Operator
Greetings. Welcome to the Tecogen third quarter 2026 conference call.
At this time, all participants are in a listen-only mode. A question and answer session will follow the formal presentation.
If anyone should require operator assistance during today's conference, please press star zero from your telephone keypad. Please note that this conference is being recorded.
At this time, I will now turn the conference over to Jack Whiting, General Counsel and Secretary. Thank you.
You may now begin your presentation.
Jack Whiting
Good morning. This is Jack Whiting, General Counsel and Secretary of Tecogen.
This call is being recorded and will be archived on our website at tecogen.com. The press release regarding our third quarter 2026 earnings and the presentation provided this morning are available in the investor section of our website.
I would like to direct your attention to our safe harbor statement included in our earnings press release and presentation. Various remarks that we make about the company's expectations, plans, and prospects constitute forward-looking statements for purposes of the safe harbor provision under the Private Securities Litigation Reform Act of 1995.
Actual results may differ materially from those indicated by forward-looking statements as a result of various factors, including those discussed in the company's most recent annual and quarterly reports on Forms 10-Q and 10-K under the caption Risk Factors, filed with the Securities and Exchange Commission and available in the investor section of our website under the heading SEC Filings. While we may elect to update forward-looking statements, we specifically disclaim any obligation to do so, you should not rely on any forward-looking statements as representing our views as of any future date.
During this call, we will refer to certain financial measures not prepared in accordance with generally accepted accounting principles or GAAP. Reconciliation of non-GAAP financial measures to the most directly comparable GAAP measures is provided in the press release regarding our Q3 2026 earnings and on our website.
I will now turn the call over to Abinand Rangesh, Tecogen's CEO, who will provide an overview of the third quarter 2026 activity and results, and Roger Deschenes, Tecogen's CFO, who will provide additional information regarding Q3 2026 financial results. Abinand?
Abinand Rangesh
Thank you, Jack. Welcome to Tecogen's Q3 2026 earnings call.
Today, I'm going to start with the base business, and then talk about where we stand with data centers and some of the larger projects. First, we saw a significant increase in revenue in the third quarter compared to the first and second quarters of this year.
We also saw an increase in revenue compared to the same period last year. The gross margin also increased by 7 percentage points compared to the same period last year, showing that our operational improvements, especially in service, are having an effect.
Our backlog is presently more than $8 million. As a reminder, this backlog does not include our recurring service contracts or our energy services.
As a result of strong deposit collection and the increase in revenue, our cash position is now higher than it was at the end of the third quarter. We are also expecting to collect more than 800,000 in the next week or two.
In 2024, we recognized that to increase product revenue, we needed to increase the average dollar value per project and build relationships with larger property owners. Successful initial projects would then lead to sales across the whole building portfolio, increasing sales efficiency.
We have worked diligently on this strategy alongside the data center outreach. I am pleased to say that this is finally coming to fruition.
More than 70% of our backlog is now with large property portfolio owners and with large energy services companies. Some of these owners have already started to look at more properties in their portfolio to incorporate our equipment.
Given the recent spikes in utility rates nationwide and increased power shortages, we are also seeing an influx of leads for projects in the $2 to $5 million range in industrial and healthcare segments. With regards to data centers, there are two categories of projects in our pipeline.
The first category is the smaller colocation data centers. Electric bills are a big portion of the operating expenses for these smaller data centers.
As you may you may have seen from our recent press release, one of our data center customers is saving significant amounts on their utility bills and is it is also giving them an edge against competitors. The projects in this pipeline are between 1 million and 5 million in size.
We believe these smaller projects have a high likelihood of closing. The timing here is really a function of expansion plans being approved.
The second category are the larger neocloud, hyperscale, and large colocation data centers. Since the summer demonstrations, the discussions have predominantly focused on how Tecogen can provide a pathway to scale up production output.
One of the challenges is that for bigger names to pilot and deploy any new technology, it needs to be deployable in volume quickly and hit aggressive delivery schedules. Given Tecogen's size, we needed a solution that allowed us to scale production quickly without large amounts of upfront capital and while if possible, increasing margins.
The good news though was that the hyperscalers and some of the larger data centers were excited enough about the dual power source technology that they wanted to see how it could be adapted for other applications within the data center, in addition to just cooling. As we explored how this option would work in practice, this led us to an innovation that is highly scalable and that we're excited to announce today.
We have designed a modular dual power source package that can be retrofitted to third-party chillers, dry coolers, and any other data center load. It has all the advantages of the dual power source chiller and is protected by the same patents, but is much easier to scale up production.
The supply chain is robust since we already buy much of the same material in volume for our service fleet and our InVerde units. This approach allows us to focus on the areas that the customer values and that make us unique compared to conventional power generation.
The first of course is the dual power source capability and the ability to blend power sources dynamically. This allows a customer to seamlessly switch to natural gas to maximize power for AI loads and to ride through power outages, increasing resiliency.
Our patented control algorithms optimize part-load efficiency. In many of these thermal applications in a data center, chillers and dry coolers may operate at part load for large periods of time.
Most conventional power generation systems see significant reductions in efficiency during part-load operation. Our system can keep constant efficiency through much of the power range.
The last area we have patents is in our emissions system. Most competing systems use consumables to maintain emissions.
Ours is a catalyst-based system that is easy to maintain while providing near-zero NOx, CO, and VOCs. This dual power source module includes integrated heat rejection, emissions control, and microgrid controls in a low-noise package from the factory, it can also command premium pricing because it requires very little on-site installation time.
As a result, we expect to maintain higher margins on this product and hence significantly reduce the need for incremental working capital as customer deposits can fund much more of the material costs. Last, focusing on the dual power source module means no specialized tooling or labor is needed beyond what we already use for the cogen production.
Therefore, adding additional factory capacity when we run out of space in our current site is straightforward. From the customer's standpoint, this is also an easy solution to approve internally, since they can use a chiller that is already on their drawings and add our package in parallel.
Because this solution is fully modular, it can be applied to any chiller size or any dry cooler size, it is fully adaptable to any future data center design, including the 800-volt architecture. This also means that if a data center has enough space, it could even be applied to a site that is already designed.
The dual power source option means that the system has redundancy built in. Of course, this is not just applicable to data centers.
Many of our existing customer base such as hospitals and campuses are very interested in this solution because it is fast to deploy. In In fact, one prospect has already specified this solution into their project.
The power-dense building block also allows us to now address bigger industrial facilities that have power draw similar to a medium-sized data center. These facilities have similar issues as data centers, where they would rather allocate scarce utility power to revenue-generating assets and cut operating costs at the same time.
Although I cannot comment today on when we will ship the first units to customers, almost all the underlying components are already operating in our dual power source chiller and our InVerde units today. We're working with our partners and end customers to find launch customers to deploy this solution.
I will update shareholders as I have more news. I will now hand over to Roger to discuss the financials.
Roger Deschenes
Thank you, Abinand, and good morning, everybody. Beginning with the results, our revenues for the the quarter that just concluded increased 9.6% to $7.9 million, which compares to $7.2 million in the third quarter of 2025.
This is due mainly to increased services segment revenue and increases in in our in our products and energy production segments revenues as well. Our gross profit increased $800,000, or 35.3%, to just under $3 million in the third quarter of 2026, which compares to $2.2 million in the third quarter of 2025.
This is due to the increased revenues and in the decreased material and labor costs in our services our services segment. Our gross margin increased 7% to 37.4% in the third quarter from 30.4% in the comparable period in 2025.
This is due largely to improved services segment gross margin. Our operating expenses increased 5.3% in the third quarter to 4.5 million from 4.3 million in the third quarter of 2025.
Which we saw increases in operating costs in our product segment and a general increase in operating costs incurred for payroll, stock-based compensation, credit losses, and and and depreciation and amortization, and costs incurred for the manufacturing capacity expansion along with the the costs that we incurred for the continued development and refinement of our dual source chiller and the design of a modular dual power source package that Abinand noted earlier in in his remarks, all of which are are continued costs or an investment in our data center strategy. As a consequence of our services segment head count reduction in the second quarter, we did see a reduction in our services segment opex in the third quarter of this year.
Our net loss decreased in the third quarter to 1.6 million from 2.1 million in the comparable period of 2025. This is again due to the increased services segment sales and gross margin and of which was offset partially by the increase in operating expenses.
Looking at the adjusted EBITDA, our adjusted EBITDA loss of one was 1.1 was 1 million in the third quarter, which is lower than when compared to the adjusted EBITDA loss of 1.7 million that was, incurred in the same period last last year, which is due to the increased, the services segment sales and gross margin. Again, this is partially offset by the increase in opex.
Moving into performance by segment, our products revenues, increased, slightly 2% to 3.1 million from $3 million in the comparable period of last year. This is due to increased chiller sales.
As we have discussed in the past, product revenue has a significant variability quarter to quarter. Products gross margin decreased to 27.1% in the third quarter from 36.8% in the, third quarter of 2025.
This is due to material cost increases incurred on our hybrid-drive air-cooled chillers, and additional costs incurred as we continue to realign the factory floor to increase efficiency and productivity. Now, as we increase, our shipment volume going forward, we would anticipate to see our material costs unit material costs, reduced going forward.
Our services revenue increased 13%, in the third quarter of 2026 to 4.5 million, which compares to 3.9 million in the third quarter of 2025. This is due to increased operating hours with our existing and existing service contracts and the Aegis-acquired contracts, as well as, price in general price increases.
Our services gross margin increased 17.3% to 42.6% in the third quarter of 2026, which compares to a gross margin or gross profit gross margin, of 25.3% in the same period of 2025. This is due to decreased labor and material costs.
This is most notably occurred in the Greater New York City area, and we've also seen improvements across the majority of our service centers in the most recent period. Our energy production revenues increased 42% in the third quarter of 2026 to $0.36 million from 0.26 million in this comparable period of 2025.
This is due to increased up time at certain energy production sites. The, energy production gross margins also increased during the period to 60.2% from 34.4% in the 2025 period.
This is due to decreased service maintenance costs incurred in the period. I will now hand the call over to Abinand for his closing remarks.
Abinand Rangesh
Thank you, Roger. First, our base business is picking up.
The product backlog is increasing. The cash cash position is flat or actually slightly higher since we last reported, and we're expecting to collect 800,000 in the next week or two.
The second is that our current product backlog has significant expansion potential because of the nature of the customers. Third, our services business is averaging more than 4.3 million per quarter so far this year, the recurring cash flow has increased year-on-year.
With regards to data centers, the solution we unveiled today wasn't developed in isolation. It was developed based on feedback and listening very closely to the needs of hyperscalers and some of the largest data center developers.
Right now, we have multiple options beyond just our current dual power source chiller. This gives data centers substantial flexibility on how they choose to deploy our our solution.
It allows us to also bridge where we are today in size versus some of the projects with minimal risk for a data center to try the solution. Existing reference designs can be used with minor modification with this solution.
It is also both future-proof and potentially retrofittable to operational sites. The route to ramp up production also uses a supply chain that is not constrained, and it solves two key problems given much of the recent AI data center backlash.
The first is the fuel cell-like emissions. We have continued to improve and tune our emissions technology.
See the image on the slide, near-zero NOx and very, very low CO. Multiple large data center power projects have faced moratoriums due to air quality concerns.
In our case, the customer can use gas strategically with very clean emissions. Second, as access to power has become more uncertain in the current climate, more data centers are interested in using every bit of available power at already approved sites.
I'll now Thank you for listening, and I'll open the floor for questions.
Operator
Thank you. We'll now be conducting the question and answer session.
If you'd like to ask a question at this time, please press star one on your telephone keypad, and a confirmation tone will indicate your line is in the question queue. You may press star two if you would like to remove your question from the queue.
For participants that are using speaker equipment, it may be necessary to pick up your handset before pressing the star keys. Thank you.
One moment, please, for our first question. Thank you.
Our first question is from the line of Eric Stine with Craig-Hallum. Please proceed with your questions.
Eric Stine
Hi, Abinand. Hi, Roger.
Abinand Rangesh
Hey, Eric.
Roger Deschenes
Morning, Eric.
Eric Stine
Hey, good morning. Good morning.
I want to just start with this, your new technology, the dual power source modules. When we think about capacity, obviously mix dependent and obviously you laid out the two categories of data center, opportunities that you're going after, but is there or is it too early to think about or or what would it be if you allocated that entire facility to these modules?
Abinand Rangesh
It's a little early, but we've been asked some of that question, and it really depends on how you think about it, right? If you it but I would say just from a, output standpoint, it'll be more than 2x of what we could do in terms of the chiller numbers.
That kind of hopefully gives you a a number in terms of I would say we could when we were talking about the chillers, right, we were saying something like a 100 units or so of chillers. This would basically double that easily, and adding additional capacity is also much, much more capable on this.
As I said earlier in the call, part of the reason also with this is to add additional If we needed to just say if we get a multiple unit, data center order or let's say a customer wants to expand onto multiple sites, for us to add additional assembly areas for this would really just require renting out additional factory capacity. A lot of the supply chain, a lot of what we already do, it's it's, much, much more scalable.
It's it's It is mix dependent, but we think the potential and especially when you include the the margin expansion that can come with this, it can fundamentally change the business.
Eric Stine
Yep. No, absolutely.
Then thinking about, obviously you're you've been in active discussions with, some of your, customer prospects, and you mentioned that, maybe it it it speeds things up a little bit. What, do you have an idea of what a potential customer might need to see in terms of of testing this?
I I know it's a it's I guess maybe simpler. I would assume they would still need to run these for a period of time to get comfortable before rolling them out more broadly.
Abinand Rangesh
Yes, I definitely agree with that. I think part of the advantages, many of them have come and now seen the dual power source chiller technology, right?
I think the way they're Well, and some a lot of this unfortunately is, there's a lot of confidential pieces here, I cannot talk specifics. What I can say is the way they're viewing this is, okay, how do I design in the potential for this further down, right?
What they'll do at this point is they'll evaluate this as a cost-benefit in terms of how much IT capacity gets added in. Then they would potentially do a smaller pilot.
I don't know how big that would be, but concurrently, they would basically, start designing in into bigger data centers the extra space and all the the pieces that would be required to connect this up. To a certain extent, this module didn't just come out of nowhere, right?
It it came with the discussions with what they're trying to do here, and also what they feel they can get approved the fastest way through. The advantage here is they don't need to change any of their thermal design, and that's why we think it can happen, a lot of things can happen in parallel paths here.
Again, the timing is pretty hard to determine based on on on this, because a lot of things typically happen in parallel in these kind of discussions.
Eric Stine
Yep. No.
I get that. All right.
Maybe last one for me. Just how do we think about this, in the context of the Vertiv relationship?
I know that, last call you talked about getting close on the master, partnership agreement. You haven't really mentioned Vertiv on this call.
Is this is should we think of Vertiv is still an active partner here? Is this outside of that or just maybe thoughts on that?
Abinand Rangesh
All I'm going to say on this one for the moment is stay tuned. I can't comment further on it at this juncture, on the Vertiv stuff, but things are in a great place.
Just stay tuned is all I'll say on that one.
Eric Stine
Okay. I'll leave it there.
Thank you.
Operator
The next questions are from the line of Bobby Brooks with Northland Capital. Please proceed with your questions.
Bobby Brooks
Hey, good morning, team, and thank you for taking my question. What I wanted to dig a little bit deeper on is just like understanding how this, modular retrofit potential retrofit solution is quicker to scale production versus, the your, legacy dual source chiller, cuz I thought the dual source chiller was also relatively easy to scale up production.
Just just kind of wanted to understand the nuances that make this, it seems like this is the a lot easier to scale. Just trying to get a sense on that.
Abinand Rangesh
Yeah. There are two pieces to this, right?
The first fundamental thing is the what with the dual power source module, the bit that we're really providing to the customer is all the the power control, the engine, the emissions in a single box. With the chiller, you're providing that plus all the refrigeration assembly.
Here you've essentially are able to drop this on-site with just the box, and connect it to a chiller the customer already says they're happy with. It's a little more nuanced than that, but that's kind of in a very simple way, that's kind of how it works.
The advantage that we have in today's climate with the with the dual set power source box is kind of the engines that we have, we there is a we already buy a lot of those engines in volume. One, we're already getting volume pricing, and number two, the the supply chain associated with the engines that we buy right now is very easy to scale up, because you can get a lot of those engines.
Some of the larger, one frees up It It uses a portion of the supply chain that isn't constrained today. That, one, increases our odds that a data center will actually do this, because they can get supplies very quickly.
We know that downstream, the supply of all of the components that we use on the product is is available. The, the second piece is just space.
When you're dealing with a bigger chiller, right, you're having to maneuver a much larger piece of equipment here, whereas with the dual power source piece, you're only doing the power module, which means just from a factory space and layout standpoint, you can get a lot more units through the floor. The two put together allows you to scale up production much, much faster.
It's also this us being able to even show our prospects, look, we know, and we can show you with the supply chain further upstream that all of these components are, available, and therefore we can deliver these on time with enough volume. It's really also being able to show our end customer that will increase the odds that these orders will come through.
Bobby Brooks
That's super helpful detail. I appreciate it, Abinand.
Then just on your, on the the dual source chillers, the STX, DTX, right, it was I know it's it can provide I think the STX is 200 tons of cooling, the DTX is 400 tons of cooling. I know it's probably not an apples-to-apples comparison with this new, module rolled out today, but could you maybe just help us sense like what one of these modules can provide in terms of like technical, aspects to a data center on like the power usage or the cooling capacity or however might we however might we should look at it?
Abinand Rangesh
That's again a that's a phenomenal question, Bobby, and I I that actually is the other reason we did this, because a lot of the data center design today that's on the on the things may use a, a 600 or 800 or even a 900-ton chiller. With this power module, we could power a 600 or a 900-ton chiller without having to build a chiller that can do all the refrigeration design for that bigger chiller.
We can actually power something that's already on on the spec right now. What We could So what this the the really unique thing about this is it we could It's It Think of it almost like building blocks, right?
You could use What we have in our current dual power source chiller would have, two of the building blocks to power a a 300-ton chiller. In this case, we what we're doing is we're stacking the building blocks together so that whatever the customer is using on-site, the building blocks just get bigger, and you could power a 900-ton chiller with just a bigger box.
It's In that sense, that's what makes it very, very unique. You can just say, okay, if the customer is using a 300-ton chiller, use two of our little building blocks in one package.
If the customer is using a 600-ton, you'd use four of the little building blocks to make the the package. That that same way, you could do the same thing for other thermal loads like a dry cooler.
If a customer turns around and says, I want to have a, I'm going to use a lot more of the big fans and the other systems that we have in the data center, you do exactly the same. You would just power the same thing with that with that same package.
It's very, very adaptable to whatever they want to run on on-site.
Bobby Brooks
That's really interesting to hear and super helpful color. I'll I'll return to the queue.
Thank you, Abinand.
Operator
Our next question is from the line of Alex Blanton with Clear Harbor Asset Management. Please proceed with your questions.
Alex Blanton
Oh, good morning. Sounds like making Good morning, Alex.
good progress. I I have a question about the supply of natural gas to these sites.
Are there any developments among the hyperscalers that would help you do business with them in terms of their bringing in natural gas for other purposes that could be used by your equipment were to be adopted?
Abinand Rangesh
Definitely. There are two categories that we're seeing.
There are people that are going to do on-site power generation anyway where they're bringing in, big transmission line level natural gas. In those cases, we have multiple things that we can do for them.
One is, allow them to keep their big power gen equipment for the IT capacity, and so that they don't waste it on on the cooling. Our equipment can help help over there.
There are other cases where the site may not be planning on doing any power generation, and let's say, for example, they have 100 megawatts of, utility power available. What In those cases, you can still get you don't need a transmission-level amount of gas available to do what we're suggesting here, because you would just use this to trim as much You could get distribution-level gas that you would find in any industrial facility or any, most urban environments.
You could use that to really just shave at the peak time, especially at the very, very peak of summer, where the utility is the most constrained. The one, if you can shed load quicker when the utility asks you to, they're more likely to give you whatever utility power you're asking for on the electric side.
Number two, it also allows you to basically take every bit of electric utility power you have, and use it for the chips. That's a slightly different use case, but both of these are available.
The second case is much easier to really maximize, right? You don't need to think about, can I get a pipeline-level gas supply to the site?
You only need distribution-level gas to be able to do this.
Alex Blanton
Thank you. Is, Elon Musk sites moving to natural gas that you know of and would you be involved in in any of their work?
Abinand Rangesh
I cannot comment on any specific customers or any specific things at this point, right? Pretty much everybody that we're talking to, we have confidentiality agreements with.
On a more general case, right, we're seeing a lot of the bigger data centers looking to do on-site power generation, whether they do turbines or so on. In those cases, we can definitely support however it works, whether they whether it's with turbine cooling, direct the cooling equipment, dry coolers.
We are seeing quite a bit of a shift to power generation happening on-site. That's happening at the hyperscaler level as well as the the smaller entities.
Alex Blanton
When you say dry cooling, what do you really mean?
Abinand Rangesh
Some data centers, especially, what they would do is they they take the the liquid cooling that's required for the chips, and they basically just use a big fan. They may use a chiller for only a portion of the time, especially in the cooler climate, sometimes they'll just use a big fan and they'll just let it run, as hot as they can.
There's a few data centers that do it. There's very few, that are actually in practice doing it.
They may have a com-, both fans just, on cooler conditions, they might just send the water through a big fan and blow, reject it to the atmosphere, not turn on the air conditioning. They they they might have that running for a lot of the year, and then turn on the mechanical chillers and so on just for the summer, the very peak.
They might have a combination of both. Those loads are still pretty large because you're talking, massive sites here.
For a data center, that could still Just the fans alone could represent, 5, 10% of the of 100-megawatt load, right? It can be it can be a large chunk of the overall power need of a data center.
Alex Blanton
I'm going to just switch topics a little bit. As there's tremendous, pushback against data centers that became an election issue during the recent election.
Do you see any indication that that could be, that those that pushback could be lessening after the election as political needs the need to politicize diminish? Do you see any indication that any projects that you've been working with have been delayed or canceled because of this, of the, NIMBY objections to data centers in people's communities around the country?
Abinand Rangesh
There I'll address that in two ways. The first one is the our just general size compared to the overall market, right, that that we have.
We don't need to win at the same scale as somebody else to really have an impact on our financials. The other piece is that our equipment can be deployed on sites that are already approved.
We're starting to see a lot more interest from people saying, "We don't know if these big gigawatt-scale power purely on-site power generation projects are necessarily going to get approved, but we have hundreds of sites that might have 20 megawatts, 50 megawatts, that there is utility power. If we can take as much of that utility power and apply it to IT, that all adds up when you look at across the whole country."
For us, actually, it doesn't matter how the politics play out. I think we have enough opportunities of different sizes that, and in particular, the ones where they have some utility power and we can help them get maximize that, that's something that's very unique, right?
If you if you're going to do power generation, it's a much more involved process. Here a customer puts this in, they can use as much gas as they like or not, and they just switch dynamically.
If the utility turns around and says, "I'm not going to give you enough, or I need you to curtail power in peak time," you can do so, and you can still not have to turn down your computing on-site. That's the play that we see it being.
I it's the bigger politics is a little too hard right now to to gauge. We're work We're looking across the board as at enough opportunities that we don't think it's going to be an impact that we need to worry about at our scale.
Alex Blanton
Yes. Given the fact that the, corporations using AI keep expanding their applications in their use, the demand for compute should keep going.
It does not look like the current anti-data-center sentiment in the country, politically, will will really restrict your growth. Is that correct?
Abinand Rangesh
That is correct. Yeah.
The demand is there, right? They're going to find ways to do this that may not involve single large campuses.
Like they The The market could go either direction and either Like, we're seeing people look at a bunch of smaller sites that would then, in aggregate, turn around and become the would provide the amount of AI compute. Es- Especially as more and more is moving towards inference and so on, where it's the end application rather than training, there's many more ways that our products, especially at the size ranges that we're in, can do so.
It It The market, I think, is is definitely much, much we're not going to be constrained on in terms of what's happening in the broader market. To a certain extent, that's also why we're looking at this modular dual power source approach, because it gives us a lot of flexibility also in terms of the size and the design of the data center.
Like, you could If it's a small site, you could either put our current chiller as is or use our power modules. If it's a much larger site, whatever is on the reference design plus the power module gets us to the same goal.
Alex Blanton
Thank you very much. I'll get back in the queue.
Abinand Rangesh
Thank you, Alex.
Operator
Our next question is from the line of Barry Haimes with Sage Asset Management. Please proceed with your questions.
Barry Haimes
Thanks for taking my question. Could you talk a little bit more about the, the smaller colo market, that the first, segment that you mentioned, and just give us a little feel?
I saw you saw the press release, of course, you put out with the one who, I think it was in Connecticut, who was using, your unit quite successfully. What is the backlog, the, the the pipeline look like there?
Are there any discussions that are, are pretty far along where, we we might expect to see some orders, over the next month or
Abinand Rangesh
order and when we expect orders to close on that, again, for confidentiality reasons. What I can say is there multiple projects, some, everything from one or two InVerdes to multiple chillers to some that are as large as like, 15, 20 megawatts, right, in size.
They're at various stages. Some of them are operational data centers that are expanding their capacity, and they're just waiting on additional tenants to sign so they can increase the load on-site, and hence they might add more pieces of equipment.
There are some that have existing sites that they they're in final negotiations with tenants. They would need to build a data center on-site, but as soon as they typically get the tenants, they're able to start placing, equipment orders.
They're they're things of different sizes in that range. Then we're also seeing, new, opportunities there where our sales team is going out and finding other sites where, again, they're operational data centers.
They might be doing just cloud-based, colo type things where utility bills, especially in the Northeast and, and so on, are very high, where adding some, small scale either power generation or our cooling can make a big difference to their, energy bills.
Barry Haimes
Great, thank you. Best of luck.
Abinand Rangesh
Thank you, Barry.
Operator
The next question is from the line of Robert Collins, private investor. Please proceed with your questions.
Mr. Collins, your line is live for questions.
Robert Collins
Yes, thank you. Good morning.
Two parts or two different questions. One is on the Vertiv.
I appreciate that you can't comment on anything going forward, but, wouldn't it be appropriate to be able to comment on the things that have happened during this quarter? That would be the first question.
Abinand Rangesh
Again, I'm covered by confidentiality agreements on that. I cannot comment right now on that.
Robert Collins
Okay. Thank you.
Then the second question kind of comes back to what has been kind of suggested, but that is the the political environment seems to be and the and the general environment seems to be much more concerned about people, about the amount of power these AI centers are using. I think we can expect that the new administration is tends to be more regulated oriented.
Wouldn't that create even greater opportunities for alternate power, i.e., natural gas? Then the opportunities that natural gas fits in with with the Tecogen strategy?
Abinand Rangesh
Yes. The natural gas side of things, right, there's two sides to that, argument.
When you do the very large power generation projects, there's a lot of There's still quite a lot of pushback from, local constituents because of the fact that the emissions, all of those other pieces. In particular, when you're having to do those power generation projects, the utility is still having to support it.
That's where I think we come in, because there are two things that we bring to the table. One is the very, very clean emissions.
Right, so that allows you to mitigate much of that air quality issue. Number two, you don't actually you don't have to even use natural gas all the time, because it really The utility grid is constrained for periods of time, but for a lot of the year, it does actually have capacity.
If you can avoid the peak time, many of these sites can actually have sufficient capacity without having to make substantial upgrades to the utility. That, again, is where this dual power source and the ability to act in a hybrid fashion, you choose when to use natural gas, when to use electric when there's sufficient.
You can You can do that on the fly without having to shut down and switch. The third piece, which is actually very unique to this approach, is we in many cases, because you're powering a thermal load direct through this box, essentially, you have you avoid a lot of the utility hassles that you would need to actually deploy this.
If you were doing conventional power generation, you'd have to get utility interconnects, you'd have to go through a lot of this. Here, you're essentially isolating a load and avoiding some of that utility requirements that you would you would need.
There there's multiple ways that our solutions impact this. The potential is there, right?
I think right now what we're really focused on is how do we provide a pathway to get from here to actually getting these projects to close? A lot of that is where we see this power module as a way to scale up output so that we can provide enough power for these data centers that would then get us to that next next stage.
Robert Collins
Thank you.
Operator
The next question is from the line of Chip Moore with Roth MKM. Please proceed with your questions.
Chip Moore
Hey, good morning. Thanks.
Hey, Chip. apologies if I missed the start of the call if Hey, Abinand.
If it's if if you've covered any of this already, just curious on, the retrofit opportunity, and your comments, it would it would seem, that your value proposition is only increasing, with some of the, political dynamics out there. Just just curious, how how much of this has been developed sort of in tandem with, the discussions you've had ongoing, how much can you leverage, the work you've already done around that, and how should we think about, potential first, proof points on that side?
Would would this be sort of a a demonstration-type, rollout at a at a smaller facility or or what's the what's the scale of of the conversations?
Abinand Rangesh
We can pretty much use all of the existing discussions as the this actually allows us to accelerate some of this, right, because it it means that an existing site or something that's in design today could have this incorporated. It, it doesn't require you to design around the full chiller.
That's number one. Number two, in terms of the the initial pilot or sites where this might go, I can't comment on it right at this point.
There are multiple places both data center and non-data-center that we're pursuing right now for that. Stay tuned on on that.
We'll We'll do our best to provide interim updates to shareholders on this.
Chip Moore
Fair enough, fair enough. We'll look forward to that.
On and on the non-data-center side, this sort of uptick you're seeing, it feels like it's it's got some legs to it. Just expand on on that and, the ability, I think you talked about, for some larger business to come in through some of these larger, type of type of clients.
What are you seeing on that side?
Abinand Rangesh
A large one with this political environment, people are looking to see how they can leverage every bit of available power on existing sites, right? Sites that have already been approved that have less risk of having them shut down because they can't scale up or if they can't get it into construction, right?
Those are places where we're starting to see a bunch of new leads. The A lot of this is really coming down In terms of getting these projects and actually securing the projects, it's coming down to how much capacity can you deliver quickly within a period of time.
That's what's going to drive those orders to close. This approach allows us to really go back down to the every piece of our supply chain and show the end customers that we can actually deliver these in volume in aggressive timescales.
That's what's going to get those things these orders to close. That's really what we're working on right now, because the good thing with the summer demonstrations was it allowed us to build some pretty strong relationships with a lot of these these sites, and they've been very open in their feedback as to what they need to be able to see from us to give us orders.
This is kind of a little bit of a dynamic process. Without getting into specifics, that's as much as I can say for the moment.
Chip Moore
Thanks. Maybe just a last one, Abinand, the the, on the service side, the margins, very nice this quarter, could could to see do you think you're past some of the challenges you've had there and and any update there?
Thanks.
Abinand Rangesh
Consistently this year, we've been running, the revenue has gone up, right? Some of the investments we made last year seem to be working.
Far, three quarters in, we've still been, mid-fours. Typically, the two summer quarters have lower service revenue just because of less thermal load.
Last year, same period, right, we were 13% lower for in terms of service revenue. Some of that margin expansion is just as a function of just more runtime.
I think we're seeing things looking good so far, but we'll see how next quarter and the quarter after, and we'll make refinements as needed. It seems like, so far, three quarters in a row, we've been running over 4 million in in revenue on the service side.
Chip Moore
Great. Thanks very much.
Abinand Rangesh
Okay. Thanks, Chip.
Operator
The next question is from the line of Maj Sheddan with GEO Investing. Please proceed with your questions.
Maj Sheddan
Thank you. Hey, Abinand.
I Thanks for taking my call. Hey, Maj.
A base base-related question on the on the service. Maybe maybe I missed it.
Maybe you answered it earlier. Some of these new projects that you're talking about in your press release and your earnings call here, $2 to $5 million worth, or maybe 1 to 5 million, you said maybe imminent, are those also going to have a component of service revenue to them?
I'm just curious to understand if most of this project revenue that you'll be potentially getting over time, is there potential where you have that that 10 to 20% service revenue that we, expect to get from those things, or that And a and a and on a related note, on the new kind of retrofit kind of, offering you're talking about deploying here, potentially, is there a service component related to that at all?
Abinand Rangesh
Yeah. Great questions, Maj.
First, our current backlog, right, our product backlog, which is over 8 million, a lot of that actually is chillers and so on, and they're going into industrial, hospital, commercial buildings. They're they're definitely service revenue associated with that, similar to, every unit that goes into the field from that product side will increase service revenue.
In particular, chillers are great from a service standpoint because we offer 24/7 service on that, and that allows us to charge a premium for that for that as a result. Definitely a service component associated with that.
Everything that we're selling right now, again, will have a service component to it. This power module and so on will Again, how you would treat the service on that would be very similar to the chiller.
Because, again, we're providing this all the core portions that we add value on would would come in there, it would be similar type to what we would do on our our current chillers. Does that answer your question there, Maj, or
Maj Sheddan
It's yeah. It It's Yeah, it's perfect, perfect.
I guess I'm trying to figure out like when when you first start talking about the data center, potential maybe maybe two years ago, maybe, you kind of hinted at it. The a lot of the narrative was focused around like that that's the direction you got to go to build this company to something as a p- public company.
You really didn't have that much kind of, I guess, expectations for the legacy business. Now you're seeing the the legacy business starting to guess get a little better here.
I guess my first question really is, with given your cash position, and I I think part of what you were saying back in the day was that you wanted to put all your, CapEx and cash towards, all in your sales efforts all towards growing the data center business. With your current cash position, c- can you grow both, Now that you have the legacy stuff coming, growing again to some degree, can you you have enough capital to to get both going at the same time?
I'll have a I'll have a follow-up question on the service revenue after you answer this one.
Abinand Rangesh
Yeah. That is a great question on that.
What part of the reason that we're looking at this from the this module basis is if we can get If we if we basically focus on the pieces that we add the highest value on, we can expand margins, because the supply chain is already robust. As we grow the supply chain as we grow volume on it, we should be able to get even better pricing on it.
The more and some of that we're already turning because of the the service business. The the same components are being used, the turns will be faster.
When you have faster turns, the amount of incremental working capital you need goes way down, because we collect customer deposits. We collect pretty substantial customer deposits on each sale that we make.
The cash flow position gets way better if you can expand the margins on this. The other piece that we're finding is even two or three years ago, majority of our sales were based on just pure economic savings.
What's happening today, both through a combination of online marketing as well as just people facing power constraints, is that we're seeing a lot of larger facilities coming to us and saying, "We don't have enough power." This package that we have can be used for both the larger base business type projects, as well as the data centers.
It's pretty much the same problem. Therefore, it's not necessarily either/or.
Both could have the same same requirements, right? You're not necessarily having to spend huge amounts of marketing dollars being spread in both directions.
What we're We've done to a certain extent is split the sales team a little bit to focus on some of the legacy business, as well as the data centers. A lot of it's also now coming in.
A lot of what we've put in to the market over the last two years and continue to do it is generating a lot of in- inbound leads. We think being able to address some of the larger facilities with this module, as well, can can help us grow the dollar value per sale.
Maj Sheddan
Perfect. Thanks for I like it's made it still a little easier to understand, perfect.
I I still have a question related to all this. Look, I think that, there's there's two things here: do you have proven technology that can work out there that people, that could solve the problems that we're talking about here?
That's That's one thing. It's kind of established in your legacy business over the years.
One of the things you talked about like, who wants to be the first one, in the data center business to use your technology, right, or or or use your solution? That's maybe some of the I'm assuming some of the kind of challenge you've kind of faced here.
Obviously, Vertiv leaves you guys to some degree, but that hasn't panned out yet. I have now a bunch more questions coming here.
I'm sorry. As I'm talking here, but so the first thing really here is like as you're doing deploying this this this this modular solution, are you going to run into this the same, okay, who's going to be the who wants to be the first to take it?
Or do you think it'll be an easier deployment? Then I I still have a couple more questions after you answer this.
Abinand Rangesh
The first portion of who is going to be first, actually, one of the reasons we put that press release out earlier was to actually show that this thing is working in a data center environment, and it's working very, very well, right? To a large extent, the bridge between that and this modular solution is very easy because it is both the the chiller as well as the InVerde, they're all based on the same underlying technology.
Having that data center being able to point to it, you've actually, based on Again, not getting into specifics, it seems to be easing some of that angst from end customers about where is this operating in a data center. Today, a lot of that conversation is, "This is great.
Show me you can scale it." Because for us to actually go through the piloting process internally, we want to know that you can deliver enough volume over the course of the next two or three years, that it's meaningful in terms of the amount of power freed up in a data center.
I'm not saying that the the initial technology risk problem is gone away, but it's reduced substantially by having this even the single site. We have a couple of others that are actually that do power data center loads operational right now.
Being able to point to those and show data from that is actually quite has been quite helpful so far.
Maj Sheddan
Okay. Does this have any relevance to your relationship with Vertiv?
Does that Does this new product offering also kind of bring Vertiv into the mix to help to to to bring them into this product offering? Or or is it totally separate?
If it's not, can you can you kind of make it part of the conversation to to include as a as as a supporter what they might actually want to push out there? Or they could could they use it in their own, take that the their their own, product set to just to sell it as their own, private label it?
Abinand Rangesh
All I'm going to say on this one, again, is stay tuned. Just we'll announce what we can when we can here.
Maj Sheddan
Okay. Okay.
Great, great. I guess finally, like you know your your service revenue, you you're right about like you said, about $4 million here, right?
That's what kind of you're running. I I'm assuming the sooner you get that up, it would be it'd be nice to be able to tell us, "Hey," you can tell investors that, you've got to a situation where you can break even just on service revenue and not have to worry about the the volatility in you know in the product revenue.
I'm just wondering just throwing that I I don't know if that's possible, in a in a relatively shorter period of time. I think that's an interesting goal kind of to like to, aim for.
Abinand Rangesh
We're running this quarter, we ran 4.5, right, on service. We ran, 4.6 million on the first quarter, I believe, and then 4.
3, I believe, in the Run We run 4 and 1/2. Yeah, 4 and 1/2 this quarter.
We're running substantially higher than we were last year and the year before. The service is definitely growing.
Maj Sheddan
You probably want to be you you you probably want to be about three about you probably want to be about $7-8 million, I'm assuming, to get to the break-even kind of conversation, any of the conversations, right? That's I guess that's what you talked about in the past.
Maybe it's a little higher now because you've got some more things going. I'm figuring you need you need to double the service revenue probably to start getting comfortable with saying that, you can break-even is around the corner, just based on that part of it.
Abinand Rangesh
Yeah. There there there's different pathways there, right?
I think this is a that's The service revenue is going to make bigger and bigger components of our, it's going to cover a larger chunk of our cost. It's It's growing.
Exactly where that number stands, and I think we're not in a position right now to comment on what that number would look like today. I think the pathway to profitability is getting closer, especially if we can get a few a couple of these additional projects, in addition to the base business, the break-even point point lowers substantially, right, because the the base product business, the backlog is relatively solid.
It's going to increase. We do think that it is lumpy, but as long as we can see two or three quarters out, we it gives us some level of managing the cash flow there.
Maj Sheddan
Right. Okay.
I guess if you sell more of the modular stuff, that the break-even comes down, right, because there's less costs associated with that, right? That can get you to break-even faster than
Abinand Rangesh
That is the goal.
Maj Sheddan
maybe. Yeah.
Yeah. Okay.
Abinand Rangesh
That is the goal. That is the goal.
Maj Sheddan
All right. Thanks, Abinand.
Thank you.
Abinand Rangesh
Thank you, Maj.
Operator
Final questions from the line of Bobby Brooks with Northland Capital. Please proceed with your questions.
Bobby Brooks
Hey, I had tried to lower my hand. I'll just ask it on the call back.
Abinand Rangesh
Sounds good. Thank you, Bobby.
Operator
Thank you. I will now turn the floor back to management for closing remarks.
Abinand Rangesh
Thank you all for listening to our Q3 2026 earnings call. We will update investors as things happen here.
Part of the there's a number of confidential discussions happening presently, which is why, we we may not provide as many announcements as people may necessarily want, but as anything substantial happens, we will we will definitely try to keep people updated between now and the next reporting period. Thank you.
Operator
This now concludes our teleconference. You may disconnect your lines at this time, and we thank you for your participation.
Have a wonderful day.