Q1 FY2027 · Earnings Call TranscriptAugust 17, 2026

Operator

Ladies and gentlemen, good day, and welcome to the Ahluwalia Contracts India Limited Q1 FY '27 earnings conference call hosted by Ambit Capital Private Limited. As a reminder, all participant lines will be in the listen-only mode, and there will be an opportunity for you to ask questions after the presentation concludes.

Should you need assistance during the conference call, please signal an operator by pressing star, then zero on your touch-tone phone. Please note that this conference is being recorded.

I now hand the conference over to Mr. Sudeep Bora.

Thank you, and over to you, sir.

Sudeep Bora

Good evening, everyone. On behalf of Ambit Capital, I thank the management of Ahluwalia Contracts India Limited for the opportunity to host their Q1 FY '27 earnings conference call.

To discuss the results, I'm pleased to welcome Mr. Shobhit Uppal, Deputy Managing Director, Mr.

Vikas Ahluwalia, Director, and Mr. Satbeer Singh, Chief Financial Officer.

Now, I invite the management to take us through the key highlights of the quarter, post which we'll open up for Q&A. Thank you, and over to you, sir.

Shobhit Uppal

Thank you. Good afternoon, everybody.

Ahluwalia Contracts India Limited has announced its financial results for Q1 FY '27. During Q1 FY '27, the company has achieved a turnover of ₹1,125.81 crore and a PAT of ₹11.42 crore, in comparison to a turnover of ₹1,004.88 crore and a PAT of ₹51.11 crore during Q1 FY '26.

The company has registered a growth of 12.03% in turnover and degrowth of 77.65% in PAT during Q1 FY '27, in comparison to Q1 FY '26. EPS of the company for Q1 FY '27 is ₹1.70, compared to EPS of ₹7.63 in Q1 FY '26.

During Q1 FY '27, the company's EBITDA margin is 4.29%, as compared to 8.59% in Q1 FY '26, and PAT margin is 1%, as compared to PAT margin of 5.01% in Q1 FY '26. The primary reasons for the dip in EBITDA margin are as under.

There has been a finalization of the bill of the AIIMS Jammu project, which has resulted in a reduction of bill value by ₹29 crore. This is a cause of dispute, and now that the bill has been finalized, the dispute will be raised through an arbitration process.

The adverse impact on this account is 2.6% on our EBITDA. Then there has been an adverse impact on account of West Bengal and Assam FIR drive and elections.

This has led to a reduction of turnover in the projects that are being executed in these states, and it has impacted in higher IDC costs, thereby impacting our EBITDA margins. Then during this quarter, labor rates have increased significantly in NCR, which contributes nearly 50% to our total portfolio.

The minimum wage increase has been to the tune of about 35% to 40%, spanning over unskilled and skilled categories. This has led to a substantial increase in our wage costs.

Then there has been an increase in our staff costs, where we have significantly increased our employee base as we have strengthened the organization, mobilized staff resources for our enlarged project portfolio. The net order book of the company as on 30th June is ₹20,663.52 crore to be executed over next 3, 3.5 years.

Total order inflow during FY '27 till 30/6/2026 as well as up to date is ₹512.81 crore. We are ready to receive questions.

Operator

Thank you very much. We will now begin the question-and-answer session.

Anyone who wishes to ask a question may press star and one on their touch-tone telephone. If you wish to remove yourself from the question queue, you may press star and two.

Participants are requested to use handsets while asking a question. Ladies and gentlemen, we'll wait for a moment while the question queue assembles.

The first question is from the line of Shravan Shah from Dolat Capital. Please go ahead.

Shravan Shah

Hi, sir. Sir, to further understand this EBITDA margin because 4.3% is kind of one of the historic lowest margin.

I understand you try to explain, but further want to understand in detail. First, you are saying this ₹29 crore for AIIMS Jammu that the bill which was under dispute now finalized.

This ₹29 crore we have booked in raw material cost and which has led to a kind of 2.6% impact.

Shobhit Uppal

You can say that. This is under dispute now after finalization of the bill.

As the project was completed last year, and final billing and its checking was under process. Now, during this quarter of Q1, it has been frozen, and now final bill value has come down by ₹29 crore.

Shravan Shah

Okay.

Shobhit Uppal

And You're right. The costs have been there, but the bill value has come down, the receivables have come down.

Shravan Shah

Yeah. The other part what you highlighted in terms of West Bengal, Assam, and the labor cost increase.

In the last call when we did, so that must be known to you at that time or even post the last concall, this was the thing and that's why there is a significant impact on the margin?

Shobhit Uppal

The increase in labor was not known during the last call, and it is a hefty increase. While there is a labor escalation clause in a few of our contracts, but quite a few contracts don't have this clause.

A lot of our large orders with some large developers, the labor escalation is not there. Post this increase, we have reached out to these clients and submitted claims, if you may say, wherein we're asking for a revision in our item rates, which can lead to compensation on account of the large increase in labor costs.

The most significant increase has been in NCR, especially Haryana and UP, where 50% in NCR 50% of our order book is in NCR. That is why it has hit us in this quarter.

Shravan Shah

Got it. Now, given these things we know, in Q2, do we see matlab how much the clients have agreed to kind of compensate or still it will take time?

How one can look at net net in Q2? Will the similar margin or can we, because we were looking at double-digit, when can we start seeing a double-digit from Q3 itself?

For full year, how one can look at the margins?

Shobhit Uppal

Look, there are a number of external factors, one being this radical increase in pricing by the government of Haryana and the government of UP. It is not possible for us to put a date as to when we will be compensated, whether it'll be in Q2.

We expect that, over the next two quarters, some of this compensation will start flowing in. Having answered the first part of your question, the second part, Q3, again, we are hearing rumors about NGT, the impact on account of NGT, Government of Delhi and Haryana looking to take stringent measures.

While nothing is there in black and white, but we can't quantify the impact on our EBITDA of the potential NGT impact. I cannot tell you whether we will be hitting the double-digit in Q3.

Q3 is likely to be impacted by NGT. How much, we cannot sort of give you an indication today.

Shravan Shah

At current juncture, what do you think that what kind of a margin we can look at, let's say, for the full year or maybe Q3, or when can we start seeing a double-digit from Q1 FY '28, or still it would be a difficult, maybe a one or See, this year this year has been yeah,

Shobhit Uppal

this year, there have been a few black swan events. One, of course, has been the war.

Second, of course, has been this labor pricing has impacted us in a major way because a couple of our projects, there are the labor factors as it is are higher because some materials are being supplied by the client or clients. It would be fair to say that this financial year, we're ruling out having a double-digit EBITDA margin.

Shravan Shah

At what max number one can look at, let's say, if I have to look at other way, how max, because as you highlighted, Q3 also Q2,

Shobhit Uppal

look, Q2 is an aberration primarily, as I said, 2.6 percentage point have been shaved off because of one this thing, and that also, it's something that the client at one time had agreed and now, for various reasons, they've gone back on it. It will we we are already looking at we are starting arbitration proceedings.

We we should whatever we had was there in Q1 of the of the last financial year, we're we are hoping that we would get back to those margins over the next three quarters. The effect of NGT, that is a rider that I'm putting here.

We we are unaware how much that is going to contribute or hit our margins.

Shravan Shah

This, in any way, is also impacting the execution? Whatever we were looking at, 15%, 20% growth for this year and even similar number for FY '28, there, is there any change on the lower side?

Shobhit Uppal

No, we still feel there has been a top-line growth this time around. We still feel that we will grow at about 12% to 15% top-line growth, and, as per the historical EBITDA margin over the past couple of years, we should be there and thereabouts.

Shravan Shah

Okay. Okay.

Some balance sheet numbers, sir, also Satbeer, sir, if you can provide inventory, debtors Inventory Inventory, debtors, trade payable.

Satbeer Singh

Debtors is ₹776 crore.

Shravan Shah

776?

Satbeer Singh

Yes.

Shravan Shah

That is the debtors.

Satbeer Singh

Pardon?

Shobhit Uppal

That is the debtors he's asking.

Shravan Shah

Debtors. Trade receivable is ₹776 crore, you said.

Satbeer Singh

776 trade payable, and debtors is ₹632 crore, and retention is ₹401 crore.

Shravan Shah

Sorry. How much you said retention is?

Satbeer Singh

Retention ₹401 crore.

Shravan Shah

₹401 crore. Inventory is?

Satbeer Singh

Inventory, including real estate inventory, ₹391 crore.

Shravan Shah

₹391 crore. Mobilization and unbilled revenue?

Satbeer Singh

Mobilization ₹924 crore, and unbilled revenue is ₹946 crore.

Shravan Shah

That is also sharp increase. Gross debt and cash?

Satbeer Singh

Debt is ₹2 crore hardly, ₹2 crore 28

Shravan Shah

lakh, and cash and bank balances,

Satbeer Singh

including cash and bank balance, is ₹920 crore.

Shravan Shah

₹920 crore. Okay.

Okay. Thank you, sir.

Shobhit Uppal

Thank you.

Operator

Thank you. The next question is from the line of Vaibhav Shah from JM Financial.

Please go ahead.

Vaibhav Shah

Sir, we saw a sharp increase in interest cost in the first quarter. The reason for that and could this be a recurring number in coming quarters?

Satbeer Singh

This is increase in finance costs due to we have availed mobilization advance during this quarter for the new project, Central Vista project. That's why there is increase in finance costs.

Vaibhav Shah

In coming quarters, it should be a similar number every quarter, ₹15 crore, ₹16 crore?

Satbeer Singh

Yes,

Shobhit Uppal

yes. It will be a similar number.

Vaibhav Shah

Sir, out of mobilization advance of ₹924 crore, what is the interest-bearing portion and the interest rate blended?

Satbeer Singh

This is 31%.

Vaibhav Shah

31%. The interest rate?

Satbeer Singh

Interest rate, you might say, around average 8%.

Vaibhav Shah

Okay. Sir, secondly, on Gems and Jewellery Park, what are the challenges which you are facing, and when can the work on the ground begin, and what is the revenue expectation on the project in this year and next year?

Shobhit Uppal

There is a change in design or requirement happening from the client side. That is why while the architectural designing has been done, but that is undergoing a change.

I think work on the ground will not happen in this quarter. It is likely to begin in quarter 3, and we're looking at a billing of about ₹100 crore in this financial year.

Satbeer Singh

Sir,

Vaibhav Shah

and next year?

Shobhit Uppal

Next year, the billing should be to the tune of about ₹450 crore.

Vaibhav Shah

What is the timeframe of completion for the project?

Shobhit Uppal

It's 3.5 years.

Vaibhav Shah

Okay. Okay.

Sir, on the CST project, we have not seen that kind of pick up even in the first quarter. How do you see the revenue moving in over there in this year and next year?

Shobhit Uppal

We are looking at an average billing in the 9 months after the first quarter to the tune of about ₹40 crore to ₹45 crore. That is roughly a billing of about ₹450 crore, ₹400 crore to ₹450 crore in this financial year, which will be ramped up to about ₹700 crore in the next year.

Vaibhav Shah

Sir, what is the main challenge over here? We have earlier, we were targeting close to ₹600 crore in this year.

What is stopping us from doing that?

Shobhit Uppal

We are hopeful that we'll still touch about ₹500 crore. As I said, we've done about ₹70 crore in this quarter, and if we do about ₹450 crore in the balance 9 months, we are hoping to cross ₹500 crore here.

Vaibhav Shah

Any project-specific issues?

Shobhit Uppal

Sorry?

Vaibhav Shah

Any project-specific issues over there?

Shobhit Uppal

No, the project is basically divided in two parts. One is the platforms and the station area, and the other is the new buildings which are coming up.

Work on the new buildings, which is the LD node, DRM building, all this, the DRM building has started. LD node will start now.

The client is approving in stages. That's why the work cannot be taken up all at one go.

As far as the platforms and station areas go, there we get blocks as per the traffic. That is why it is taking time.

Vaibhav Shah

Okay. Okay.

Sir, lastly, on Central Vista, how is the work on ground going, and what revenue are we targeting for '27 and '28?

Shobhit Uppal

FY '20 work Let me first tell you, there are two buildings which were to be broken there, Nirman Bhawan and Udyog Bhawan. Nirman Bhawan completely broken.

The foundation casting has begun, and in September, we'll start erecting the structural steel. Udyog Bhawan was handed over to us about 3 weeks ago, and 90% of that has been demolished.

The demolition will be completed in the next 15 days, and we've started the excavation work. A month from now, the foundation works will start in that area also.

We are looking at a billing of about ₹700 crore in this financial year.

Vaibhav Shah

Sir, next year?

Shobhit Uppal

Next year, it would be about ₹1,000 crore.

Vaibhav Shah

Okay. Sir, you mentioned that

Shobhit Uppal

We are looking to complete the building which we started where Nirman Bhawan existed, which is about 50% of the job, we're looking to commission it by the end of next year.

Vaibhav Shah

Entire project should be completed in FY '29?

Shobhit Uppal

Entire project will be completed in FY '29, yes.

Vaibhav Shah

Sir, on revenue, you mentioned 12% to 15% growth, right? We are lowering the guidance from the previous call?

Shobhit Uppal

It was 15%. We are sticking to that.

As I said, the lower 12 the NGT is something which we are not sure about what impact that is going to cause. That is why.

Vaibhav Shah

If it is similar to what happened last year, then we may cross 15%?

Shobhit Uppal

Yes.

Vaibhav Shah

Okay. Okay.

Thank you, sir.

Shobhit Uppal

Thank you.

Operator

Thank you. The next question is from the line of Sandip Sabharwal from asksandeepsabharwal.com.

Please go ahead.

Sandip Sabharwal

Yes. I think your last conference call happened 15 days after the end of the previous quarter.

It's very difficult to believe that you did not know the impact of the new labor charges, etc., and what impact it'll have on your first-quarter results because your results and concalls typically happen 45 days, last day of the results season. I've been observing that you've been giving guidance on growth, on margins, etc., last many quarters, but I think those have no relevance actually because the numbers which come out are totally different.

Have you any comments to offer on that?

Shobhit Uppal

It's a very generic observation that you've given. You have some data, or we can have a separate meeting.

Our CFO can meet you. I would like to think that we have been more or less in line with the guidance that I've been giving over the past 3, 4 years post-COVID.

If you could be a little more specific. While I agree No, no, no, no, let me complete.

While let me address the first part of your query that whether I was aware or whether we were aware of the impact of the price escalation on account of labor when we did our last investor call. Are you insinuating that I was aware and I hid that?

Sandip Sabharwal

Do you have

Shobhit Uppal

some specific data? Do you have some specific data which you want an answer from me to?

Sandip Sabharwal

Your last conference call happened 45 days after the end of the previous quarter. You, I think, had a call around the 15th or 16th of May.

You are saying that the new labor charges were imposed on you after 15th of May or before 15th of May? Was that for full month, or full quarter, or half of the quarter?

Shobhit Uppal

If you know the nature of our business, if you track this industry, you would know that April, May, June are traditionally that part of the calendar year where labor is in extreme short supply on account of various factors. This quarter, this was further exacerbated by a slew of festivals, especially Muslim festivals.

50%, 60% of our labor, skilled labor, or 80% of our skilled labor is Muslim, right? The impact on the ground was felt much more, which was very difficult to predict, especially in NCR, especially in Haryana and UP, where government further compounded this issue by increasing the labor cost by 40%, 35% to 40% between skilled and unskilled.

It was very difficult for us to predict the impact on our costs. Have I spelled out the position clearly?

Sandip Sabharwal

No, not really, because when was the increase in labor cost done for you? Was it from 1st of April?

Shobhit Uppal

It's an ongoing process. Then you are not understanding, then it seems you've not tracked this industry.

Please understand, what we are paying today on the ground to a bar bender or a carpenter or a mason, that is totally based on demand and supply. In most cases, over the past 2 months, it has been more than what the government has mandated.

It's a demand and supply issue. If you track this industry, you would know that.

If you don't, we would be more than willing to meet up with you and give you a refresher course.

Sandip Sabharwal

No, no, I don't need a refresher course. There's no need for you to become aggressive on the call.

It's a

Shobhit Uppal

No, no, I'm just telling you, you are insinuating. Your first question that you asked me, you are insinuating that I've hidden some facts.

You need to articulate better your questions. No,

Sandip Sabharwal

no, I said you have a call middle of the quarter. By that time, you should have a fair idea of what's happening in that quarter.

If you don't have a fair idea of what's happening in that quarter, then any kind of guidance is of no relevance.

Shobhit Uppal

Look, I know what guidance I'm giving. It is your prerogative to agree to it, believe it, or not believe it.

I am willing to invest more time with you and trying to take you through what impacts my costs on the ground. You are the one who's saying you don't need it.

What more do you expect from me?

Sandip Sabharwal

No, I don't think Anyways, let it be.

Shobhit Uppal

Let's move on.

Operator

Thank you. The next question is from the line of Vishal Periwal from PL Capital.

Please go ahead.

Vishal Periwal

Sir. Thanks for the opportunity.

Shobhit Uppal

Hi, Shobhit.

Vishal Periwal

Thanks, sir. Sir, on this labor, whenever these changes happen, can this be considered more like a GST-related changes, a change of law?

Will this become applicable, and then the same can be passed on to our clients?

Shobhit Uppal

This is not considered a statutory increase, while if a certain component of the increase, say if the PF was getting increased, that would be taken as a statutory increase, which the clients would have to necessarily bear. In terms of increase by the government, it's not a statutory increase, as I said, but having said that, we are still writing to all our clients and telling them that this increase, coupled with the demand and supply issue, today labor has become a big issue.

Especially over the last 2, 2.5 months, all our projects, especially in NCR, have been operating at 40% to 50% labor strength. We have reached out to our clients, and they have been sympathetic in at least listening to or going through the numbers that we are presenting to them as to the impact on our costs.

We are hopeful that the projects which do not have a labor escalation clause with some of our larger clients in NCR, client will consider compensating us to some extent.

Vishal Periwal

Okay. From accounting point of view, the employee cost that we book in our P&L, does this have an impact of labor or it's only the HO-related and other things which is part of the employee cost?

Say ₹120 crore in this quarter.

Shobhit Uppal

It has To the extent that such labor is employed by the company, it is included therein, and what is not employed and they are into contractors or labor suppliers, that is in the subcontractor or labor cost.

Vishal Periwal

Okay. Because from the P&L, it looks like, I think, probably a ₹30 crore kind of impact which is coming from the AIIMS, and if it is getting booked somewhere in the raw material subcontracting where the labor cost is also there, then that explained probably a ₹30 crore impact.

The other impact is the employee cost increase, that is impacting much more to our P&L, I think that what I could gather.

Shobhit Uppal

You're right. One one is that ₹30 crore.

There is actually a threefold impact on our EBITDA, right? One is that ₹30 crore.

The other is broadly split up into our increased staff cost and increased labor cost.

Vishal Periwal

Okay. Maybe one last thing.

In terms of the employee cost, is there any one-off in terms of any bonuses or anything that has happened, or it's more like a recurring employee cost?

Shobhit Uppal

It is just this that this should rationalize over the next three quarters because we have ramped up considerably on account of our large projects, like Central Vista starting, or Dalia starting. These are large projects.

One is a ₹3,000 crore-plus project. One is a ₹2,000 crore-plus project.

Also, another project for DLF, which is Downtown, which is also a ₹1,600 crore, ₹1,700 crore project, that project has been delayed owing to design changes. There the client is looking to compress timelines.

We've further ramped up our mobilization in terms of our staffing there. These large projects, to say, as their turnover from these projects or their contribution to top line increases, the percentage-wise staff cost will rationalize.

Vishal Periwal

Okay. I think that's all from my side, sir.

Thank you very much.

Shobhit Uppal

Thank you.

Operator

Thank you. The next question is from the line of Shravan Shah from Dolat Capital.

Please go ahead.

Shravan Shah

Hello. Sir, currently the L1 last time we said, ₹1,620-odd crore, the hospital in Delhi and Odisha Government University, Bhubaneswar.

Out of that, which one got converted into LOA and

Shobhit Uppal

No, university, they were asking us to increase our bid validity. We refused because that was a fixed-price contract, and seeing the volatility and the increase in costs at the ground level, we refused.

That has fallen through. That is no longer live now.

RML continues to be live.

Shravan Shah

Okay. So, ₹512 crore inflow for this quarter is different from the RML, which is still L1, or that is the one which got converted into LOA?

Shobhit Uppal

RML is still L1. RML has not translated into a work order as yet.

This 512 is different from that.

Shravan Shah

Okay. RML value is ₹700 crore, ₹600 crore?

Shobhit Uppal

No, I think it's ₹500 crore.

Satbeer Singh

₹500 crore.

Shravan Shah

₹500 crore. Okay.

Then full year, what we guided in terms of inflow, ₹8,000 crore, so that remains intact?

Shobhit Uppal

No, to be frank, we are no longer very aggressive. That should come down because this volatility both in terms of material prices as well as labor prices, we are looking for this to stabilize.

As it is, our order book is ₹20,000 crore-plus. We're being conservative as far as the rest of this year is concerned in our approach towards picking up new orders.

Shravan Shah

Maybe ₹4,000 crore, ₹5,000 crore for full year, we can

Shobhit Uppal

Itna to ho jaega, yes.

Shravan Shah

Okay. Got it.

Currently, in terms of the bid pipeline, that will also will be now reduced, should be a ₹5,000 crore, ₹6,000 crore?

Shobhit Uppal

What I'm saying is our bid pipeline, the visibility is there. We'll not be very aggressive.

We'll factor in the ground realities and these fluctuations, and then bid. We will not bid very aggressively.

Shravan Shah

Okay. Got it.

Currently, from the total order book, ₹20,000 crore-plus, 11%, 12% would be the fixed-price contract?

Satbeer Singh

Yes. 10.34%.

Shravan Shah

10.34%. Okay.

Capex in Q1, how much we have done? For full year, we were looking at ₹300 crore.

There also any slowdown in terms of the capex?

Shobhit Uppal

This quarter was ₹60 crore. That's full year, we will reduce it to anywhere between ₹220 crore to ₹260 crore.

Shravan Shah

Okay. Overall, in terms of at working capital level, there, from here on, do we see some further pressure will be there or it will remain here or can improve by year end?

That

Satbeer Singh

we are expecting in this quarter that to be reduced from the existing level. At present, it's 119 days, and because of we are getting money from the Assam regions and that we are expecting that should be at previous quarter's level.

Shravan Shah

Okay. Got it.

Thank you, sir.

Shobhit Uppal

Thank you.

Operator

Thank you. The next question is from the line of Parvez Qazi from Nuvama Group.

Please go ahead.

Parvez Qazi

Hi. Good afternoon, sir.

Thanks for taking my question.

Shobhit Uppal

Hi, Parvez. Yeah.

Parvez Qazi

The external environment is challenging, there is no doubt about it, both on execution and on the cost front. The first question is, we have a relatively lower proportion of fixed-price contract at about 10-odd percent, but, in general, how have or how has commodity price volatility been over the last let's say, 5-odd months since the Iran war started, and, on the ground, how difficult or easy has it been to navigate through these challenges?

Shobhit Uppal

As I mentioned earlier, we're facing the brunt both on account of materials and labor, right? While labor, I've answered in detail as the questions have been asked since the call began.

As far as the material is concerned, impact is on two counts. One is the price increase, and second is the supply chain getting impacted in terms of the delivery getting impacted because of the war.

That has also led to, say, let me give you an example. Now, we buy a lot of panels, which run into many, many crores, right?

The switchgear is not available. Delivery which used to take 4 to 6 weeks is now taking 3 to 4 months.

That is impacting our performance on the ground also. While in between, whenever there was a call for ceasefire or news of ceasefire happening, the prices used to stabilize.

The impact, it's been up and down. This quarter has been impacted by that also.

Coming back to some of our large contracts and labor specifically, say for instance, DLF, there have been changes in design at Dahlias, which is one of our largest projects. That has also contributed to lesser work being done in this quarter on that project.

Our IDC costs have also impacted our margins there, right? These are some things which have sort of hit us as far as this quarter is concerned.

Having said that, geographically, these projects are in NCR. NCR seems to have borne the brunt as far as supply chain issues are concerned also, and labor price increase is concerned also.

Hopefully, going forward, I think now that these projects have started in real earnest, we are targeting a billing of, as I said, nearly ₹30 crore, ₹35 crore every month from Dahlias. We are targeting a billing of close to ₹60 crore from Central Vista.

We're targeting a billing of ₹25 crore, ₹30 crore from DLF Downtown, where design issues also seem to be a thing of the past. I think the increased turnover from these projects should sort of help us in sort of getting back to the margins that we were showing over the past couple of years.

Parvez Qazi

Sure. Secondly, in terms of payments, etc., how are things today vis-a-vis, let's say, what they were 6 months back, specifically with regards to central government, state government, etc.?

Shobhit Uppal

Central government projects, payments are not an issue. Central Vista just started.

We're doing Varanasi, Darbhanga, these are Airport Authority of India projects. There is a project that we're doing which is the Central University in Himachal, where we haven't been paid for the last 5 months because the project has gone over budget, our bills are lying certified, but the payments are not coming through.

Other than that one project, central government projects, we're not having any issue. State government, as Satbeer mentioned, Assam, due to elections, our bills were not getting signed off and payments were not coming.

As of 15 days ago, that process also seems to be getting streamlined, and we've started receiving major chunks of our outstanding dues.

Parvez Qazi

Sure. Lastly, when we look at the business over last 3, 4 years, in general, one would say volatility has increased in terms of, labor is a perpetual problem, but whether it is NGT, whether it's supply chain issues, or even approvals, etc., those have become difficult, and it is impacting everyone.

How are we kind of incorporating it in our risk management frameworks, especially when bidding for newer projects so that we can at least contain the impact of some of these issues in future projects?

Shobhit Uppal

The more obvious things that, our experience over the last year, year and a half, whatever the impact on our bottom line we've seen, the empirical data shows, we are actually now putting that as a part of our costing while bidding for future tenders. Say for instance, we know there is a huge shortage of carpenters, bar benders, as I mentioned earlier.

Our bid prices are now incorporating this. We have virtually doubled our shuttering prices or steel prices and other such similar items where labor is in extreme short supply.

Secondly, now, this has become the new normal. Our project staff cost used to be about 3.5%, 4%, 4.5%.

Now, with extreme increased focus on safety measures, especially with large developers and even government clients, our safety budget, we've increased from about 1 percentage point to nearly 3 percentage point. Our staff costs, we've now started taking in excess of 5%.

All this is being incorporated in our bids going forward. We feel that this is something that all large construction companies have begun doing, and this is how we feel going forward in our newer jobs, quoting and getting these higher rates will help us get back to our historical high margins.

Parvez Qazi

Sure, sir. Thanks, and all the best.

Shobhit Uppal

Thank you.

Operator

Thank you. The next question is from the line of Jainam Shah from Antique Securities.

Please go ahead. Mr.

Shah, your line has been unmuted. Please go ahead with your question.

Jainam Shah

Yeah. Hi.

Can you hear me now?

Operator

Yes,

Shobhit Uppal

please go ahead. Somewhat.

Jainam Shah

Yes. Sir, my question is on the AIIMS Jammu part.

Of course, ₹29 crore has not been recognized into the revenue. Do we have anything in terms of unbilled revenue or inventory or any other asset item related to this income that we were talking about?

Shobhit Uppal

In Jammu? For Jammu project?

Jainam Shah

Yeah.

Shobhit Uppal

No, that project is now closed.

Jainam Shah

Okay. We have booked everything in the expense, but this ₹29 crore has not been recognized into the revenue because of some Yes.

Shobhit Uppal

I think what you seem to be asking is, is there a potential for any further hit? No.

Jainam Shah

Got it, sir. Yeah.

Thank you so much, sir. Yeah.

Operator

Thank you. The next question is from the line of Parth Thakkar from JM Financial.

Please go ahead.

Parth Thakkar

Thank you for the opportunity. Sir, depreciation was higher in the first quarter, can we expect this to be recurring in the nature or it was just a one-time thing?

Shobhit Uppal

Yes. That would be recurring.

Because higher capital expenditure in the last 2, 3 years, that would be recurring.

Parth Thakkar

Okay. Can we expect the margins to be double-digit in FY '28?

Shobhit Uppal

In FY?

Parth Thakkar

'28, next financial year. Yes.

Shobhit Uppal

As I said, we aspire to get there, hopefully, whatever our empirical data has shown us over the last year, year and a half, we're trying to factor that in our costing and bidding. Your guess is as good as mine, but as Parvez said and Shravan also said, this is becoming a number of issues which keep cropping up, like the NGT or labor shortage for that matter,

Satbeer Singh

elections

Shobhit Uppal

round the year in some part of the country or the other. If there are a number of headwinds which sort of, 2, 3 years ago, these used to be occurring only 1 or 2 months in a year, now something or the other happens every other month.

It's very difficult to give a projection or prediction.

Parth Thakkar

Okay. Thank you, sir.

Those were my questions. Okay.

Operator

Thank you. The next question is from the line of Mahesh Patil from ICICI Securities.

Please go ahead.

Mahesh Patil

Yeah. Hi, sir.

Sir, mostly my questions have been answered. Just one query.

I think last call, we discussed that 89% of our order book has escalation clause for the materials, right? In terms of labor, also can we quantify it?

How much percentage of our order book value do we have this clause, and for the remaining, we have to kind of get it done, especially for NCR?

Shobhit Uppal

We don't have that data as of now, but you can reach out to Satbeer. We will get back to you on that.

Satbeer Singh

You may send mail to me, please.

Mahesh Patil

Sir. Yeah.

Thanks.

Shobhit Uppal

Thank you.

Operator

Thank you. The next question is from the line of Shubham Harne from Purnartha Investment Advisers.

Please go ahead.

Shubham Harne

Hi, sir. Thanks for the opportunity.

My first question is, how many months of increased labor cost impact is in numbers?

Shobhit Uppal

Sorry, I don't understand your question. Could you clarify?

Shubham Harne

Labor cost increase is in middle of the quarter, let's say, for 1 month or 1.5 month we got impacted by increased labor cost. It is a 1 month or 2-month time period, or for the whole quarter labor cost has been increased?

Shobhit Uppal

No, whole quarter. Going forward, the labor cost, once the labor price gets increased, it doesn't come back down.

Shubham Harne

No, that's clear to me. In the current quarter, for the whole 3 months increased labor cost is there?

Shobhit Uppal

It is.

Shubham Harne

Okay. This would be a new base?

Shobhit Uppal

Yes.

Shubham Harne

Okay. Second, on NGT impact.

In last concall, you had said that since Central Vista will start, NGT impact would be minimum for the current year.

Shobhit Uppal

On that particular project, that work will go on there. The impact will only be limited to, if at all, because we are trying to get special permissions, will be limited to raw material coming in from other parts of the country.

Shubham Harne

Okay. Earlier also, this same assumption was there, correct?

Shobhit Uppal

Central Vista the work per se on the ground does not stop.

Shubham Harne

Can you move labor from other projects in NCR to Central Vista? Which

Shobhit Uppal

we will definitely do that.

Shubham Harne

Got it. My last question is on EBITDA margin.

So, 2.6% impact is roughly due to AIIMS Jammu issue, 2.6%, while the rest is of raw material and increased labor cost, correct? There is nothing else.

Shobhit Uppal

Increased staffing cost also.

Shubham Harne

Okay. Increased staffing and labor cost will continue and material price will vary, basically?

Shobhit Uppal

Yes, and as material price will vary, and a lot of material costs or volatile material costs is a pass-through, like cement, steel, that's a pass-through. The major impact, which is what I've been stressing from the beginning of the call, is on account of labor.

Shubham Harne

Got it. Since this increased material cost, what is the time lag between increased cost and what usually our customers will give that increased labor cost to us?

Right.

Shobhit Uppal

I think I did say earlier that it would take over the next two quarters for us to sort of get the client to agree to compensate us.

Shubham Harne

No, material cost already client has agreed, correct? What is the time lag?

That is a pass-through. What is the time lag to that pass-through?

Shobhit Uppal

There are two formulae for this. On the private sector side, there is a base price for cement and steel.

Any increase from that base price is compensated to us with every bill. The lag is about 30 days, right?

As regards the government contracts, the escalation is based on Wholesale Price Index, which is released every quarter. Every quarter an escalation bill is proffered, and based on the index published, and that the government pays.

Shubham Harne

Got it. Thank you, sir.

Shobhit Uppal

Thank you.

Operator

Thank you. The next question is from the line of Vaibhav Shah from JM Financial.

Please go ahead.

Vaibhav Shah

Yeah. Just one thing.

You mentioned initially in the call that you are in talks with the clients regarding this higher labor cost. It is for the 90% of the book which is variable pricing in nature?

Shobhit Uppal

Primarily, we are in talks with our clients in NCR, where the impact has been sizable. We are sort of talking to them showing them what the actual costs are and telling them that it'll be very difficult for us to continue to work on old pricing.

Vaibhav Shah

Sir, but if they don't agree, it is not necessary that they may comply to this, right? Or it is in the clause

Shobhit Uppal

I agree with you. Contractually, strictly going by the contract, they may not.

Vaibhav Shah

Okay. Sir, we know that the labor rates are here to stay.

You mentioned that you don't expect it to come back down once they are increased now. In that case, for the NCR book, there could be a sizable impact on the margins from where we had bidded when we won the project?

Shobhit Uppal

Wherever the impact is sizable, we've already told the client. There are two parts to this compensation.

One is for the job already executed in this quarter, where the impact has already been felt by us. The other is going forward and the potential for the impact on the balance contract.

We're giving them various options that one is the impact till now. They are within their rights to say no.

Going forward, there are various options that we're discussing with them. All I can say at this stage is that the clients are looking at what we are saying favorably because they have realized that today one major thing which can make or mar a project is labor, and especially skilled labor is in extreme short supply.

Vaibhav Shah

Okay. Got it, sir.

Okay. Thank you.

Shobhit Uppal

Yeah.

Operator

Thank you. The next question is from the line of Madhur Rathi from Counter Cyclical Investments.

Please go ahead.

Madhur Rathi

Sir, I'm trying to understand that due to one reason or the other, if we look at our numbers, till FY '24 the growth was really strong. Sir, but after that, even though unexecuted order book has doubled over the last 2 years, but somehow the execution is just not moving due to either labor or this or that.

Sir, but, basically, labor is a part of our business. If there is a shortage and everything, NGT and so on, sir, these are all routine matters.

Now, the concern is I hope it is not the case that we will have to pay some penalty to our customers for not executing the projects on time. Till date,

Shobhit Uppal

Ahluwalia has not paid any penalty to any customer. If you were to go through, we would be more than happy to share historical data, especially over the last 2 years or 3 years where projects have been delayed, but it's been amply proven and accepted by the client that they've been delayed for no fault of ours.

It's not only Ahluwalia Contracts. If you were to do a deep dive into the historical project completion dates of all our peers, you will see that there are a number of factors leading to headwinds as far as project execution is concerned.

Labor is one thing, and this labor shortage has been building up over the last 4, 5, 6, 7 years. Projects have become more and more complex.

Projects have increased in scale. There are changes happening as we move along executing a project on a month-to-month basis from the client side, which clients are recognizing.

That is why extension of time is granted on projects, be it on private projects or government sector projects. If you've been covering this sector, you would know all this is a part and parcel of this industry.

When we bid for a project, we factor in some delays. As I said, there have been a few black swan events over the last 2 to 3 years which are part of the historical data.

The impact that has been felt on our bottom line has been more than we could have predicted. It's not only us.

If you do a peer-to-peer comparison, I think we've been showing better numbers than some of our peers.

Madhur Rathi

Now, sir, if we compare B.L. Kashyap, which is operate in our geography, is a fraction of our size, has balance sheet nowhere compared to us, drowning in debt, sir, they have grown in the first quarter, their EBITDA actually has also grown.

I'm not able to understand

Shobhit Uppal

Their base is very small, na. What I'm trying to tell you is you do a comparison which is spread over a larger tract of time.

You do a comparison with, say, if you want to do B.L. Kashyap, compare the results for the last 2 years at least, right, where base is very small.

When we were at that base, some of your peers would tell you our margins were 12%, 13%.

Madhur Rathi

Sir, in fact, that was my another question that I remember that few years back when I had asked that why our margins have declined from low teens to single digits, you had said that once the private sector orders become the majority of our order book, then our margins will expand to the previous levels of low teens. Sir, but now our private sector is 62% of our order book, but still our margins have actually declined to single digits.

Shobhit Uppal

As I said, there are a number of factors or newer factors which have cropped up in the last 2, 3, 4 years, labor shortage being one. As I said, increase the projects have become much more complex, increased staffing costs, and other IDC costs.

These are some things which have hit our margins, which are leading us to, going forward, when we're bidding for large projects, we are factoring this in.

Madhur Rathi

Sir, now, lastly, sir, if we look at our stock price since 2008 till now, the stock then the stock price was ₹350, today it is ₹795. The stock price has grown at less than 5% CAGR and there have been no dividends also.

Sir, after such a huge underperformance, also we have a cash-rich balance sheet, the stock price has halved since FY

Shobhit Uppal

We are a dividend-paying company. I think we've been paying dividends for the last 3 to 4 years.

Madhur Rathi

Sir, it is 0.07% dividend yield. It is practically irrelevant.

My point is different, sir. My point is that when our stock price has grown at sub-5% CAGR for the past 18 years and we have surplus cash on balance sheet, then why aren't we doing share buyback?

Shobhit Uppal

I think I had answered this question during the last call. This sector is facing extreme volatility, right?

Our focus is on growing our business. We don't want to use our war chest to buy back our shares.

At the moment, going forward, as it is, we are at an inflection point. We are growing rapidly.

We have a healthy order book. We want to digitize.

We want to become more efficient. We want to invest in machinery to counter or offset the labor paucity.

Share buyback is not really on the anvil for us. It's not a part of our plan.

I did explain this in detail last time round also.

Madhur Rathi

Understood, sir. Thank you very much.

Shobhit Uppal

Thank you.

Operator

Thank you. The next question is from the line of Parikshit Kandpal from HDFC Securities.

Please go ahead.

Parikshit Kandpal

Yeah. Hi, Shobhit.

Shobhit Uppal

Sir,

Parikshit Kandpal

my question is more on the industry and generic question. Just on the NCR market, this was 50% of our order book.

Just wanted to understand how much of our labor cost or how many labors are deployed in that market, and are all these labors currently at minimum wages because you said that there is a demand-supply issue also, I would understand that there would be certain person of the labor which will be above the minimum wages? If you can help us understand the quantification in terms of how many would be under just about the minimum wages, how many above that, and what was the total quantifiable impact in terms of crores on the profitability or the EBITDA in this quarter because of labor issue in NCR?

Shobhit Uppal

Okay. Just to put a number, this may not be extremely accurate, but it'll be there and thereabouts.

We would have close to about 10,000 to 12,000 people working for us, which I would categorize as labor, both unskilled and skilled. Now, 70% of this labor would be skilled, which would constitute bar benders, carpenters, masons, electricians, plumbers, and so on and so forth.

While the unskilled labor would be at the threshold of the minimum wage, the skilled labor would be in excess of that, excess of the skilled wage declared by the government. It is the skilled labor which is in extreme short supply, demand and supply conundrum that I mentioned.

The impact on our projects in NCR per se would vary on our total top line, I'm talking about the impact. Again, detailed figures Satbeer can get back to you on if you write to him, but it would vary from 2% on some projects to about 5% of the turnover where the material is free issue by the client.

Parikshit Kandpal

Okay. You're saying in this quarter, particularly in this quarter, what is the quantifiable impact on EBITDA because of the labor increase, the minimum wage increase?

Shobhit Uppal

At a company level, it is about a percentage and a half, 1.5%. Now

Parikshit Kandpal

this is permanent in nature. We start off if there is no escalation given on this account from the customer, we have a 150 basis point hit on the NCR order book because of the labor issues as of now.

Is that the right assumption?

Shobhit Uppal

There will be a hit if there is no escalation given, but it would be to the tune of about 1% because in some of these contracts, escalation is a pass-through, and some of the contracts the escalation kicks in after a certain amount of time has elapsed on a particular project, which varies from 6 months to a year.

Parikshit Kandpal

Max damage is about 100 basis point if the client doesn't give us any escalation, we have a hit of about 100 basis point. I think we took a lot of time debating this.

I think if this was quantified, it could have been helpful earlier. Sir, and how do you intend to cover up this like productivity, cost savings, other measures?

How much do you think if the client doesn't give us any escalation, when you grow it, how much do you think you can cover a part of this damage?

Shobhit Uppal

Again, what is happening, as I said earlier, client is recognizing this. What client is doing, while we feel on some of the projects, some of our larger clients will look at this favorably, but even if they don't, what they've already started doing, the Godrejs of this world, the DLFs of this world, the Signature Globals of this world, they've started announcing incentives which are linked to progress or stage-wise timely completion.

You cast a certain number of slabs in a month, they give incentives, right? Which, to some extent, may offset some of these higher costs.

Parikshit Kandpal

You can gain a part of it through the productivity gains or at the site levels which could be ahead of schedule?

Shobhit Uppal

Exactly.

Parikshit Kandpal

Part of that could be

Shobhit Uppal

that. That's why that's why a lot of you, as I mentioned earlier, should, we'd be more than open to share You should do a deep dive.

This labor problem is a huge problem, right? While some of us So, I'm sure you would have you cover this sector and you've been doing it for a number of years, we would be more than happy to take you through project sites and show you how we are being impacted.

Some of our peers may have recognized that impact this quarter, they will also feel it going forward. Different geographies are facing it at different times.

Parikshit Kandpal

The bigger question right now is what was the motivation of the Haryana government to do this, and if other states start doing it, then it becomes a broader level issue on the entire order book, which can exacerbate our overall margin impact. If you can help us understand why did it happen first, and then also earlier in the call you said 70% of the labor is skilled, I assumed that the hit would not have been there, it would be at the labor which is at the border line level, right?

If you can help us understand what was the motivation behind this, and why was the hit so high if it was only to the part of the labor force because the skilled The Haryana government

Shobhit Uppal

Sorry, go ahead. Sorry.

Parikshit Kandpal

I'm saying it was out of the 100 labor, you said 70 is skilled, where anyways it's a market-determined pricing, I assume it'll be push and pull, which will determine their wages, not the government-mandated minimum wages. It'll be more like where the part was exposed to the minimum level of wages where you had to align with the government policy or given escalation.

What was the motivation of the Haryana government, and secondly, whether other states can also now implement this, at least for the borderline cases?

Shobhit Uppal

Your first question, what was the motivation of the government? The Haryana government over the past 1 month has cracked down on RMC manufacturing plants, and today 90% of the plants are shut down in Haryana, right?

What is the motivation behind it? Who can say,

Parikshit Kandpal

right?

Shobhit Uppal

With governments, it's very difficult to say. Similarly, they have at such a time increased the labor pricing.

While the developer lobbies are talking to the government, they may agree to sort of reopen some of these plants, but I don't think there's going to be a rollback on the labor pricing. It's never happens.

It's a very sensitive politically issue. It's very difficult for us to comment.

Second thing is, push and pull on the skilled labor is right, but it's, as I said, it's demand and supply. There is a huge shortage of skilled manpower, and whatever skilled manpower is there, the skill levels are down.

The buildings are becoming more and more complex, right? That leads to low productivity on the project.

That's why our costs are rising. That's why I'm saying that we would be more than happy to take you to our project sites and show you how it's very difficult to sort of explain all this on an investor call, but at ground zero we can show to you how the impact is happening.

Parikshit Kandpal

Just last question. Is it only for the labor domiciled in Haryana state, or if you can, say, pull out labor from UP or Bihar or some other states, you still have to pay them the minimum wages or so how does it work like?

Shobhit Uppal

This is all migrant labor. This labor is coming in from Bihar or Bengal or Orissa or Madhya Pradesh.

It's not Haryana labor.

Parikshit Kandpal

Not a domicile issue, understood. Still don't understand the motivation, but anyways, I'll take it offline.

Thank you.

Shobhit Uppal

Yeah. Thank you.

Operator

Thank you. Ladies and gentlemen, due to time constraints, we will take that as the last question for the day, and I would now like to hand the conference over to the management for closing comments.

Shobhit Uppal

Thank you so much, everybody. As I said, any further queries, please reach out to us, and we'd be more than happy to explain the ground realities to some of you, even if you want to sort of visit our project sites to get more clarity.

Thank you so much. See you on the next call.