Dhingra

No, no. How you should look at this commissioning is you look at the elements which have got commissioned, right?

There is a solar which got commissioned at some places, and there are quite a few places where the solar is not even commissioned, right? It's only battery.

Wherever the battery is commissioned, it's purely charging of that battery and discharging of that battery, right, because the solar is not there, this 25% CUF is not applicable, right? Wherever the solar is charged, there also the capacity is partially commissioned as of now, as mentioned.

There also, let's say at Bikaner, currently 133 MW is charged out of 300 MW. For 133, you can benchmark 25%, right, in that specific project.

Yeah. I think in the next we can incorporate the exact numbers, where you can match this 25% because

Amit Bhinde

That would be request for that. If we can have that in the PPT as to what is your plant configuration and how much has been commissioned in the operational table below.

Nikhil Dhingra

We will do that. We will do that in the next presentation.

Amit Bhinde

Yeah. The last question that I have is basically if I look at your Q1 to Q2 gross block difference, that's almost about 1,782 crore, whereas the operational debt that I'm seeing, that is increasing by around 31 billion.

The 3,100 crore. Ideally, it should be 75:25 or 80:20 when you recognize as operational debt.

There's a mismatch. If you can help me understand the accounting behind that?

Nikhil Dhingra

Amit, you are comparing Q1 FY27 with Q2 FY27 or corresponding quarter Q1?

Amit Bhinde

No, Q1 Q1 FY27, Q-o-Q. Q-o-Q, your gross block has gone up from 196 billion to 214 billion, so that's a 1,782 crore of gross block increase, whereas if I look at the operational debt increase, that's around 3,100 crore.

Ideally, I would have expected a 75:25 or 80:20 kind of a recognition into operational debt when the project gets capitalized, but here the difference is higher. If you can help

Nikhil Dhingra

me understand that? I'll just put up the numbers for your reference, right, so that we're clear.

In Q1 FY27, our gross debt was roughly INR 20,000 crore. In this quarter, it is roughly INR 26,500 crore.

That's number one. In terms of gross block, our gross block for Q1 was around INR 24,900 crore, and for this quarter, it stands at roughly INR 28,500 crore, right?

Which is roughly a capex of roughly INR 3,500 crore, which we were talking about during the quarter. The gross debt has increased partially because some of the refinancing must have also happened, and rest of it went into CWIP.

Right,

Amit Bhinde

but then okay, I'll try to take this offline because the operational debt is appearing more versus a CWIP debt, they're in that

Nikhil Dhingra

Some of the debt happened at the quarter end, which anyway is reflecting as a cash balance in the book, which is INR 10,000 crore. Which is INR 10,000 crore.

Yeah.

Amit Bhinde

Okay. Just to understand, could there be a possibility that you are taking more debt on the operational asset and funding in some of the equity through that for the CWIP?

Is that a possibility?

Nikhil Dhingra

No, no. That has not happened at least in this quarter or the previous quarter, so that is not the case because when we typically refinance is when the project just becomes the COD, right?

That is when you deserve a top-up because the debt equity can move from 75:25 to a higher number. This has not happened in the two What we have really done is we have taken disbursements early on these FDRE and peak power projects to push our battery capex, right?

That has resulted because as the battery capex for us is quite front-ended, right? We are ordering 12 GWh of batteries.

All those projects, battery debt has come in early, right? The battery LCs are only opened when required.

This is a factory acceptance test, at that time, you open a LC. Even though you take debt at the end of the quarter or whenever, because it's aggregate disbursement they do, not on the each and every LC period.

There is a time delay between the disbursement and the utilization of that debt. That is why you see a lumpy amount coming in in terms of gross debt, whereas the capex is happening as we open these LCs and we install those batteries or deliver these batteries, that is how it will pan out.

You will see this whole of debt converting into gross block and converting into revenues also because their timescale from installation to revenue is very short in a battery project, and we are only calling for batteries where the GNA is live and where we are ready.

Amit Bhinde

Right. Got it.

Right. Only one data question: how much units internally were used to charge the BESS if you can give that, and second, the average purchase price of the BESS that you have recently ordered in Q2?

I think Q1 ordering was around 15 GWh. Now you have 19, you have ordered 4 GWh during the quarter.

How has been the rates because lithium carbonate prices are going up and BESS capex can see a upside to the INR 1 crore that you have been doing till now?

Nikhil Dhingra

In terms of the solar being used to charge BESS, out of the 133 MW, Tushar, how much is

Manoj Kumar Upadhyay

around 700 MWh per day,

Nikhil Dhingra

which is around 80, 90 MW of AC.

Manoj Kumar Upadhyay

Around

Nikhil Dhingra

90 to 100 MW of AC out of 133 is used to charge the BESS, and 33 to 40 MW is going to the client.

Amit Bhinde

Got it. On the BESS capex, if you can

Nikhil Dhingra

On the BESS capex, of course, we have done lower than INR 1 crore per megawatt-hour because as the key difference in the capex for us is we are installing BESS at operational substations,

Amit Bhinde

right?

Nikhil Dhingra

The capex for the transformers and the AC infrastructure exists at these plants. We are not doing a greenfield installation.

That saves us around INR 20 lakh per megawatt-hour odd of capex. That's why we have been able to do between INR 90 lakh to INR 1 crore kind of a number for the capex which we have capitalized on our books.

In terms of the going forward, what we are seeing is the lithium carbonate prices have come down, the copper prices have gone up, and, of course, the Chinese tax is coming into picture in January, 6% tax is there from export tax. It's a combination of factors, but overall, the battery doesn't look to be going up at all.

It will go down. How much it goes down is dependent on the three, four factors we spoke about and, of course, on the supply and demand and various other geopolitical factors, yeah.

Amit Bhinde

Right. Got it.

Those were all the questions. This was really helpful.

Thank you.

Operator

Thank you. Next question is from the line of Mohit Kumar from ICICI Securities.

Please go ahead.

Mohit Kumar

Good afternoon, sir, and thanks for the opportunity. My first question is that are we seeing this change in the bidding environment where SECI is floating bids after completely tying up of the power with discoms and thereby conversion to PPA are happening faster?

Is the understanding correct? Yes,

Nikhil Dhingra

yes, please. That is a correct understanding.

As you can see in the cycles of our recent PPA, we won a bid and it got signed to PPA around 2 months, within 2 months. That is absolutely true.

Of course, the selectiveness with which the bids are being coming is also very praiseworthy, I may say, because they are actually collecting the exact bids they need to do from the states and coming up with only those bids, whether it is a PSP bid or a wind bid or a peak power bid, it is actually catered to only the demand. They are not coming up with bids where there is no customer, and there is a pre-tie-up of customers because otherwise you cannot do this 2 months bid to signing.

It is impossible to do that otherwise. Understood.

Mohit Kumar

My second question is on the batteries. Can you please help us understand the battery PPA tie-up which you have done for INR 15 billion and INR 16 billion for FY27 or FY28, I believe this is the right numbers.

Is it possible to quantify how much of the current capacity that tied up for H2 and FY28? Are we exposed to the input price volatility?

Nikhil Dhingra

For FY27, we are around 90, 95% tied up in terms of what we can produce. We have contracted.

We keep around 5, 10% for RTM kind of a sale. In terms of FY28, we are around 65% tied up or maybe 60 50 to 50 to 60%, we will confirm that number, but around that number is what we are tied up.

In terms of capex, you are asking, Mohit, or you are asking about the cost of buying power? You're talking about cost of buying power?

Cost of buying power, yeah,

Mohit Kumar

buying power.

Nikhil Dhingra

Yeah. Of course, we don't have any tie-up for the buying power as of now.

We are, of course, dependent on these IEX prices for buying power. Wherever we are producing our own solar, right, which is a large number, we are more and more reducing that risk because I think by end of March or maybe by June, at quite a few places, our solar will be fully ready to charge these batteries which we have at stations because they have that kind of configuration.

Our procurement from IEX would reduce substantially. In the next presentation, we will incorporate that also, that how much we will buy from outside versus how much we will have, but we will give you that number.

Operator

Sorry to interrupt, Mr. Mohit Kumar.

When management is answering your question, may we request you to please mute yourself? Because of that, there is a disturbance, sir.

You may go ahead with your questions.

Mohit Kumar

No, no, I'm done. Thank you for the opportunity.

Thank you. All the best, yeah.

Operator

Thank you. Next question is from the line of Sourabh Arya from Oaklane Capital Management.

Please go ahead.

Sourabh Arya

Hi, sir. Am I audible?

Nikhil Dhingra

Yes, please.

Sourabh Arya

Hi. Congratulations on great set of numbers.

I have two questions. One is on your this strategy 2.0.

Of course for 2030, we are saying now we can do 15 GW. What we are seeing in market is ultimately, grid connectivity is the challenge.

For our existing project already, of course, we're not able to fully commission them. In that context, how realistic this 15 GW are 15 GW target?

If you could throw some light.

Nikhil Dhingra

Shaurya. I think, see, as you must have noted from our strategic plan, which we have also mentioned in the presentation, we are focusing more on the revenue generation capacity than the absolute megawatt number.

I think you pointed out really well that we are not flustered about

Operator

Sorry to interrupt you here, sir. Mr.

Sourabh Arya, may we request you to please self-mute your lines when management is answering? There is a disturbance coming from your line.

Thank you very much. Sir, you may please go ahead.

Right, right,

Nikhil Dhingra

right. In terms of the strategy, we were just explaining that the strategy is more about, of course, in terms of the numbers, right, in terms of the revenues we can generate, the profit we can generate, and, of course, the pace at which we can grow, right?

In terms of our strategic alignment, we are fully geared up to grow at a very fast clip in terms of both of these. How we achieve these gigawatts and how we achieve these crores is, of course, linked to the connectivity we have, right, which is more than required for this 15 GW, and the timelines of these substations, which is also very well in planning and very well in delivery.

So 15 GW is not at risk in terms of the GNA connectivity because the substations we are targeting for these 15 GW have a timeline of 2028 at last and maybe early 2029, right? The delays we see in these substations, and now the substations are coming up with a timeline of 36 months, 30 months, that is the extension already being done by CTU or the MOP in terms of the planning, which is, again, a very good step they have taken.

Even if you factor in a 6 months delay or a 12 months delay, we are within our goal of achieving this capacity. In terms of the BESS capacity, again, we have enough connectivity for doing those BESS projects we have spoken about.

The main thing, I think, Arya, which we are working on and keep working on is the customer, right? To have the demand for such projects and to be able to do these projects.

What may happen is we may do, let's say, a 17 GW and a higher amount of BESS, right, which is entirely likely going by the amount of peak power deficits which is coming if you notice the tender which Ankit spoke about, right? It is a higher amount of peak power which is needed, and in terms of revenue realized per megawatt, it is much higher, right?

The profit realized is also potentially higher. It is in terms of connectivity, in terms of the demand, of course, they are there, and we see good demand coming up because as you see the power prices in India, people have realized that you have to go full steam on all the sources and not choose a particular source.

Thermal may come up, right, renewable is also coming up with firm demand backed up, and peak power is also coming up. We see that a lot of bids are coming which are very rightly designed and which captures to the real demand.

We don't see from all these three perspectives of connectivity tie-up, the demand availability, and, of course, in terms of our execution abilities, we don't see a challenge. That's why we have upgraded because what we noticed is we have already 8.5 GW of PPAs, right?

We are going to participate in more than 3 to 4 GW of PPAs very soon. We notice that if we get those PPAs done by end of '27 or so, we will definitely be around 12 GW of capacity by 2029.

If we assume something in, let's say, a lot of BESS we are doing for which there is a ready customer available, there are a lot of states which want to buy those peak power projects. It is very, I think, very very safe to assume that in terms of contracted capacity, we can go reach there by 2027 in terms of tie-ups.

Of course, the execution will go on till 2029 and '30, but in terms of PPA tie-ups, we can go there by end of next year, calendar-wise. Wow,

Sourabh Arya

okay. Could you throw some more light on this 10 to 15, of course, incremental this 6 GW?

How much of this you're thinking on data center, hydrogen molecule, maybe from your own ACME Cleantech? Their plans are also going pretty pretty ahead.

If you could divide, will the nature of the business change from current PPAs with these central utilities or if you could divide? Shaurya,

Nikhil Dhingra

yeah, yeah. No, that's a good question.

In terms of the overall growth we are seeing in terms of demand centers, we don't see a change in the nature of the customer for us. Of course, there'll be incremental demand coming from various other sources including what you mentioned, data center, green ammonia, and multiple other demand areas.

Our primary source for capturing this would be these AAA PPAs with these counterparties like SECI, NTPC, SECI primarily now, and, of course, state governments. The addition to this would be state governments, which is entirely there.

Of course, we will participate in the SECI bids, like SECI is procuring power for green ammonia projects also. There, feeder to SECI is increasing of whatever sources you mentioned in terms of data center, green ammonia.

SECI is also catering to demand for these sources also. In terms of the conduit for us to get these PPAs, so that will remain a AAA counterparty and that is what we want to achieve.

We don't see a shortage of these bids, like we mentioned. We have sufficient bid to take it from 10 to 15 GW.

We are already at 8.5, if you see, if we kept it at 10, right, we are at 8.5 already in '26. That doesn't show any growth in terms of our contracting capacity for the next 2 years in terms of the bids won and PPA signed.

Because we have been winning projects to the rate of around 1.5 GW every year for the last three, four years. I think even if you project it like that, we are bound to reach that number.

We see a great increase in these bids coming up because of the shortage of peak power in India, and that is playing out in the terms of prices already. We see that 10 to 15 GW, an incremental 5 GW capacity, being won by us in the next 18 months, 12 to 18 months, for sure.

Sourabh Arya

We're not factoring anything from ACME Cleantech in this? That is also a part of it?

Yeah.

Nikhil Dhingra

We are not factoring in anything from the ACME Cleantech. Of course, it could increase this 15 GW further if ACME Cleantech were to, let's say, buy power for the green ammonia or for data or for any other sources through SECI or through any other agencies.

We are not factoring in that in this 15 GW. BESS

Sourabh Arya

gigawatt, okay, fair enough. Second is so, of course, what we all expect is these spreads of BESS will go down over 2-year, 3-year.

What matters is at what pace the new BESS comes into the system. Here we see you yourself are putting so big BESS numbers.

What do we expect about then these BESS spreads? Should they narrow very quickly?

Because let's say, I don't know what is the reason, but Q1 to Q2 itself it is down. That might be from a different reason.

But 2, 3 year hence, then how to think about this particular market from a spread perspective?

Nikhil Dhingra

If you look at Q1 to Q2, right, and if you look at the prices we have signed up for this year and next year, they have substantially gone up, right? In terms of the delivery, those contracts were already signed, right, in Q1.

We actually don't wait, right? We want to reduce risk.

What we do is we sign for, let's say, next two quarters, and these bids are also for next 6 months. They are not for, let's say, 15 months onwards.

It is 6 to 12 months maximum they are. The Q2 contracts were already signed.

The tariffs have not moved from Q1 to Q2, they were already contracted, right? We can tell you our tariff for Q3 also, right?

They are already contracted. In terms of the new bids we have won for, let's say, Q4 or Q1 of next year, they are substantially higher.

The tariffs are substantially higher than, you can say, what we have realized so far. It is dependent on how the states are feeling about their power demand in near term because these are near-term bids.

Structurally, let me tell you, there is a big shift happening from RTC procurement, which is the thermal procurement or a gas procurement, to BESS procurement. Because like we said in our previous conference call also, this is a new form of power.

BESS is a new form of power which has developed trust with now maybe 10 to 12 governments, which maybe our peers and us have supplied to. People are more and more confident about shifting their near-term power mix from RTC to batteries.

You will see that lot of new demand is being created. In terms of the tariffs, of course, the RTC at INR 7 or INR 6 is much more expensive than BESS at INR 10 because you are buying unnecessary volume of power, which you don't need to during the day when you contract out this RTC, and that volume is huge.

Basically, the 85% of the near-term power is RTC, right? Which is waiting to be disrupted.

Sourabh Arya

Perfect. Okay.

Sir, this is quite helpful. Thank you.

All the best.

Operator

Thank you. Next question is from the line of Shaunak Godbole from SBI Life Insurance.

Please go ahead.

Shaunak Godbole

Hello. Hi, everyone.

Thank you for the opportunity. I wanted to understand what's the capacity addition target for FY28 in megawatt terms, '27 and '28?

Nikhil Dhingra

In FY28, in terms of the GNA availability, we are looking at upwards of 3 GW. Around 2.5 to 3 GW is what we are looking at in FY28.

Because, Shaunak, we are seeing all of our substations coming alive during that particular year, and it is aggregating around that. You'll see from June to December, bulk of our substations are coming alive.

If you look at most of the substations date today, that is where they are. Of course, they're with some delay, we are very confident that there will not be further delayed because the elements are ready and the work is happening at a very good pace.

That's where we are.

Shaunak Godbole

What about '27? Because I guess initially it was 2.5, but when I was looking at the PPT last quarter, around I suppose 700 MW was one of the capacity which was basically the substations were ready for the GNA timelines as per the PPT.

It was around 700 MW. What is the status of that?

Because if you see in this quarter, we haven't commissioned any project, and H1 capacity addition is around, there is no any capacity addition in this H1, right, if I compare with the two quarters.

Nikhil Dhingra

Shaunak, when we look at the capacity addition, we look at the elements we have charged for each of these projects, right? We have laid out in our presentation and we have partially commissioned around 1.9 GW of capacity so far out of the total under-construction portfolio we have.

In that 1.9, we have partially commissioned solar at two places and battery at around four places. All of these projects are under those and excluding one project, which is ACME Suryodaya, all of these are under PPAs, and they are generating revenues.

In terms of if you are I think mentioning about the generating source, which is the solar, right? If you are tracking only that or in terms of the contracted capacity, we have operationalized 133 MW of grid-facing solar, right?

Of course, that is what we have done in this quarter. Of course, in terms of the commissioning targeted for FY27, it is depending on the Fatehgarh II operationalization, we could do 1.5 GW still, but, of course, it could move to a quarter by June or something, but 1.5 GW is what we are targeting for FY27.

Shaunak Godbole

Okay. Okay.

On the financials, I had a query. If you see your interest cost has been flat for the past two to three quarters.

Basically, what's the reason for that? Because we have commissioned battery, ideally, depreciation is increasing, basically, finance costs also should increase, right?

Nikhil Dhingra

So Right. There are a couple of reasons for that.

One is that we've done a QIP raise, right, of around INR 2,800 crore. That has, of course, resulted in us paying down some of the debt, which has resulted in saving that interest cost, right?

That is one of the key reasons. The second thing is some of these cash flows we are generating from BESS, right, that is also saving on the debt drawdown from our side that we are able to use it as equity and that is increasing the internal accruals available to either pay down debt, because we are paying down debt from these internal accruals also and not incurring the interest cost, and we are drawing down less debt because these accruals are to be used for capex or for debt reduction.

In some cases, lenders have allowed it for using it as equity also. That is resulting in us keeping flat.

The third thing is we have refinanced higher interest rate bond. Right now, we don't have any dollar exposure in the overall book.

It is 100% rupee, and that has resulted in substantial interest saving in this quarter for us. Which will continue to be there going forward.

These are the three, four reasons we have.

Shaunak Godbole

Okay. Thanks.

Just one question. Even I was looking at the other expenses, for the past two to three quarters, it was a bit higher.

This quarter, it is, as compared to the last quarter, it is around INR 45 crore. Is there any specific trend has to look at it or how to look at it?

Nikhil Dhingra

Arun, what does these other expenses include?

Arun Chopra

Other expenses basically include the O&M expenses, which we generally incur, and in the last quarter, the other expenses was higher because there was a one-time expense of the authorized capital being increased of companies and probably in almost 7 to 8 companies, it was almost INR 20 crore, this was on the higher side in the last quarter, but generally, it remains static if you see on a quarter-to-quarter basis.

Nikhil Dhingra

This ROC bit, I'll just explain. It is basically when you put equity in a company, you have to pay a fixed ROC fees for issuing share capital.

That is very lumpy and it only comes when you start doing a project. That keeps it kind of a lumpy.

I think maybe we can have a line item showing this or in schedules we can show this, yeah, as a one-time expense. That will help you to predict it on a quarter-on-quarter basis going on.

Shaunak Godbole

Can you just repeat what was that one-time expense? I didn't

Nikhil Dhingra

ROC, Registrar of Companies, when you put share capital into a company, right,

Arun Chopra

When you increase your authorized capital, basically you have to pay an ROC fees.

Nikhil Dhingra

That ROC fees, when you start a project, how much is it typically?

Arun Chopra

It goes from limited at INR 2.5 crore.

Nikhil Dhingra

Around INR 2.5 crore per SPV you need to pay that. That increases whenever you start putting equity in a company, right, you need to pay this INR 2.5 crore,

Arun Chopra

so that

Nikhil Dhingra

per SPV. That keeps it slightly unpredictable to that extent.

Okay.

Shaunak Godbole

Okay. Thank you very much.

Operator

Thank you. Next question is from the line of Apoorva Bahadur from IIFL Capital.

Please go ahead.

Apoorva Bahadur

Hi, sir. Thank you for the opportunity.

A couple of questions. One is on the partial commissioning of projects that we have done.

Would be helpful if you can explain so do we capitalize these assets and start charging all the expenses to P&L or they're still capitalized on balance sheet?

Nikhil Dhingra

Apoorva, wherever we are selling power, we have expensing out because we have capitalized and rest is wherever we are not selling power, it is not yet capitalized.

Apoorva Bahadur

The solar which is used to charge your batteries, would that be capitalized or it's only the battery?

Nikhil Dhingra

That is capitalized completely, yeah. See, we are selling power means we can sell to the grid or we can sell to our own BESS, right?

In both cases, the sale is being made from that SPV. Wherever the sale is being made, we have capitalized, right?

I think wherever we have said partially commissioned, they are capitalized.

Apoorva Bahadur

Understood. Our gross block already includes them, it's no longer in the CWIP?

Yes, yes,

Nikhil Dhingra

yes. Exactly.

Apoorva Bahadur

Understood. Secondly, on these new PPAs which we are signing, I believe that they will be under the ambit of ALMM-II now.

How are you seeing the pricing for DCR ALMM-II compliant modules? What's your view?

When would you tie up for these? Would it be this year, next year?

Right,

Nikhil Dhingra

right, Apoorva. We have plans of buying modules for these projects from, you can say, June onwards of next year.

Because these are commissioned targets from December onwards, December to March of '28, those are the timelines for commissioning these projects. We have done some initial negotiations and discussions because we don't intend to buy immediately.

Of course, whatever briefings we've done, we are getting prices of lower than 17 as of now, but it is very dependent on the various factors. We are substantially within the prices we had assumed in terms of bids for that.

That's not a risk we see. Of course, given the Chinese regulations which have come into force in terms of the recent Chinese regulation, if it impacts the cell capacity in India, then we will have to see, but it doesn't look like.

There is already substantial cell capacity which has come up or which is ALMM-registered and which is already there. We don't see these prices increasing because of shortage of suppliers.

That we think that because of that, the prices will not increase.

Apoorva Bahadur

Connectivity for all these projects, we had to declare them before bidding or is it like we will still have to wait for CTU to commission those substations and only then? There could be a deferral in further setting up these capacities?

Nikhil Dhingra

No, actually, see, most of these projects are peak power projects. These ALMM, if you are only talking about ALMM-II or you're talking about all projects?

Apoorva Bahadur

The recent ones, the ones which we have say signed PPA this quarter or

Nikhil Dhingra

Yeah. Most of these projects are peak power projects.

We are already installing where GNA is almost operational. There is no GNA risk because these peak power projects are actually very immune to GNA delay because we typically install them at projects where GNA is live.

In a lot of our book, there is no GNA dependency delay because they are operational. Most of the peak power projects we are doing, the GNA is operational.

There is no risk to these timelines. Other than maybe you can say RTC project or REMCL, wherever you need to install a grid-facing solar project, there you are more dependent on the GNA being getting delayed, but in peak power projects like the ones where the battery is supplying power to the grid, from our side, we allot such that there is no delay possible in those projects because of GNA.

Apoorva Bahadur

Okay. Just last question on this peak power projects.

I think one of the recent projects we have signed at a tariff about INR 6, where we have to supply during peak hours and we also have to arrange for the charging power. How does the math work at INR 6?

Because I think the battery cost at $100 itself would be closer to INR 4.5, right, 12% IRR, on top of that, the cost of charging. What type of equity IRR are we seeing over there at INR 6 tariff?

Right,

Nikhil Dhingra

right, Apoorva. In terms of that project and the resultant economics of it, there are a couple of things in terms of the early commissioning, right, because as I mentioned, we have allotted these projects to an operational GNA.

For us, the solar takes time to come up, right, because of ROW issues, because of the land acquisition issues, but battery comes up for us fairly early, and as you see, we have preponed a lot of these battery commissioning. In terms of the battery commissioning, the battery will come up earlier for these projects, and, of course, since the PPA is signed, the debt is available as well.

There is early commissioning revenue which you realize out of this project because specifically it is available to sell power today. That's the key difference between our earlier projects and this project.

Of course, it is dependent on the competition, right? Nobody likes to reduce their returns, but we make a high-teen return on this even if we factor in, you can say, a 6 to 12 months of operations of short-term power, but we will, of course, have around 24 months, maybe we will do higher than that.

Apoorva Bahadur

Fair enough. Thanks a lot, Nikhil.

All the best. Thank you.

Nikhil Dhingra

Thank you.

Operator

Thank you. The next question is from the line of Dhruv Muchhal from HDFC Asset Management.

Please go ahead.

Dhruv Muchhal

Sir, thank you so much. Sir, you made a comment that 85% of near term is RTC and is waiting to be disrupted.

I didn't get that point. If you can please expand on that?

Nikhil Dhingra

Dhruv. Basically, in terms of the DEEP portal, there is a DEEP portal, as you must be aware, where discoms procure short-term to medium-term power, right?

The volumes in that DEEP portal, 85% of them are through thermal, RTC kind of tenders, and only 15% are through, you can say, gas or other sources, right? That is where we were saying that this 85%, right, because there was no availability of other sources, that was the trend.

Because people are buying like we see a lot of states buying this RTC power when they only need peak power because there is no other source available. Like you saw Gujarat, right?

Gujarat used to buy a large amount of RTC power, but this year, you see Gujarat bought a large amount of peak power, so that has reduced their RTC purchase volume of these short-term and medium-term power. That is what I was talking about.

Dhruv Muchhal

Got it. Perfect, sir.

Got it. Sir, the second thing is in your presentation, you mentioned 50 GW of peak power bids rolled out till September '27 and 20+ GWh of upcoming tenders.

This is a large quantum. In your assessment, is it backed by state demand or like previously SECI and others used to just roll out tenders without any demand assessment?

You might have done some work around this. Is it backed by state demand or how is it?

Nikhil Dhingra

Yes, Dhruv, primarily state demand only because SECI doesn't have demand of its own, and, of course, we are working because now we are selling power to a lot of these states on short-term basis. We have a big understanding of what they need and in what timeframe.

What we have done is mapped out their demand in short term, medium term, and long term. What we realize is in a short to medium term, there is very high demand for peak power, right?

There are a lot of 5-year PPAs. People are trying to contract out some of these PPAs expecting their thermal to come up or expecting their PSP to come up, right, or expecting these slowdown in the demand.

Some of the states are rightfully looking at 20-year PPAs also, depending on each state, this varies from state to state, but everybody is short on peak power, and nobody wants to be dependent on the weather patterns to assess their demand and also depend on other capacities to come up, and they are impacted because of GNA delay. As you must have noticed, a lot of these states are impacted because the plants are not coming up because of GNA delay in short term.

They are very skeptical of the commissioning timelines, and that is why, maybe looking at their plan, they may be contracting out surplus than what they may need or may not need. That is where states like Chhattisgarh, Odisha, like Bihar,

Dhruv Muchhal

Telangana,

Nikhil Dhingra

if you notice, large amount of bids have come up from Telangana, and now with Chhattisgarh, Andhra Pradesh. A lot of these states are coming up with their own bids.

Of course, and in our SECI bid, states like West Bengal is buying, and a lot of other states are buying because everybody is short on peak power. They don't have a firm tie-up for their peak power, right?

In terms of solar, some states are surplus, you're right. That is the case.

Nobody is now installing solar and sending it to the grid. Everybody is converting into peak power, and that is the intent with which the states are also buying power.

If you notice, there is a recent SECI tender which has come up today only, which Ankit also spoke about, that's a 16 GWh tender, 4 GW into 4, 16 GWh tender, and it is coming up with a VGF and it calls for a 12-month commissioning, right? That is purely looking at the power situation prevailing today, and it caters to somebody who is ready to supply power because they want to promote the battery installations sooner than later because that is where the issue is in terms of procurement of power, and that is where the trend will go in terms of the procurement, and that is where we see the shortage.

The pure solar, the conventional method of seeing that solar bids and all that, that is no longer true. That is why the megawatt-hour are also there.

In terms of RTC, RTC at 5.25 is again a very competitive bid which happened at SECI, which is currently being sold. That will also, once it becomes a mainstream and people are able to commission that plant, the issue with some of these bids is the plants have not got commissioned, right?

Once these plants come online with the GNA going live, I think the belief in these PPAs will also go substantially up, and then you will see a lot of procurement happening from these kind of RTC also because it's very competitive, right, in terms of the price. It is much more competitive than a thermal or any other source, right?

In terms of the awareness, it is building up and that is where you see Telangana kind of project states which have come up with this RTC and peak power project bids. More and more states are picking this up, and in terms of competitiveness, it stays, right?

Competitiveness stays for all the three sources of renewable: solar, wind, and battery, and, of course, PSP also in certain context in terms of life of the project and the stability it provides. I think the fundamentals are strong, states are buying.

A lot of demand has shifted to states, and now we understand that a lot of aggregation will happen at the central level for this peak power. SECI has already come up, maybe some other agencies will also come up with a similar bid of a large quantum of battery procurement.

Dhruv Muchhal

Sure. Sir, one quick question.

Your generation has grown by about 20% Y-o-Y, your capacity is almost flattish, and I see your PLF has improved. Just trying to understand, is it repowering that which is driving such a massive increase in the generation or is it the partial commissioned assets are also included in generation now?

Nikhil Dhingra

There are two reasons for it. One is, like you rightly said, the capacity has increased and also the repowering has increased.

Then the third, the wind has come up online. As you see, it has done around 41% CUF in in this quarter, right?

Introduction of, because wind was not there last year, 150 MW of wind is there, which is contributing significantly to the average CUF, and, of course, I think that's that's the main reason. Then the weather patterns.

Last

Dhruv Muchhal

year,

Nikhil Dhingra

last year, sorry, our Sikar plant was not fully operational, which became operational on a Y-o-Y basis, so that actually when in the last year, it was contributing less. If you look at the next quarter after that, it will be much less steeper growth curve.

Dhruv Muchhal

Got it. Great, sir.

Perfect. Thank you so much and all the best.

Nikhil Dhingra

Thank you.

Operator

Thank you. Ladies and gentlemen, that was the last question.

With that, we come to the end of the today's call. One more thing,

Nikhil Dhingra

sorry, I'd just like to correct one query. I think Puneet asked about the reduction we have shared in the newly signed PPA.

There is around 33 paise reduction, out of which 11 paise is tentative change in law and 22 paise is voluntary, I think that's the broad reduction in the tariff for the NTPC PPA. Just for everybody's reference, I pointed out.

I don't know whether Puneet is there or not, but I'll just clarify. Thank you.

Operator

Thank you very much, sir. Ladies and gentlemen, on behalf of ACME Solar Holdings Limited, that concludes this conference.

Thank you for joining us, and you may now disconnect your lines. Thank you.