Operator
Good day and thank you for standing by. Welcome to the NUAI business update conference call.
At this time, all participants are in a listen-only mode. I would now like to hand the conference over to your speaker today, Lincoln Tan, Investor Relations for New Era.
Please go ahead.
Lincoln Tan
Thank you, operator, and good afternoon. My name is Lincoln Tan, Investor Relations for New Era.
Thank you for joining our fourth quarter fiscal 2025 business update call. Joining me today are Will Gray, Chairman and Chief Executive Officer; Charlie Nelson, President and Chief Operating Officer; and Ted Warner, Chief Financial Officer.
Before we begin, I'd like to remind everyone that today's call is being recorded and will be available on the Investor Relations section of our website. Following management's prepared remarks, we will address questions submitted by participants through the webcast platform, time permitting.
I'd also like to note that today's prepared remarks will be somewhat longer than usual. With our expanded executive team now in place, including Charlie and Ted participating in their first business update call with the company, management will take additional time to provide a more comprehensive overview of the business, recent developments across the platform, and how they are thinking about strategy and execution going forward, following what has been a period of significant transition and activity across the entire organization.
Please note that during the course of this call, we may make forward-looking statements. These statements reflect our current views and expectations and are subject to risks and uncertainties that could cause actual results to differ materially from those expressed or implied.
We encourage listeners not to place undue reliance on these statements and to review the disclaimer on slide two of the accompanying presentation for additional information. With that, I'll turn the call over to Will Gray.
Will Gray
Good afternoon, everyone, and thanks for joining us today. Before I begin, I just want to be direct about what this call is about and what it isn't.
This is not just an earnings recap. The 10-K's filed, the numbers are public, and we can all read them.
What this call is about is something more fundamental. We're going to walk through what New Era Energy & Digital actually is, how we're building it, and why we believe we're positioned to be a defining platform in AI infrastructure development.
A lot of investors still associate us with our former life as New Era Helium. Trust me, that chapter's closed.
We're not going to talk about it again. What we're building now is fundamentally different, and we owe it to our shareholders to explain it clearly.
Looking at slide two, let's just talk about the disclaimers. I just want to remind everyone that today's presentation does include forward-looking statements and is subject to the disclaimer shown here and detailed as well in our SEC filings.
I would encourage everyone to review those carefully, please. Going on to slide three, I really want to make some introductions on the two individuals who are essentially critical to the next phase of this company, and they have been critical since day one Charlie has.
Many of you are familiar with Charlie Nelson, and Charlie been with me really since day one, since we went public, as an independent board member. Charlie is now our Charlie Nelson's now our President and Chief Operating Officer and officially joined us in the executive capacity in January after stepping in from an independent position last July to really help me with the transition into the digital infrastructure.
As Charlie has mentioned, he spent his career building and scaling large energy and industrial infrastructure platforms, pipelines, gas processing, power, terminals, fuels, GTLs. He's overseen more than $1 billion in infrastructure projects.
Charlie is the person who knows how to take a complex, multi-party infrastructure development and actually deliver it. He's going to be walking us through the technical heart of what we're building today.
Essentially what Charlie and I have been able to accomplish this far is the real reason why the next introduction is so pivotal, because it's about execution. Very pleased to introduce our new CFO, Ted Warner, who, again, recently joined us as Chief Financial Officer, effective today.
Yesterday it's amazing, because Ted brings 20 years of infrastructure and energy capital markets experience. Formerly, he was the head of Energy & Power and Digital Infrastructure at Northland, where as an investment banker at Northland, he led more than $7 billion in data center infrastructure financing, literally in the last two years alone, quite impressive.
All structured capital solutions specifically for AI and HPC infrastructure. When we talk about our financing strategy, that is the GP/LP structures, project-level capital formation, Ted is the individual who's done this at scale for his entire career across energy and now large-scale greenfield HPC data centers.
Ted will definitely be speaking as to our financing strategy later in this presentation, but definitely want to welcome Ted to the team, as he's going to be quite instrumental in getting us to where we all need to go here on our execution model. Really kind of want to just dive right into kind of the industry landscape and growth drivers and really want to explain what we're actually building here at NUAI, because I think this is the part that most investors really haven't kind of grasped yet.
It's the most important thing I'm going to have to say today. I want you to think about what happened during the shale revolution in oil and gas, and that was the upstream companies, they produced the hydrocarbons.
Refineries consumed them. In between, there was a massive infrastructure buildout which essentially was attributed to the pipeline companies, the processing companies, Kinder Morgan, The Williams Companies, MarkWest, etc.
Those midstream companies didn't produce a single barrel of oil, and they didn't consume the gas. What they did was build the infrastructure that connected the supply to the demand.
That infrastructure sector became a $500 billion industry. Here's a critical point: it was spun out from vertically integrated supermajors due to very specific financing engines, project-level financing, GP/LP structure, asset-level debt secured against long-term contracted cash flow.
The midstream company acted as the general partner, the developer, the originator, the operator. Institutional capital, PE funds, pension funds, infrastructure funds, sovereign wealth, they provide the project capital as limited partners.
The developers earn the fees, equity participation, and then co-invest alongside the LPs. The institutional investors get contracted infrastructure returns.
That model has financed hundreds of billions of dollars of infrastructure over the last three decades. Essentially, what NUAI is doing is we're applying that exact playbook, but to AI.
Again, we don't manufacture chips. We don't run AI models.
We don't operate GPU clouds. We build the powered infrastructure, which is the land, the power, the buildings, that sits between the energy supply and the compute demand.
Essentially, we are the midstream of the AI economy. We finance it the same way.
NUAI is the general partner and developer as well as the opportunistic investor. Project-level capital, debt and equity from institutional infrastructure investors, that funds the build.
The tenant's balance sheet, not NUAI's, is what the lenders ultimately underwrite. This is not speculative.
This is how large-scale infrastructure has been financed for decades, and this is what we're essentially going to copy, paste, and do it again. Now let's look at the demand side of the story, because this is something most of you are already familiar with, I don't want to spend too much time here, but there are several points worth underscoring.
First, hyperscaler demand for data center capacity continues to accelerate. The numbers on this slide simply tell the story: projected capex exceeding $350 billion in 2025, and that global capacity expected to quadruple by 2030.
That's a substantial amount. Here's the second point, and it's the one that actually matters for our business, for NUAI: the constraint isn't demand.
Everyone knows that's there. The real constraint is power.
In every major data center market in the country today, timely access to large-scale, reliable power has become the gating factor for new deployments. Grid interconnection queues are stretching to 3, 4, 5 years plus.
Utilities are issuing notice-to-serve letters telling applicants, "You ask for a gigawatt? Here's 400 megs.
We'll let you know when we can provide more." That dynamic is exactly where NUAI NUAI plays.
We develop campuses where power infrastructure is designed and delivered alongside the data center itself, behind-the-meter plus grid, not just grid. I think that's important to note.
On-site, purpose-built for hyperscale AI workloads. The constraint is power, and that's where NUAI comes in.
Charlie, why don't you kind of looking at the next slide, Charlie, here on slide five, why don't you if you don't mind, kind of take over and kind of give your thoughts here?
Charlie Nelson
Definitely. Thanks, Will.
Let me briefly walk you through the company that we've built and kind of the execution machine that we have built to do all this. Our development model rests on four pillars.
First is differentiated site sourcing. Historically speaking, data centers have been pretty straightforward.
You basically looked at the intersection of power, that's medium- to high-voltage power lines; fiber was a must, right on site basically; ample water supply because most people use evaporative cooling historically. That worked great for 30 to 50 megawatt data centers, which was very large 3 years ago.
Moving into these larger-scale ones, even some gigawatt-plus, it just broke the mold. The new paradigm is dramatically different.
Fiber proximity is less important. It's less important because you can build long-haul, last-mile fiber that basically costs the same for a 30 megawatt data center as it does for a gigawatt data center, and so the cost is spread out over a larger amount of megawatts.
Water is kind of an afterthought. It's not completely gone, but everything's closed-loop, we use direct-to-chip cooling, and so it's less important than it used to be, but it's still a must.
The big thing is power, and power's the wild card. Grids everywhere are constrained.
To get data centers built on time, all these utilities are so overwhelmed right now that our position is that you effectively have to build your own. All this leads to our development model.
We chose TCDC, which was riddled with pipeline easements, active pipelines, all sorts of things, and those to a normal developer would look undevelopable. Our group, given the fact that we have done all these things, we've built pipelines, we've moved them, etc., it's allowed us to basically play moneyball with sites that otherwise are very well-positioned but hard to develop, and take undevelopable Cs and turn them into As.
Second, we have a coordinated execution ecosystem. We don't build everything ourselves.
These are massive projects, especially when you're building your own power. We work with best-in-class partners across power generation, engineering, modular manufacturing, and construction, etc.
We've migrated towards factory-built components which reduce on-site labor requirements, which is huge in this market where at these large scales, if there's 10 of these things being built across the country where each of them require 5,000 to 10,000 contractors on site at the same time, we just don't have the contracting capacity in this country to do that effectively at the same time. Our basically move into this modular manufacturing has allowed us to and will allow us to compress timelines and more effectively execute on the projects that we're doing.
Third, as Will mentioned, we've deployed a capital-efficient GP/LP structure. This lowers balance sheet requirements, lowers dilution versus traditional development because institutional capital will fund the build at the project level, and Ted will touch on this a little bit more later.
Fourth, everything that we're talking about here is a repeatable development platform, standardized frameworks that get faster and better with every single project we do. TCDC is Project 1, but the platform that comes with the partnerships, the playbook, the financing model, the permits, the execution, all of that is designed to support a lot of campuses over time so we can copy and paste.
Will, I'll let you take the next one.
Will Gray
Cuz now, Charlie, there's one thing that we've touched on a number of times is why we're here, right? Solving the core constraints.
That's really behind-the-meter plus grid versus grid-only. I really want to spend some time talking about that, the single most important thing for this audience, right?
That's to understand about our business, why behind-the-meter power it's not just a niche strategy. It's becoming the default for hyperscale AI infrastructure.
I'd love to explain why, because we've been here and demonstrated this a number of times why this is so important. When we talk to hyperscale customers, we spend a lot of time in their conference rooms, just articulating a very clear priority stack, and that's speed to power is first, reliability, unfortunately, is second, Cost is third.
If we got the other two, that's not our framing, but that's what customers tell us directly. Obviously, again, speed, reliability, cost.
Let's take those really one at a time, cuz I want to kind of dive through those and dissect them so that the audience has a really good understanding of where we're coming from. Obviously, the most important is speed.
I think we all understand about the grid interconnections. Today they're measured in 3 to 5-year increments, and that's really kind of on a good day, assuming you have the capacity you asked for, whether it's ISOs, ERCOT, PJM, every major grid network in the country is so stressed, and unfortunately it's getting worse.
When you hear companies cite multi-gigawatt campus plans, we kind of ask ourselves, Where's this coming from? If the answer is the grid, then they're waiting in line with everyone else.
Behind-the-meter power can be deployed in 12 to 24 months. It's not a marginal advantage; it's complete different competitive position.
That's where NUAI has really kind of just planted our flag. That's what we're doing with our first asset here in the Permian.
Again, not just speed, but reliability. Interesting fact here, you just can't build a power plant and plug it into a data center and expect it to execute perfectly.
Doesn't work that way. The two don't match up.
When the market demands five nines reliability, and that takes the nuance to get it done, we've developed the method to do so. Of course, cost.
3 to 4 years ago, you could buy grid power in Texas at $45 per megawatt-hour. Today, open bids are $85 to $95.
Grid power is getting more expensive, because utilities are funding massive grid upgrades, and unfortunately those T&D charges are getting passed through to the ratepayers, transmission and distribution charges. That's a real number that consumers are seeing each day.
A lot of jurisdictions are looking at adding a data center surcharge to the larger load clients. It's only going to get worse from here on out.
We're approaching a cost curve where behind-the-meter is cheaper than grid. Again, behind-the-meter costs are relatively static.
What your gas costs, you know what your capital recovery charge is, you know what your operating costs are, the convergence between behind-the-meter and grid pricing is real. We believe parity is not far off in many markets.
Then there's the dimension most people just aren't talking about, and that's really the social license to operate, whether that be Texas Senate Bill 6, new regulations in Ohio, PJM reforms, all these responses are the fact that you just cannot be a parasitic load in the grid. You have to have community support.
You have to have regulatory support. That means reducing what you consume from the grid and bring your own power.
Meta just announced behind-the-meter. Vantage announced a major behind-the-meter deal with Liberty Energy.
Our thesis is not alone in isolation. The entire industry is moving in this direction.
New Era Energy & Digital saw this early and we designed around it. Charlie, based upon that, let's talk about how we designed around that, because you were instrumental in taking that baton and really kind of carrying it forward, I'd love to kind of get your thoughts on that.
Charlie Nelson
For sure. Just talking about the development life cycle of a campus, and our campuses are supported by these platform-level execution partnerships that we've talked about before.
We've got some established and this is a growing ecosystem that we have, but we've got partners like Ramboll, RK Mission Critical, Thunderhead, Zero Intensity, etc. Beyond the more mechanical parts of what we do in the development process, which is really around originating, structuring, coordinating, and executing, what we really want to highlight today is what we can do that most can't, just because it's not straightforward and it's not easy.
I think it's best illustrated in an example of what we've done at TCDC. What we do is we take sites that are embedded in active energy corridors.
These are not necessarily the prettiest ones. These could be greenfield, these could be brownfield.
They may have active stuff on them. They may have some blemishes that we have to rectify, things like abandoned infrastructure, environmental complexity, etc.
We convert them into powered hyperscale-grade campuses. Look at what we did with TCDC, for example.
TCDC had wells on the property. They had abandoned pipelines on the property.
All of these things, these surface conditions are typically something that, in the low-hanging fruit matrix, it is not the easiest thing to do. These locations are key for a lot of reasons.
They've got redundant pipelines, for example, that we can build power plants that have high reliability on them. They've got multiple power lines.
They've got a lot of the ingredients that we'd like. This is something, again, traditional data center development wouldn't take a look at this and say, "Oh, this is a fantastic site," but we didn't walk away.
We knew how to convert it. What do we do?
We relocated the pipelines. We've had to negotiate with midstream operators to do that.
We've had to coordinate shutdowns. We've had to go through additional permits, etc.
We've had to remediate stuff. How do we do that?
Far, we've completed soil sampling, we've done environmental assessments, we've done clearing, we've done grading. We've removed this infrastructure, and we've basically brought it back to kind of baseline.
Again, this isn't traditionally what data center companies do. This is very common for what energy infrastructure companies do.
That is at the core of what we've done historically. All this requires a very specific kind of operator who kind of straddles the fence between the energy world and the digital infrastructure world, which is a pretty rare combination.
This is a fundamental insight that we want you to take away. In a world where AI compute is growing exponentially, the supply of viable powered land sites is growing linearly, and frankly, there's more noise than signal in this sector trying to find where's the best place to build and where's the next best place to build.
What we can do is we can take sites that are very well-positioned, but may not be perfectly buildable day one, and this is going back to what I said before: turn Cs and Bs into A-pluses. That's what we do.
We're not competing for these exist sites cuz frankly, they're becoming fewer and far between. We're just making new ones.
By doing so, it enables us to build in extremely advantageous areas that most would overlook because it's not the easiest path forward.
Will Gray
Yeah.
Charlie Nelson
Will, I'm going to hand it back to you.
Will Gray
It's well-said, Charlie, when you look at, starting here on slide eight, which is our multi-campus and our multi-gigawatt platform, this slide really kind of outlines our broader development pipeline, obviously with Texas Critical Data Centers. We've said this multiple times, this is our flagship campus in Ector County, heart of the Permian Basin, it's a 1-plus gig under active development.
We've also kind of touched on our New Mexico campus in Lea County. Again, over in New Mexico, it's a longer-term multi-gigawatt opportunity that's really in early planning, with engineering work underway.
I want to be disciplined about expectations here. Right now our core focus is on advancing our TCDC asset towards full commercialization.
Please note, everything we do, every partnership, every engineering decision, every capital conversation, it's truly oriented around being designed to be repeatable. This is a platform that Charlie and I built to rinse and repeat.
Again, TCDC is just asset number one. We have a number of other assets that are ready to be spun up, but we want execution done on TCDC first and foremost.
Once that's COD, then we're off to the races. Again, please note that all of our sites are very real.
New Mexico is real. The site characteristics are extremely suitable for the AI data center deployment, which are, of course, all the necessary items, of course, proximity to water, fiber, labor, major gas transmission lines, all the things that are needed for behind-the-meter, speed to power, and of course, reliability.
Of course, with our New Mexico asset, we have commenced some engineering work on that, but it's for future deployment for the platform. It's not our near-term priority.
Our near-term priority is execution on TCDC and deliverability there of our gigawatt-plus site. Charlie, let's talk about that.
Speaking of our flagship campus, I'm going to hand it over to you here on slide nine.
Charlie Nelson
For sure. Just talking through TCDC, it's an absolute gem, right?
TCDC sits on what was 438 acres, now we're up to 492. This site, it sits right next to two major power plants.
One's Vistra's Ector County generating station, which is roughly 1.1 gigs, and right next to Calpine's Quail Haven facility, which is roughly 550 megs. Why does that matter?
Again, there's existing POIs nearby, points of interconnection. There's a reason why they built those plants there.
There's three natural gas transmission systems operated by three separate companies. One's operated by ONEOK, one's operated by Enterprise, and one's operated by a group called WhiteWater.
Why does that matter? Gas pipelines, they go down.
In the data center world, traditionally, five nines of reliability is the gold standard. To get to five nines of reliability, you can't just operate off of one pipeline because pipelines go down.
They go down for maintenance, things like that. If a pipeline goes down for maintenance, guess what?
Your data center goes dark if it's running off of those pipes. We've got three physically diverse sources from three separate operators.
We can maintain continuous supply. That's kind of a Goldilocks situation for a behind-the-meter application, because it's not just about the equipment, it's about the supply of the materials that run that equipment.
Obviously, having redundancy on gas supply is critical. We talk about fiber.
This is just going back to more of the ingredients in the data center soup. Fiber connectivity is great here.
There's fiber that runs along the I-20 corridor. For those who don't know, fiber runs along most major interstate corridors.
This connects to major hubs between Dallas, El Paso, etc. Being able to tap right into that just makes our lives a lot easier.
That's just one more notch in the belt for the site. Water, building codes, workforce, regulatory, etc., these are all very favorable for this.
The site is not in the middle of nowhere. It's in a area that has historically built hard things in the oil and gas space.
There is a level of familiarity nearby both in terms of the regulatory bodies as well as the workforce that allows us to basically build this with greater ease. Additionally, we've initiated an industrial district designation with City of Odessa, which gives us access to municipal water, wastewater should we need it.
A lot of what we've been doing on this site is, as mentioned before, it's not just all of the relocating of pipelines, etc., it's just a lot of the basic stuff that goes along with development: that's land acquisition, consolidation, commercial negotiation, site clearing, soil samples, civil engineering. Building something of this scale takes a lot of things.
We've just been knocking all those items out. Again, we'll continue to communicate that going forward.
Kind of moving on to the next thing, and we're super excited to kind of talk about this. Again, the complexity here is actually the moat.
Our power development plan at TCDC is phased into three stages. Initial phase is going to be roughly 200 megawatts.
Phase 1 is a build-to-suit development leveraging existing generation and grid interconnection. Then Phase 2 is an additional 450 megs that we've announced behind-the-meter, and then Phase 3 will be the balance of that power.
That's going to be a combination of bidirectional interconnect as well as additional behind-the-meter generation. All of that is going to be phased in, and we can talk about that at a later date exactly what that looks like.
Will touched on this. Let's touch on the power systems.
How do these things actually work? Because this is kind of a black box for most people.
Just to kind of give a little bit deeper dive into this, we're using what are called simple cycle gas turbines. Most people hear gas-fired power plants or whatever, and you think of a large combined cycle power plant.
Combined cycle plants are great, they're super efficient, but they do have a critical flaw if you're just plugging a combined cycle plant into a data center. It doesn't work like that.
You can't throttle them quickly. A combined cycle plant's kind of like an ocean liner.
It's slow to turn, you can't throttle it up and down as easily. Simple cycles operate more like jet engines.
You can ramp them up, you can ramp them down. It happens fast.
You can black start them fast. There's a lot of benefits to using these and coupling these into this application, versus a traditional power developer would look out and say, "Hey, let's build what's called heat-rate-efficient plant."
This is not what we're trying to do. What we were doing is matching the equipment to the application.
On that, there's this misconception that data centers are these stable loads. It's like, "Hey, we're going to build a gigawatt data center."
That does not mean that a data center is going to be consuming a gigawatt all day every day. That's not how that works.
Depending on the application, these data centers, they can be jagged, they can be seasonal, there is variability in them, and inference is different than cloud, that is different than AI training. While there is some stability in those things, compared to residential loads, they are far from just like, "Hey, we're going to plug this in and it's going to be consuming the same amount of power every day."
That's just not how these things work. Really, what we've done is designed a system for behind-the-meter that works with the application.
We've designed a system that sits in between the behind-the-meter, the substation, and the eventual grid interconnection, that all operate kind of automatically. We're talking chip-level communication that basically can communicate with the energy system.
Basically, when the data center load drops, excess power can either be routed to storage, can be, eventually, when we have a bidirectional interconnect, can go back on the grid, or it can communicate to effectively turn down these units, the power units, when the power demand goes down. These bidirectional interconnects are a different animal.
We believe that they are the best way to interact with the grid. If the name isn't immediately descriptive, a bidirectional interconnect is an interconnect with the grid on which you can take power off the grid or put power back onto the grid.
We believe that this is kind of the wave of the future. It's one of these situations that turns us into a non-parasitic load, it's not just, "Hey, we're asking the grid to provide us power."
This also allows us to export excess power back to ERCOT and back to other grids in the event that there's a major weather event like Uri that happened back in 2021. In the context of all these new regulations that are coming into place that are really aimed at trying to have the data centers be a more community-focused ecosystem, a bidirectional interconnect is an easy way to do that.
Again, behind-the-meter is not just like, "Hey, let's build a big power plant and plug it into the building." That's just not how this works.
You'll end up breaking equipment, it doesn't function properly in the application. The way that we've gone about doing this is what we believe to be the right way forward in terms of designing your equipment scheme to actually work in the context of the application that it's existing in.
Kind of moving on to the next slide, and this is going to be a new one for just about everyone here. As we've gone through this, what we've identified is a very critical weakness industry-wide: and I mentioned this earlier, these large data centers take an enormous amount of labor.
While data centers are not incredibly complex, it's just a big box filled with computers that cools those computers effectively. The problem is that those large computers take enormous amounts of electrical labor to actually execute on them.
What we keep seeing thematically over and over and over again and learning from our peers is you can only build so many of these at the same time before you stress the labor pool until it breaks, or until basically you're just bidding for labor that doesn't exist. What's the answer to that?
Our belief is the answer to this is standardization and modularization. We are excited to announce what we are calling the ATOM platform.
ATOM is our standardized data center platform. This is going to be the first of a couple manifestations of this.
The ATOM platform is a 25 megawatt base unit. If you feel like flipping back to the slide before, you can zoom in on those buildings and kind of see how they're divided up.
Each of those units is 25 megawatts. Those 25 megawatt units can be stacked side-by-side.
Basically, you can adjust the number of units in parallel to effectively come up with whatever capacity you need for that particular building. It's pretty straightforward, to be perfectly frank, and what it allows us to do is reduce our on-site labor by about 80%, as it's being projected today.
It also means that most of this is constructed in a controlled manufacturing environment and then shipped to site for final integration. Historically speaking, data centers have been what's called stick-built.
Stick-built, in the context of major construction, means that you basically ship all the materials to site and you build it on site. Modular means that you build it in a factory and ship it and then just plug it in.
What does this do? Again, it enables us to do things faster, cheaper, more effectively, and control our costs.
As mentioned before, we partnered with a group called RK Mission Critical, who is a US-based manufacturer with their vast majority of their manufacturing base existing in Denver, Colorado. They've been in business for 65 years.
They've got about 1 million square feet of production space, over 2,000 employees, and they also are vertically integrated all the way through their own steel manufacturing. We selected them for their expertise.
They've been delivering modular components in the past for smaller-scale data centers, and we believe that they've got the expertise to really make a difference for our company and allow us to execute efficiently and on time and on budget. Again, going back to why are we doing this?
It really just comes down to copy and paste. Will's example of the midstream industry that he gave before, I cut my teeth in the midstream space during the boom between 2010 to 2020 2014, and the only reason why the midstream industry was able to execute so efficiently on its buildout was because they standardized on a plant design for gas processing, it was a 200 million standard cubic feet per day of design.
You want a basically 1 billion cubic feet of gas processing, you installed 5 200 million a day cryos. You didn't install 1 1 billion cubic feet a day cryo.
These things really enabled an industry to grow at a very rapid pace and execute on time and on budget. That's just absolutely critical.
Again, going back to our energy roots, we're kind of adopting a similar principle of copy and paste manufacturing, cuz it's something that we believe, going forward, that for this scale, smaller scale, and larger scale, is going to be the way to go. Now, I know that we've hit on this quite a bit, but I can't really express how important the partnership ecosystem is to us in terms of execution, because, historically speaking, that's how we've found success in the past.
If you try to take on too much and boil the ocean, odds are that something's going to fall apart at some point. This partnership ecosystem that we've developed is a very deliberate strategic choice.
It's not a sign that we lack capability; it's a sign that we understand how large projects are delivered on a repeatable basis. Again, and having these credible counterparties with their own balance sheets know to execute is the way that we see that we can move into hypergrowth effectively.
The partnership ecosystem that we've developed right now is very strong. We're going to continue to make it stronger over time.
Just to kind of go through a few critical pieces of this. For one, we've designed all of basically the TCDC site and the internal equipment with a legacy engineering company called EYP, which is now a division of Ramboll.
They are our engineering partner. Why did we choose them?
Frankly, the hyperscalers pointed us in their direction. They've designed more than 75 million square feet of data centers worldwide.
They've been in operation for 25-plus years. They know how to design facilities that work, plain and simple.
We've taken that exact same design expertise and worked with them to design the ATOM platform that I just laid out before. Let's talk about RK Mission Critical.
RK Mission Critical is actually a division of a much larger company called RK Industries. RK Industries is that vertically integrated manufacturing company that we talked about before that we've partnered with.
They've got everything from RK Water to RK Steel, they've got an oil and gas division. They've got this dedicated production capacity that allows us specifically to know what we can manufacture over a period of time.
Their vertically integrated manufacturing capabilities reduce delivery risk, especially as it relates to certain critical supply chains. They've just got a great track record of execution on complex data center projects.
When we look at any project, all we're looking for is what passes muster for institutional investors and what do hyperscalers want to see. How can we reduce risk?
We view RK as a very critical component to that whole ecosystem. We've also talked about this before, but Thunderhead.
Thunderhead is our power generation partner for TCDC. Thunderhead is backed by a group called Harbert Infrastructure.
Harbert has been doing a lot in the power space for a very long time. They finance, construct, and operate behind-the-meter power islands.
They bring their own balance sheet. We don't have to carry capex exposure for the power equipment.
They've already secured the initial turbine equipment that's on order that we know can be delivered through their partnership and now our partnership with TurbineX. This is, again, the start to a growing partnership ecosystem that will continue to advance.
Happy to share more updates as we continue to add more to that ecosystem. With that, been talking a lot, let me hand it over to Ted to walk through how these projects are actually financed, because obviously it's important and the capital structure is one of the most misunderstood aspects to our story.
Ted, I'm going to hand it over to you.
Ted Warner
Thanks, Charlie, and thanks to Will as well. Couldn't be more excited to be a part of this team and the New Era story.
As a banker, I've seen hundreds of development opportunities in this HPC AI landscape over the last few years, and when I was able to dig in on this opportunity and the team, prospective partners and core assets, I knew that I had found the opportunity I was seeking, and also that my experience and expertise were, I think, exactly what this opportunity needed at its current stage, just felt right and, again, really happy to be here. I've been focused on large-scale, AI-focused digital infrastructure for a few years now.
I joined this team ultimately because the opportunity to apply proven infrastructure financing principles to AI data center development is one of the most compelling things happening in the capital markets today. During my last few years as a banker, my group was at the forefront of bespoke, accretive, scalable financing solutions for early-stage HPC AI data center developers like New Era.
We want to quickly walk investors through why we feel the structure we're building here is smart, practical, and the best possible strategy for our shareholders at this stage of our company. The diagram on this slide shows our corporate structure.
At the top, you have NUAI, the holding company, the publicly traded entity, the centralized developer, owner, and asset manager. Below that, each project is structured as an individual special purpose vehicle, an SPV, and TCDC is SPV 1.
Future campuses we would add additional SPVs. Why does this matter?
For a few reasons. First, it isolates project-level risk while preserving our optionality at the parent level in the future.
The project encounters a problem, it's ring-fenced within that SPV. It allows us to prevent issues from cascading to the corporate entity or to other projects if we want to.
Then second, it enables flexible, project-specific capital formation with institutional partners. Different projects may have different capital partners, different needs, different structures, and ultimately, a different type of tenant.
The SPV model accommodates New Era and allows us to capitalize on the best possible partners and financing structures for each unique project that we're developing. Third, it just enhances our overall financeability as our platform scales.
Institutional infrastructure investors, the kind I've been working with for the last few years now and before that in the energy world, they know this structure very, very well. It's been used by a number of our well-known peers in the HPC space with top-tier investors when they were at a similar stage over the last few years and even at later stages, and we definitely think this structure is a great fit for us at this stage with our asset base.
This next slide simplifies the financing model to its essentials. NUAI sits at the top as general partner, the sponsor and developer.
Institutional investors sit at the bottom as limited partners, providing as much of the project capital as we need. Now, given our availability of capital and all the relationships we have with top funds and investors, our goal is to invest as much as is allowed under any future partnership agreements and increase our ownership in each new project and partnership as we scale.
The flow here is straightforward: LPs provide capital into the project SPV, project builds and operates the infrastructure, and LPs receive their investment returns, contracted cash flows backed by long-term triple net leases from creditworthy tenants, with the goal of finding the best possible IG tenants, specifically at TCDC. NUAI receives development fees upon project delivery, recurring management fees for ongoing asset management, and the right to material equity project participation in the project.
What this means for our shareholders is critical. The vast majority of the capital-intensive construction is not funded from our corporate balance sheet.
It's funded at the project level against the creditworthiness of the tenant. The tenant's balance sheet is what the project lenders ultimately underwrite, and if we're talking investment-grade tenants, we're getting probably 80% loan to cost, and we are, again, at TCDC especially, striving for the best possible tenant we can find from a credit rating perspective.
Then our portion of the equity dollars needed after that project finance at the project level can be funded through numerous shareholder-friendly structures that help to minimize dilution and maximize our shareholder returns, many of which I have specialized in over the last few years as a banker. I'm excited to bring some of those options to New Era.
Again, structures designed to limit dilution, maximize returns at the parent company while still allowing a New Era to develop and manage large-scale infrastructures even at this early stage of the company. It's the same model that built the midstream energy sector, and all three of us know that well, and it's well understood by all the institutional infrastructure investors.
Now, I'll turn it back over to Will.
Will Gray
Ted, I appreciate that. Again, welcome aboard.
Greatly looking forward to having you facilitate kind of what Charlie and I have been able to place together. What you've accomplished the last couple years on the banking side has been monumental, and it's been honestly something that we've looked at and have studied in depth.
Having your expertise on board in that, to apply that to making the company more valuable, minimize dilution is off the charts. Welcome aboard, and look forward to a fun ride that we're going to have with the shareholders here.
Appreciate it. Charlie, I want to say thanks as well.
You coming on, again, you've been here since day one. You've been here through the transformation.
You coming on and assisting with TCDC and what many people once laughed about now the top hyperscalers want, especially the one that we're in deep talks with. With that being said, there's a number of milestones that we've achieved in 2026 and in 2025 and then, heck, I've been with the company, we started this back in its current, not in its current form, but back in May of 2020.
I've seen this company grow. We've had successes, we've had failures, but ultimately what we've done is we've created value and a lot of it.
Where we stand today is very exciting. We have some great news to announce before too terribly long that I think everyone's waiting for, rightfully so, especially myself, I know Charlie as well.
I think having Ted on board to be able to assist us in financing that at the SPV level is going to be massive, because again, I think the GP/LP structure has been quite unique in how we differentiate NUAI against other peer groups. They just don't exist.
Then of course, you layer on the fact of our ability to effectuate speed to power through our behind-the-meter is off the charts as well. Then of course, our strength through partnerships, it's just, it just lends credence of why we're succeeding, why we're going to be a phenomenal success story in this particular space.
Again, Ted, welcome aboard, and we definitely look forward to what you bring to the table, the value you're going to create. Obviously, looking at that, let's look at kind of what we've achieved thus far and touch on some of these things briefly.
Again, in January, I think what was most impactful was we had a great partner in Sharon AI, and congratulate Sharon AI and the team, James Manning and in what they accomplished as a neocloud. They had initially came on as our initial partner to facilitate Texas Critical Data Centers.
Ultimately, we kind of developed our pathway. James and his team developed their own pathway within Sharon AI, and again, great partnership and allowed us to facilitate our growth by essentially allowing us to purchase their 50% of the JV, giving us 100% of and full control of the project.
I think that was absolutely amazing. We look forward to kind of getting that funded, getting that closed out, and potentially working with James and Sharon AI in the future as a potential tenant.
That's something that, I think, we know what they're capable of. They know what we're capable of, and so that could be something of interest down the road.
Then I think some other important things that happened was, of course, Charlie was announced as President and COO. He was doing a lot of work on the board, a lot of time guiding myself, guiding the entire board on kind of how do we really effectuate this tremendous asset that we have in Ector County, Texas, that again, that exists next to two very powerful power plants.
Again, my thesis is the easiest place to build power is where it already exists, and that's what we've done. That's what we're doing.
The 438 acres plus the 54-acre corridor that we announced definitely some major milestones, and that was a very strategic acquisition that's going to be kind of laid out here before too terribly long so our shareholders kind of understand that energy corridor and why it's so imperative to how we look at Phase 1, Phase 2, and Phase 3 ultimately. Then I think, obviously been announcing the 450 megawatt behind-the-meter generation plan through some of our commercial arrangements, all the way through Thunderhead and TurbineX.
Look forward to working with those guys, because, at the end of the day, that's been instrumental working on the air permit. That should be submitted and approved here short order, because this thing is going.
We're ready to deliver, and second part of 2027 and go COD. I think one other major milestone that we've hit here obviously is bringing Ted on board.
I think he's had such a tremendous career, great success in raising billions for a number of our peer groups. I think having Ted on board and understanding what our GP/LP model looks like, how we look to effectuate maximum value through minimal dilution is going to be, again, something that's not been done before, and looking forward to proving that to the marketplace.
I think that's going to be really some of our next phase of growth and that is happening, and just appreciate everyone's patience to date and look forward to announcing some forthcoming news here shortly. Really, here looking at slide 16, some of the near-term operational priorities, and really want to just close in just being very clear about where we are and what should our investor base be watching for.
As a developer, listen, the ultimate priority is really kind of advancing our site control, development readiness. Listen, we've assembled the land.
The corridor is underway. We're actually working on the Phase 1, getting that ready to rock and roll.
The site work's underway. Despite all the naysayers, listen, we're executing.
I love it. I wish everyone can go out there and put boots on the ground, because obviously pictures don't do it justice.
Getting out there, seeing what we've done, seeing what we are doing, seeing what we will do is great. I think flipping through the slide deck, you see, I think what's really kind of really excited me as one of the co-founders and current Chairman and CEO of this company is what this data center is going to look like, this gigawatt site campus is what it's going to look like, it's amazing.
We're just focusing on the engineering and execution, really advancing the commercial discussions with our hyperscaler customer. I can say that, again, we've talked about this, and just to reiterate, we are in commercial negotiations with a leading hyperscale tenant.
We feel that there's four creditworthy hyperscalers, and we are dealing with one of those four. We believe our site characteristics, the power strategy, and of course our partner ecosystem really positions us as a very compelling story why that particular household name is in even talks with us.
Of course, I think the specific timing of a binding agreement is not something that we can 100% control. I think that's one thing we've all learned.
We're not going to set artificial deadlines, but we are going to do is essentially continue to advance every controllable milestone that positions this campus for our successful commercialization. Again, as a management, we're focused here on the project-level financing partnerships and continuing to build out the team and of course the capabilities, and that's really exactly what Ted's arrival represents.
It represents execution and that we're here, we're at the dance. With March Madness in play right now, we're here.
Not many people think we would get a seed, but we did. I think we're going to advance nicely as well.
I just want to kind of close with a thought about what NUAI is and why it exists. Again, it kind of goes back to the buildout of the AI infrastructure.
It's going to be one of the more defining infrastructure cycles of the coming decades. I think we all understand that the demand is real.
The power constraint is real, unfortunately, but the need for developers who can actually create power, deliver building hyperscale-ready capacity, it's just not cite theoretical megawatts. We call them kind of braggawatts.
It's cute, it's here. We're sitting on something that's real, that's tangible, and that will be subscribed to by our end tenant.
Again, we sit at the intersection of two industries that rarely overlap. Obviously, the energy infrastructure, again, of course, that's kind of our near and dear to our hearts, and of course what the digital infrastructure has brought.
No one operates in both worlds. That intersection, the ability to take a raw site in a energy corridor, which we've done, and convert it into a power campus that meets the most demanding technical specifications on Earth is our moat.
It's hard to do, and that's why we're valuable. We've done it.
We're doing it. If people can see that what I saw when I first stepped foot on that property well over a year ago, it was a vision I had that I knew would come to fruition.
We've done it. We've assembled the land.
We've assembled the power, the team, the partnerships. Now what we do is we just execute.
I just want to, from the bottom of my heart, say thank you. We've had so many people out there to tell us what we're doing wrong, what we're not doing, what we can't do, and I'm here to tell you, we're doing it.
It will get done. Just again, I thank you for your patience, for your loyalty, and we're going to open this up for questions.
Thank you again.
Lincoln Tan
Great. Obviously just conscious of time, we've seen quite a few questions come through the live webcast.
Many of them relate to similar topics, perhaps, Will, we just address a couple of those grouped by themes. I think some of the questions are around the cash position, liquidity, and how we're anticipating to fund working capital and growth.
Will?
Will Gray
Yeah. I think that's a good question.
Obviously, we ended the end of the year with about $1.2 million of cash on hand. Since that time, we've essentially gone out and kind of worked on some of those capital needs, short term.
Ideally, our G&A is relatively modest to the overall spend of what we're looking to do at TCDC, of course, taking into the GP/LP model. I think that's one thing bringing Ted on is better understanding the financial structures that are available to the company, whether that be some sort of senior convert, whether it's take some sort of a mezz piece, some sort of a credit facility.
Ideally, we have a lot of options to do that. Of course, we have some upcoming obligations that's due to Sharon AI at the end of the month, and we've got some different opportunities to fund those that are going to be quite meaningful to how we position the company moving forward financially.
Definitely, it's a great great question. Yeah.
I hope I answered that one, Lincoln.
Lincoln Tan
Thanks, Will. The other theme, obviously many, many of these questions come through, I know you sort of touched on it, just any more color, Will, on the hyperscaler tenant announcement.
Are we anticipating more hyperscaler tenants in the future? Who is the counterparty?
Questions of that nature.
Will Gray
I think I sit here and sympathize with all the shareholders because I get it. We all want to know.
You all want to know. We created that.
Like I said previously, there's four hyperscale, investment-grade companies that are out there. We are speaking with one of those, I don't anticipate us bringing any others into the mix.
At this stage, we are pretty far along. I think that's one thing I do want to share with investors is that we can control what we can control.
When you start looking at those four hyperscalers, some of the largest companies in the world, and unfortunately, they do not move as fast as we would like them to. Is it progressing?
Absolutely. Will it happen?
It will. It will happen.
I do feel there's going to be some news that we can announce forthcoming that would give some clarity. I think at this stage in the game, when we made the announcement of the lease option acquisition of the 54 acres, that was at the behest of the end tenant.
When you start to put the pieces of the puzzle together, it's going to make perfect sense on why that energy corridor will come into play with Texas Critical Data Centers. Again, I do sympathize and I do understand and recognize the need to disclose this as soon as possible because there's one thing that we are adhering to, and that is basically delivering data center on or before in Q3 of '27.
That is not being moved. That's a hard date that we have that we will meet.
With Charlie better rolling out his modularization of kind of the ATOM project, I think that's definitely helped us, because again, anyone can go out there and announce triple net lease and announce a hyperscaler. Again, I think what we all have to look at is also the delivery of the data center itself.
How do you execute? Because if not, there is no cash flow.
I think we're trying to handle all of these various nuances and craft it into one document, which again is very time-consuming, cuz again, this gigawatt-style era of data center campuses is new. We're creating documents that no one's seen before.
It has taken some additional time than we originally anticipated, but things are moving. That's the promising aspect of this, but when we're asked the question of are we talking to other hyperscalers, absolutely, because those are for our additional projects.
We're pretty well along, very far down the path with Texas Critical Data Center, and who do we anticipate getting in there and breaking dirt there. I do think I just appreciate everyone's patience, and again, it will be forthcoming, and again, just stay tuned, please.
Lincoln, how are we doing on time here?
Lincoln Tan
I think just conscious of time, Will, I think we're over the hour, it probably makes sense to wrap up.
Will Gray
Okay. I think I just want to just thank everyone for logging in today and listening.
I know that was a very lengthy presentation that was delivered by both myself, Charlie, and Ted. A lot of commercial data was shared today, both on kind of where we've been, where we are, where we're going.
I think at the end of the day, it starts with the execution and the deliverability of Phase 1, which is on TCDC, which is coming, which is speed to power in Q3 of '27. With that being said, we will be communicating additional items to the market to keep everyone up to speed.
Again, just like I said earlier, I cannot thank everyone enough for their patience, for their loyalty, and for their belief in what we're building, what we've built thus far. Again, just thank everyone, and look forward to providing additional updates here very soon.
Operator
This concludes today's conference call. Thank you for participating.
You may now disconnect.